Loading...
4. Change Order/Final Acceptance/Nupac/Woodland Ct ProjectAgenda -May 27, 1997 AGENDA ITEM 4 - CHANGE ORDER/FINAL ACCEPTANCE OF NUPAC CONTRACT - WOODLAND COURT PROJECT BACKGROUND/CONSIDERATION: I have enclosed a memo from the City Attorney concerning the final billing. (You have previously received a copy of this memo.) Based upon the analysis of the contract documents by our consulting engineer, the City Attorney, and an independent engineer's review. Based upon this review and meetings with the three parties (Nupac, T D & H, City Staff), I have directed that T D & H prepare a change order and final payment based upon the recommendation enclosed within this memo. RECOMMENDATION: Based upon the recommendation of our consulting engineer, the City Attorney's review, and subsequent review of an independent engineer, I concur with the recommendation for a change order of $5,614 for extra services/material costs requested by Nupac. ACTION REQUIRED: Approval of the change order and final acceptance of the Woodland Court project should be completed by RESOLUTION. Thomas, Dean & Hoskins, Inc. 00L- Engineering Consultants f I May 23, 1997 Clarence Krepps, City Manager City of Kalispell P.O. Box 1997 Kalispell, MT 59903-1997 RE: Woodland Court Project Dear Clarence: Enclosed is the Final Pay Estimate for NUPAC. We have included the items recommended for payment by the City Attorney. In all cases, the items added are increases to quantities of work included in the contract. A Change Order is not necessary since there is not change in unit price or time. Also enclosed is the Certificate of Substantial Completion. This should be accepted by the City. After Council approval, the Pay Estimate and Certificate should be forwarded to NUPAC along with the payment. NUPAC should sign and return the Pay Estimate. Very truly yours, THOMAS, DEAN & HOSKINS, INC. W'J 'J Michael W. Fraser MWF:mj K94-46-4 Encl: a:may23kre.ltr cc: Susan Moyer Glenn Neier 690 North Meridian, Suite 101 • Kalispell, MT 59901 . (406) 752-5246 • FAX (406) 752-5230 CITY OF KALISPELL Date: May 23, 1997 PROJECT: WOODLAND COURT Pay Estimate No. 8 TIN) JOB #: K94-46-4 Page 1 of 3 Amount Completed To Date $287,575.12 Less Retained Percentage (0 % of the total) $0.00 Subtotal $287,575.12 Dept. of Amount Due Revenue Contractor Estimate #1 $40,263.37 $402.63 $39,860.74 Estimate #2 $81,927.83 $819.28 $81,105.55 Estimate #3 $84,387.60 $843.88 $83,543.77 Estimate #4 $6,251.40 $62.51 $6,188.89 Estimate #5 $8,486.21 $84.86 $8,401.35 Estimate #6 $16,015.32 $160.15 $15,855.17 Estimate #7 $19,107.94 $191.08 $18,916.86 Less Previous Payments $256,439.67 Amount Due Contractor $31,135.45 Less 1 % Dept. of Revenue $311.35 TOTAL AMOUNT DUE $30,824.10 We hereby certify the work for which payment is hereon requested has been performed in accordance with the specifications. CONTRACTOR: PACK AND COMPANY Paul r m We hereby certify the foregoing is a true and correct statement of the amount due the Contractor for construction, to date, of the above project, and payment for same is hereby recommended. ENGINEER: THO S, DE N OSKINS, INC. By: MJW sc a raser, . CITY OF KALISPELL APPROVED: Susan Moyer, City of Kalispe1F- CITY OF KALISPELL Date: May 23, 1997 PROJECT: WOODLAND COURT Pay Estimate No. 8 JOB #: K9446-4 Page 2 of 3 SCHEDULE I - SITE GRADING AND DRAINAGE IMPROVEMENTS VALUE OF WORK BID QUANTITY UNIT COMPLETED ITEM DESCRIPTION QUANTITY COMPLETED PRICE TO DATE 1. MOBILIZATION LUMP SUM 100 % $10,000.00 $10,000.00 2 OROROWD 3900 CY 3527CY $4.60 $16,224.20 3. EXCAVATION, TYPE I W/ TYPE A BACKFILL 40 CY 40 CY $7.00 $280.00 4. 