Loading...
Resolution 3093 - Contract Amendment - Pack & Co - 1st Ave E Storm DrainRESOLUTION NO. 3093 A RESOLUTION TO ALTER AND AMEND THE PLANS AND SPECIFICATIONS OF CONTRACT WITH PACK AND COMPANY, INC. ON FIRST AVENUE EAST STORM DRAIN IMPROVEMENT PROJECT. WHEREAS, the City did, on July 22, 1976 enter into a contract with Pack and Company, Inc. of Kalispell, Montana for construction of storm drain improvements on First Avenue East; and WHEREAS, upon the advice and recommendation of Thomas, Dean & Hoskins, Inc., who is the City's consultant and engineer on said project, certain changes and alterations in the sanitary sewer grade and pipe are necessary because the pipe leaks and the grade is adverse. This change order will correct these problems. Said changes and alterations have been found necessary and adviseable and in the best interests of the City; and said changes and alterations could not have been necessarily foreseeable when the original design and specifications were prepared on the construction of the storm drain project. Said changes are contained in Exhibit "A" attached hereto and is by this refer— ence made a part hereof; and WHEREAS, it appears in the best interests of the City to approve said changes and alterations; NOW THEREFORE, pursuant to the provisions of Section 11-1204, R.C.M., 1947 be it hereby resolved: 1. The alterations and modifications of the specifications and plans of the contract between the City of Kalispell and Pack and Company, Inc., dated July 22, 1976, as set out in Exhibit "A" attached hereto, and is hereby approved; and 2. As soon as the price to be paid for said alterations and modifications are agreed to in writing, signed by the cPntiE4or and approved by the Council, this approval thereof shall be in effe 119766. BY CITY C�d'CINCIZ At�/APPROVED BY/THE MAYOR THIS 15TH DAY OF NOVEMBER, Norma E. Happ, May , City I, the undersigned, City Clerk of the ity of i pe c ify that the foregoing is a true copy of the Resolution duly �^ -by Ci C c 1 of Cit of,T�alispell, Montana at a regular meeting held � ! �� Ci f ity of Kalispell FOR CITY OF KALISPELL Project- Storm Drain Improvements Kalisniall-. Montana Date: October 26 1976 Change Order No. The following changes in the plans, specifications and quantities for the above project for utility adjustment , are proposed: A. Description: Removal and replacement of 18" sanitary sewer. B. Purpose: To correct adverse grade® C. Cost- Contract prices and/or time -materials® (See second sheet.) When accepted and approved by_ The City of Kalispell and by the Contractor, this Change Order becomes a part of and subject to the terms and conditions of the original contract for construction of storm drain improvements at Kalis-oell. Montana. RECOMMENDED FOR ACCEPTANCE AND APPROVAL: ACCEPTED AND APPROVED: By:_ ATTEST: THOMAS, DEAN & HOSKINS, INC. Engineers 1►, B Y.. Cont��� V- By 3),;6A CITY OF KALISPELL Date October 26, 1976 KALISPELLy MONTH 59901 Change Order No. PACK & CO. P. 0. Box 222 Kalispell, Montana 59901 Value of Item Bid Quantity Unit Work Comple- No. Description Quantity Completed Price ted to date 1. Labor 21 Hrs. 21 Hrs. $14.50 $ 304.50 2. Superintendent 7 Hrs. 7 Hrs. $17.00 119.00 3. 500 Backboe 8 Hrs, 8 Hrs. $29.50 236.00 4. Concrete 3 Yds. 3 Yds.' $33.35 100.05 5. Type I Bedding 5 Yds. 5 Yds. 4.20 21.00 6. Type 11 Bedding 14 Yds. 14 Yds. $ 4.10 57.40 7. Type I Pavement 17 Yds. 17 Yds. 8.75 148.75 8. Oakum 50 Ft. 50 Ft. $ .50 25.00 Total: $1,011.70