E5. Bid Award - Chip Seal Project201 Is' Avenue East PO Box 1997 VL.- Kalispell, MT 59903 Phone:406-758-7720 PUBLIC IA RK EP .fZTl�i£NT Fax: 406-758-7831 www.kalispell.com/Puhlic works MEMORANDUM DATE: March 12, 2017 I — TO: Doug Russell, City Manager FROM: Tom Tabler, PE, Civil Engineer CC: Susie Turner, PE, Public Works Director SUBJECT: Chip Seal Project for Year Ending December 31, 2018 MEETING: March 19, 2018 BACKGROUND: Each year the City of Kalispell performs pavement maintenance in the form of chip sealing to extend the service life of existing paved streets. Chip seal pavement maintenance for the year of 2018 will consist of chip sealing approximately 5 miles of City streets. Bids were received on Thursday March 8, 2017 at 2:30 PM. One responsive bid was received from local contractors: Contractor: Pavement Maintenance Solutions Engineer's 2018 Estimate Total Bid Price $176,451.50 $202, 856.00 References for Pavement Maintenance Solutions were contacted and interviewed. Pavement Maintenance Solutions was determined to be a responsive and responsible contractor successfully completing similar projects in Northwest Montana. STAFF RECOMMENDATIONS: Award the bid for the Chip Seal Project for Year Ending December 31, 2018 to Pavement Maintenance Solutions. ACTION REQUESTED: Motion to award the Chip Seal Project for Year Ending December 31, 2018 to Pavement Maintenance Solutions with the execution of the total amount bid for $176,451.50. FISCAL EFFECTS: The total project construction cost will be funded in parts ($141,005) by the Gas Tax Fund Overlay/Chip Seal Fund (2420-421-430240-368) and ($35,447) by the new Bridge and Road Allocation funds. The required 5% match ($1,772) for the new Bridge and Road Allocation funds will come from the Pavement Maintenance Fund (2500-421-430244-354). ALTERNATIVES: As suggested and approved by the City Council. ATTACHMENTS: Bid Analysis. BID TAB - Bids Opened March 8, 2018 2:30 pm Chip Seal Project for Year Ending December 31, 2018 Kalispell, MT 59901 City Proj. No. 18-0122 Engineers Estimate Pavement Maintenance Sol. PO Box 3379 Columbia Falls, MT 59912 No. Item Unit Quantity Unit Price Total Price Unit Price Total Price 1 Project Mobilization LS 1 $ 10,000.00 $ 10,000.00 $ 20,500.00 $ 20,500.00 2 Asphalt Seal and Chip Coat SY 76190 $ 2.40 $ 182,856.00 $ 1.85 $ 140,951.50 3 Traffic, Parking and Pedestrian Control LS 1 $ 10,000.00 $ 10,000.00 $ 15,000.00 $ 15,000.00 Total = $ 202,856.00 1 $ 176,451.50