Loading...
Westside Interceptor Project - Schedule 3 Bid Results & Tabulation5/9/2018 QUESTCDN: Project Bid Results Previous Next Close Window Print Results Project Bid Results SCHEDULE 3 - WESTSIDE INTERCEPTOR PROJECT (Quest project #5670951) Owner: City of Kalispell, MT 201 1st Avenue East Kalispell, MT 59901 ph: 406-758-7727 contact: Keith Haskins e-mail: khaskins@kalispell.com Soliciting agent: Robert Peccia & Associates - Kalispell, MT Contact: Robert Peccia and Associates Phone: 406-752-5025 E-mail: iwargo@rpa-kal.com Bid Date: 04/26/2018 02:30 PM MDT Owner Project Number: CITY OF KALISPELL Award Date: Comments: Award Status: Pending Bid Result/Award (no information presently available) Information: Letting Bid Tabulation: view Company/Contact Sandry Construction Chuck Pisk S & L Underground, Inc Shem Johnson Phone/E-mail 406-752-2419 chuck@sandryconstruction.com 208-267-7996 admire@slunder.com Amount Awarded $2,985,000.00 $3,397,933.00 https://www.questcdn.com/questcdn/projects/prj_view/project_view. html?&projbrowse=true&jobNo=5670951 &rowld=5670951 &projType=project 1 /1 <b>SCHEDULE 3</b> - WESTSIDE INTERCEPTOR PROJECT (#567095 1) Owner: <b>City of Kalispell, MT</b> Solicitor: <b>Robert Peccia &Associates</b> -Kalispell, MT 04/26/2018 02:30 PM MDT Sandry Construction S & L Underground, Inc. Section Til Line Item Item I Code I Item Description UofM Quantity Unit Price Extension Unit Price Extension Base Bid Section -Required Completion $219851000.00 $313971933.00 1 1 Mobilization, Bonding and Submittals (5% Max) LS 1 $1311551.00 $1311551.00 $1701000.00 $1701000.00 2 2 Construction Surveys LS 1 $141870.00 $141870.00 $351000.00 $351000.00 3 3 Material Testing LS 1 $121190.00 $121190.00 $351000.00 $351000.00 4 4 Traffic Control -Devices DAY 180 $245.00 $441100.00 $250.00 $451000.00 5 5 Traffic Control - Flaggers DAY 30 $11145.00 $341350.00 $11200.00 $361000.00 6 6 Asphalt Surfacing Removal SY 800 $10.00 $81000.00 $12.00 $91600.00 7 7 Concrete Flatwork Removal SY 1070 $12.00 $121840.00 $12.00 $121840.00 8 8 Concrete Curb Removal LF 365 $10.00 $31650.00 $8.00 $21920.00 9 9 Miscellaneous Work LS 1 $251090.00 $251090.00 $151000.00 $151000.00 10 10 Fence Removal &Replacement LF 384 $26.00 $91984.00 $25.00 $91600.00 11 11 Temporary Fence -Install and Remove LF 250 $9.00 $21250.00 $12.00 $31000.00 12 12 Dewatering LS 1 $1421290.00 $1421290.00 $3841560.00 $3841560.00 13 13 Erosion Control & Stormwater Permitting LS 1 $221830.00 $221830.00 $501000.00 $501000.00 14 14 Manhole - 48" Sanitary Sewer (Type 1 -Flat Top) EA 1 $41597.00 $41597.00 $61500.00 $61500.00 15 15 Manhole - 48" Sanitary Sewer (Type 2 -Eccentric) EA 4 $51032.00 $201128.00 $71500.00 $301000.00 16 16 Manhole - 60" Sanitary Sewer (Type 2 -Eccentric) EA 3 $71169.00 $211507.00 $91500.00 $281500.00 17 17 Manhole - 72" Sanitary Sewer (Type 2 -Eccentric) EA 1 $91800.00 $91800.00 $131000.00 $131000.00 18 18 Manhole - 72" Sanitary Sewer (Type 3 -Eccentric, Interior Drop) EA 1 $111620.00 $111620.00 $151000.00 $151000.00 19 19 Pipe -Buried: 8" Sanitary Sewer Main (ASTM D3034 - SDR 35) LF 418 $74.00 $301932.00 $110.00 $451980.00 20 20 Pipe -Buried: 12" Sanitary Sewer Main (ASTM D3034 - SDR 35) LF 42 $106.00 $41452.00 $125.00 $51250.00 21 21 Pipe -Buried: 18" Sanitary Sewer Main (ASTM F679 - PS 46) LF 21 $194.00 $41074.00 $132.00 $21772.00 22 22 Pipe -Buried: 27" Sanitary Sewer Main (ASTM F679 - PS 46) LF 342 $138.00 $471196.00 $145.00 $491590.00 231 23 Pipe -Buried: 30" Sanitary Sewer Main (ASTM F679 - PS 46) LF 1 6 $334.00 $21004.00 $165.00 $990.00 24 24 Bore &Jack Casing - 48" Steel Pipe (0.50" Minimum Thickness) LF 340 $11300.00 $4421000.00 $11452.00 $4931680.00 25 25 Casing Carrier Pipe - 27" Sanitary Sewer Main (ASTM F679 - PS 46) LF 340 $124.00 $421160.00 $135.00 $451900.00 26 26 Pipe Anchor - 27" Sanitary Sewer Main EA 5 $11033.00 $51165.00 $650.00 $31250.00 27 27 Existing Sanitary Sewer Main Connection EA 1 $31836.00 $31836.00 $121000.00 $121000.00 28 28 Pipe -Buried: Dual 12" Sanitary Sewer Force Mains (PVC C900, DR 18) LF 2872 $87.00 $2491864.00 $145.00 $4161440.00 29 29 Valve -Buried: 12" Plug Valve EA 1 $71067.00 $71067.00 $61500.00 $61500.00 30 30 Existing Force Main Sewer Connection EA 1 $171880.00 $171880.00 $181000.00 $181000.00 31 31 New Lift Station LS 1 $9521934.00 $9521934.00 $9721651.00 $9721651.00 32 32 Lift Station Abandonments EA 4 $291450.00 $1171800.00 $61000.00 $241000.00 33 33 Water Main Vertical Adjustment EA 4 $71637.00 $301548.00 $51500.00 $221000.00 34 34 Existing Water Service -Vertical Adjustment EA 29 $795.00 $231055.00 $650.00 $181850.00 35 35 Type II Bedding CY 1210 $64.00 $771440.00 $45.00 $541450.00 36 36 Pipe Insulation LF 2850 $23.00 $651550.00 $12.00 $341200.00 37 37 Imported Trench Backfill - Type A CY 2670 $42.00 $1121140.00 $18.00 $481060.00 38 38 Imported Trench Backfill - Type B LF 695 $48.00 $331360.00 $50.00 $341750.00 39 39 Trench Plugs EA 5 $922.00 $41610.00 $21500.00 $121500.00 40 40 Stabilization Fabric SY 250 $7.00 $11750.00 $4.00 $11000.00 41 41 Select Subbase Gravel CY 60 $59.00 $31540.00 $38.00 $21280.00 42 42 Crushed Base Course Gravel CY 150 $62.00 $91300.00 $40.00 $61000.00 43 43 Asphalt Surfacing TON 240 $149.00 $351760.00 $132.00 $311680.00 44 44 Concrete Curb LF 365 $37.00 $131505.00 $30.00 $101950.00 45 45 Concrete Flatwork - 4" Thick with Base Gravels SY 880 $65.00 $571200.00 $38.00 $331440.00 46 46 Concrete Flatwork - 6" Thick with Base Gravels SY 50 $113.00 $51650.00 $75.00 $31750.00 47 47 Landscape Tree EA 20 $756.00 $151120.00 $11200.00 $241000.00 48 48 Irrigation System Removal, Repairs &Replacement LS 1 $51814.00 $51814.00 $251000.00 $251000.00 49 49 Vegetation Restoration -Field LS 1 $91274.00 $91274.00 $251000.00 $251000.00 50 50 Vegetation Restoration -Lawn LS 1 $201230.00 $201230.00 $41500.00 $41500.00 51 51 Marker Post -Sanitary Sewer Manhole & Forcemain EA 10 $98.00 $980.00 $250.00 $21500.00 52 52 Pavement Markings LS 1 $11163.00 $11163.00 $41500.00 $41500.00 Base Bid Total: $2,985,000.00 $3,397,933.00