5. Review of Bids - Center Street Pedestrian Improvements ProjectAgenda -September 2, 1997 AGENDA ITEM 5 - REVIEW OF BIDS -CENTER STREET PEDESTRIAN IMPROVEMENTS PROJECT BACKGROUND/CONSIDERATION: On August 19th we received the bids for this project. The low bids were: Base Bid $79,659.25 Alternate 1 $15,629.25 The combination of the bids, the Engineer inspection cost of $12,746.00, and the purchase of the lights, controls, poles and appurtenances is estimated at $37,181.00. This is a total of $145,221.50. Our budget for this project was $140,000. We will be able to utilize approximately $5,000 from the TIF budget designated for signals at other intersections. This would allow us to complete the entire improvement now. RECOMMENDATION: I recommend that we do the entire project at this time - both the crosswalks and the signals. ACTION REQUIRED: A MOTION to approve both of the bids received from Montana Lines and will authorize the staff to prepare for the actual construction of this project. We hope to have the project completed prior to winter weather.