Resolution 3172 - Contract Amendment - Dyck Constructiont" J �J
RESOLUTION NO. 3172
A RESOLUTION TO ALTER. AND AMEND THE PLANS AND SPECIFICATIONS OF CONTRACT WITH
Dyck Construction, Inc. ON Metal Shop Building
Contractor Project
WHEREAS, the City did, on April 10, 1978 , enter into a contract with
Date
Dyck Construction, Inc. of Box 3452 Hwy 93 So. Kalispell, MT
Contractor Address
for construction of metal shop building
Description of Work
on the metal shop building and
Project
WHEREAS, upon the advice and recommendation of
John P. Kain , who is the City's consultant and
Director of Public Works
engineer on said project, certain changes and alterations of design and specifica-
tions have been found necessary and adviseable and in the best interests of the
City; and said changes and alterations could not have been necessarily foreseeable
when the original design and specifications were prepared on this phase of the
metal shop building , and said changes are contained in
Project
Exbibit "A" attached hereto and are by this reference made a part hereof; and
VIEBREAS, it appears in the best interests of the City to approve said changes
and alterations,
NOW 'THMWORE, pursuant to the provisions of Section 11-1204, R.C.M., 1947,
be it hereby resolved:
1. The alterations and modifications of the specifications and plans of the
contract between the City of Kalispell and Dyck Construction Co. ,
Contractor
dated April 10, 1978 , as set out in Exhibit "A" attached hereto, are
hereby approved; and
2. As soon as the prase to be paid for said alterations and modifications
are agreed to in wri
Council, t ' pprov
PASS BY THE CITY C
1st DAY OF 1
ATTEST
signed by the contract r, as hereby approved by the
1eof shall be in effe t.
AND APPROyED BY MAYOR OF THE CITY OF KALISPELL THIS
Mayor
1
?orm C-2
?/77
CHANGE O1ZMR NO. 1
PROJECT Metal Shop Building
OWNER City of Kalispell
CONTRACTOR Dyck Construction, Inc.
The following change(z) � hereby made to the contract dated April 10, 1978
1. Furnish and install one (1) 8,000 lb. dual side post hoist in the
Amount of Change $ 3,200.00
2.
.Amount of Change $
The total amount (added) UU*n) hereby is $ 3,200.00
The amended contract price including this change order now is $ 74$212.00
The contract time is changed by 0 calendar days thereto.
The ammiducl date for completion of all work now is .August 10, 1978
JUSTIFICATION
It will be almost impossible to service vehicles without this hoist
ACCEPTANCE
The City of Kalispell, owner, and Dyck Construction, Inc. contractor,
in the above referenced contract, do hereby agree to the terms and conditions of.
the instant change order number 1 and same is effective this date in rdance
with Resolution No. 3172 and said contract is neAd eR accordingly
Contractors Name
ACCEPTED BY. THE CITY OF
ATTEST:
to
+orm C-1
?/77
EXHIBIT "Are
PROPOSED CiiAt9GE ORR NO. 1
PROJECT Metal Shop Building
O'di'm City of Kalispell
CONTRACTOR Dyck Construction Co.
DATE May 2, 1978
The followiaig change are hereby proposed to the Contxact dated April 10, 1978 .
1. furnish and install one (1) 8,000 lb. dual side post hoist in
Amount of Changp_.�,2,200.00
2.
Amount of Change
The total amount to be (added) (dmbzbaQz- hereby is 3,200.00
The contract price including this change order will be: $74,212.00
The contract time is changed by 0 calendar days thereto.
The .-mle-d date for completion of all work will be August 10, 1978
JUSTIFICATION It will be almost impossible to service vehicles without this
hoist
I, the undersigned, City Clerk of the City of Kalispell certify that the foregoing is a -t'—
copy of the Resolution duly assed by the City Counoi of the City of Kalispell, Montana ai
regular meeting held the fday of
City Cle of they of Kalispell, Montana