11-17-16 Site Development Review Committee MinutesSITE DEVELOPMENT REVIEW COMMITTEE SUMMARY Thursday, November 17, 2016 Lower Level Conference Room 201 First Avenue East ATTENDING: Dave Dedman, Fire Chief Chad Fincher, Parks & Rec. Director Tom Jentz, Planning & Building Director Jarod Nygren, Senior Planner Wade Rademacher, Police Captain Tom Tabler, Senior Civil Engineer P.J. Sorensen, Chairman Kathy Nelson, Recording Secretary GUESTS: Doug Peppmeier, (TDH Engineering); and Margaret Davis (Resident) HEAR THE PUBLIC: Margaret Davis: "Congratulations on the Arbor Day Award." PERFORMANCE BOND REMINDERS: Captain's Marine — Their bank called Fincher yesterday regarding the bond. Landscaping has been finished. Tabler will check to see if we have received their as-builts. Jim Davis — KNIC — Their bond for fence along Treeline by the bypass and the apartments was tied in with the subdivision plat they did, rather than the C of O. They still need to put it in. Nygren will look into this. OLD BUSINESS: First American Title — 219 E. Center; new office building. Public Works has not received anything on this yet. This is still tabled in ARC but they are getting close. Fincher stated we need a site layout, and sidewalks need to be determined before we need a Landscape Plan. The sidewalk should be on the property line, with the same width as the Depot Place sidewalk. This will be on the agenda next week. KRMC — 320 Sunnyview Lane; G.I. Building (new digestive health building). This will be going off the north of the existing building, right near the Women's/Children's Clinic. They are planning for a spring start. This is still status quo, trying to pull together the PUD. The PUD has the potential of going to the Planning Board Work Session on December 13th. Nygren stated we'll know by the middle of next week. This will be on the agenda for next week. NEW BUSINESS: McDonald's — 1110 Hwy 2 W; new building to replace existing. They plan on taking down the existing building and putting in a new building on slab. This building will be five feet wider, with no basement. The property owner to the east is concerned about their southeast corner of the site where their stormwater leaves the site and goes south to the creek. They have a drainage easement there but it's not sufficient to capture all the water that is leaving that site. It's common for it to flood their parking lot. McDonald's will need to look at water drainage, although Peppmeier noted they will have less impervious area with more landscaping/grass area. They will be adding a downstream defender, and will be lifting the site. They will be draining to the same spot. Jentz asked about their drive-thru lanes. It will be concrete, pavement, and striping. There is no barrier between the drive- thru lanes and the parking lot. Sorensen noted the flood plain comes up in the NW corner and then down at the SE corner, and a flood plain permit was discussed. Peppmeier stated they have a full topography survey that can be provided. We would need a Site Plan with the contours and then stamped. They will need to figure out the base flood elevation off the FIS and then show where that would be. Fincher will review the Landscaping Plans. This is set for spring. They will be going to ARC on Tuesday of next week. They will update their Approach Permits and will also need an Encroachment Permit for the sidewalk. These permits will come from MDT. They will need concrete sidewalks and City Standard concrete approaches. This will be on the agenda for next week. PLANNING OFFICE ITEMS: Lofts at Ashley - Airport Road & Teal — They have decided to go forward with a 55-unit project in their RA- I zoning. They will be submitting their new design by next Monday. They will have higher density along Airport Road with some mixture of duplex and 4-plex. More single-family type units, even though they will still be apartments. Southside Estates — formerly Ashley Park Phase 9 — at Merganser and Pintail. We received plans for a 37-lot, single family subdivision. These will be modular -type homes. They will be sprinklering all of the units. They will probably post cash in lieu for parks. They have completed a Sound Study and will need a 6' wall with a 2' berm. Discussion was held regarding the street names. Jentz would like to see them continue with the "duck" names. OTHER REPORTS: Papa Murphy's — Regarding their C of O, they will need to bond for their landscaping. Tabler noted their sanitary sewer abandonment needs to be completed. Shops Building — at Spring Prairie 4. They need a 20' landscape buffer. This is part of the subdivision. They also need to paint the man doors on the building. Next Week — Because of the Thanksgiving Holiday, we will be meeting for Site Review on 2 Wednesday, November 23rd, at 10 a.m. The meeting was adjourned at 10:35 a.m. cc: Police City Manager Fairgrounds MDOT Bldg. Fire City Clerk City Airport Planning Parks Comm. Dev. Public Works