Resolution 4341 - South Woodland Construction Change Orderfi 3 3 RESOLUTION NO. 4341 A RESOLUTION TO ALTER AND AMEND THE CONTRACT WITH SANDON CONSTRUCTION CO., INC. ON THE SOUTH WOODLAND WATER MAIN IMPROVEMENTS PROJECT. WHEREAS, the City on October 2, 1996 did enter into a contract with Sandon Construction Co., Inc. for construction of water main improvements, South Woodland Drive, and WHEREAS, certain elements in the project required additional gravel and asphalt; and said additional gravel and asphalt could not have been necessarily foreseeable when the original construction contract was entered into, and said changes are contained in Exhibit "A", attached hereto and are by this reference made a part hereof; and WHEREAS, upon the advise and recommendation of John Wilson, Assistant City Engineer, it appears in the best interests of the City to approve said changes and alterations. NOW THEREFORE, pursuant to the provisions of Section 7-5- 4306{1} MCA be it hereby resolved: 1. The alterations and modifications of the contract between the City of Kalispell and Sandon Construction Co, Inc., dated October 2, 1996, as set out in Exhibit "A" attached hereto are hereby approved, and 2. As soon as the alterations and modifications are agreed to in writing, signed by the City Manager, as hereby approved by the Council, this approval thereof shall be in effect. PASSED AND APPROVE BY THE CITYfOlCIL AND MAYOR OF THE CITY OF KALISPELL THIS ✓i DAY OF b,. 1997• Doug1dA D. Rauthe, Mayor ATTEST: ' Ai4k." � Debbie Gifford Clerk of Counc O V) j:\wp\chng\So.Woodland 1 11634 EXHIBIT "A" CHANGE ORDER No. 1 PROJECT South.Won cUand.Water..Hain—Improvements DATE OF ISSUANCE ............................... EFFECTIVE DATE .............................. :............ OWNER........................................................................................ OWNER's Contract No . ..................................... CONTRACTOR ... ENGINEER ..ham,..Dean..6.14oskins ................ You are directed to make the following changes in the Contract Documents. Description: None Reason for Change Order. Extra quantities required for gravel and asphalt. Attachments: (List documents supporting change) CHANGE IN CONTRACT PRICE: CHANGE IN CONTRACT TIMES: Original Cmttran:t Price Ongiral Carib= rffm SntSstantial N[A ----- $ 157,273.60 .. Ready far final payment: NIA day, or dand .. ., Net changes ream previous Change Orders No. _ to No.. _ Net change from previous Change Orders No. to No. , .... = None days Contract Price prior to this Change Order Cant M rrrees prior to this Change Order s 157,273.60 Substae W CannOWow Ready for final payment: &P or don Net Increase (decrease) of this Change Order Net Increase (decrease) or this Change Order s 1,042.80_ - days Contract Price with all approved Change Orders Contract runes with all approved Change Orders Substantial Completion: 158, 316.40 Ready for final payment 6y. of Jaw RECOMMENDED: APPROVED: ACCEPTED: By. L*wr imck i,sd S;Vwwe) By: o.aer (AMR.., sgou.p By Caa, udw IA� ` Date• Date: Dates E)CDC No. 191043-B (1990 Edition) Prepared by the Engineers Joint Contract Documents Committee and endorsed by The Associated Cmicral Contractors or Amenici 1 ..- 3111