Progress ReportCitY Airaor� S27 PROGRESS REPORT Kalispell City Airport - Master Plan Update Stalling Engineers, Inc. Reporting Period: August 26, 2010 - November 30, 2010 Activity Description Completion Special Notes: Complete Date 1.1 Prepare Agreement 100% 7/20/2010 1.2 Prepare Preapplication & Grant Application 100% 6/21/2010 1.3 Prepare Work Plan 85% Majority of Work Plan Items are Complete a 1.4 Review Existing Files/Collect Airport Information Pilot Survey 100% 85% 8/20/2010 Completed Review of FAA Archives in Helena Survey out for Responses 1.50 a 1.60 Update Airport Inventory/Review Existing Data 65% Airport Inventory In -Progress z 1.70 Update Aviation Forecasts 25% Preliminary Forecasts at End of December 1.80 Conduct Airport Noise Studies a cc 1.90 Review Airport Planning Criteria W 1.10 Review, Refine, and Assess Aeronautical Alternatives N 1.11 Land Ownership 1.12 Preliminary Cost Estimates 0 1.13 Capital Improvement Plans 1.14 Environmental Overview 1.15 Draft Master Plan Update Report 15% Inventory Chapter approximately 75% Complete 1.16 Final Master Plan Update Report 2.1 Airport Layout Plan 50% Existing Inventory Developed and Verified Z 2.2 Terminal Area Layout Plan cc i w 2.3 Airport Airspace Plan CL j o a 0 a 2.4 2.5 Airport Approach Surface Plan - -- Airport Departure Surface Plan -- -- - Ci 2.6 Inner Portion of Al PP 9 Approach Surface Drawing -a 2.7 Exhibit "A" Property Map ZAProject-Active\Nirports\0043 - Kalispell City\003-2010\Billing\Progress Reports\0043-003 Progress Report No 2.xls 1 of 2 PROGRESS REPORT Kalispell City Airport - Master Plan Update Ste//ing Engineers, Inc. Reporting Period: August 26, 2010 - November 30, 2010 Activity Description Completion Special Notes: Complete Date 3.1 Public Outreach Plan 40% Setting Up Guiding Document v = 2 3.2 Public Informational Meetings (5 Mtgs) 20% Kick -Off Meeting Complete m a 3.3 Identify & Coordinate with Stakeholders (5 Group Mtgs) a a 3.4 Preliminary Meetings with Affected Landowners 0 0 a 3.5 Support & Coordination for City Sponsored Meetings 3.6 Design & Maintain a City Airport Website 20% Developed KCA Logo for Documents and Website 4.1 Closeout Checklist � 0 lZ 4.2 Cancelled Warrants Cn a 4.3 __ _ Financial 3-Way Check __ _ aO w o � cc 4.4 Overall Closeout Report � U Tasks Planned For Next Period 1 Complete Pilots Survey Complete Preliminary Forecasts Complete Preliminary Critical Aircraft Identification Complete Chapter 3 - Airport Inventory Complete Chapter 4 - Aviation Forecasts Critical Issues 1 None. Approved By: Jeff Walla, Project Manager Date: November 30, 2010 Z:\Project-Active\Airports\0043 - Kalispell City\003-2010\Billing\Progress Reports\0043-003 Progress Report No 2.xis 2 of 2