12" STORM DRAIN PIPE, CLASS II, IN PLACE 120 LF 120LF $25.00 $3,000.00 5. 12" CMP CULVERT, IN PLACE 104 LF 104 LF $35.00 $3,640.00 6. STORM DRAIN INLET 1 EA 1 EA $1,500.00 $1,500.00 7. RIP RAP, IN PLACE 12 CF 12 CF $20.00 $240.00 SUBTOTAL SCHEDULE I $34,884.20 SCHEDULE H - WATER AND SEWER IMPROVEMENTS WATER 1. TYPE II PIPE BEDDING MATERIAL, IN PLACE 50 CY OCY $18.00 $0,00 2 IMPORTED L 1050 CY 881.3 CY $13.00 $11,456.90 3. WATER MAINS, IN PLACE 8" PVC DR 18 1242 LF 1248 LF $$17.00 $21,216.00 12" PVC DR 18 369 LF 363 LF $26.00 $9,438.00 4. GATE VALVES & VALVE BOX, IN PLACE 8" 4 EA 4 EA $750.00 3,000.00 12" 2 EA 2EA $1,200.00 12,400.00 5. FIRE HYDRANTS W/ AUXILIARY GATE VALVES AND BOX, IN PLACE 3 EA 3 EA $2,500.00 $7,500.00 6. 3/4" WATER SERVICE, IN PLACE -INCLUDING PIPE, CORPORATION STOP, CURB STOP AND CURB BOX 24 EA 25EA $600.00 $15,000.00 7. CONNECTION TO EXISTING WATER MAIN, INPLACE 1 EA IEA $1,500.00 $1,500.00 8. PRESSURE AND LEAKAGE TEST, COMPLETED & ACCEPTED -MIN OF 7§ % OF ITEM 7 LUMP SUM 100 % $500.00 $500_00 CITY OF KALISPELL Date: May 23, 1997 PROJECT: WOODLAND COURT Pay Estimate No. 8 JOB #/: K94-464 Page 3 of 3 VALUE OF WORK BID QUANTITY UNIT COMPLETED ITEM DESCRIPTION QUANTITY COMPLETED PRICE TO DATE --------------------- 9. ----- ------ --------------- ---------------------------- CLEANING OF WATER MAINS -MIN OF 7§ % OF ITEM 7 LUMP SUM 100 % $500.00 $500.00 10. DISINFECTION AND BACTERIOLOGICAL TESTING OF WATER MAINS -MIN OF 5 % OF ITEM 7 LUMP SUM i EA $500.00 $500.00 11. CAST IRON FITTINGS, IN PLACE 1240 LBS 2010 LBS $3.00 $6,030.00 SEWER 12. TYPE II PIPE BEDDING MATERIAL, IN PLACE 80 CY 76CY $18.00 $1,368.00 13. IMPORTED CKFILL 3170 CY 3074.1CY $13.00 $39,963.30 14. EXCAVATION TYPE 2 W/ TYPE A BACKFILL 2250 CY 3697.1 CY $6.00 $22,182.60 TYPE 1 W/ TYPE A BACKFILL 1615 CY 0 CY $6.00 $0.00 15. SANITARY SEWER, IN PLACE 8" PVC SDR 35 2423 LF 2428LF 13.00 $31,564.00 8" PVC DR 18 290 LF 31OLF 16.00 $4,960.00 16. TESTING COMPLETE AND ACCEPTED - MIN OF 3 % OF ITEM 15 LUMP SUM 100% $1,700.00 $1,700.00 17. SANITARY SEWER MANHOLE, IN PLACE 10 EA 8EA $3,665.00 $29,320.00 18. SANITARY SEWER DROP MANHOLE, IN PLACE 2 EA 2 EA $4,490.00 $8,980.00 19. EXTRA DEPTH OF MANHOLE, IN PLACE 27 VF 33.8 VF $180.00 $6,084.00 20. EXTRA DEPTH OF DROP MANHOLE, IN PLACE 16 VF 16.4 VF $180.00 $2,952.00 21. SANITARY SEWER SERVICE, IN PLACE 712 LF 830LF $10.00 $8,300.00 22. CONNECTION TO EXISTING SEWER 1 EA 1 EA $500.00 $500.00 SUBTOTAL SCHEDULE II $236,914.80 SUB -TOTAL SCHEDULES I & II $271,7".00 APPROVED ADDITIONS AND DELETIONS I. Connect to Existing Water Service (3) $1,168.01 2. Water Main Adjustment $8,261.11 3. Asphalt Pavement Replacement $6,347.00 SUB -TOTAL ADDITIONS $15,776.12 PROJECT TOTAL $287,575.12 CERTIFICATE OF SUBSTANTIAL COMPLETION OWNER's Project No. ENGINEER's Project No. K94-46-4 Project: South Woodland Court CONTRACTOR Pack & Company (NUPAC) Contract For Schedules I & A Contract Date November 15 1995 This Certificate of Substantial Completion applies to all Work under the Contract Documents or to the following specified parts thereof: Schedule I, Site Grading and Drainage Improvements Schedule II, Water and Sewer Improvements To City of Kalispell Owner And To Pack & Company (NUPAC) Contractor The Work to which this Certificate applies has been inspected by authorized representatives of OWNER, CONTRACTOR and ENGINEER and Work is hereby declared to be substantially complete in accordance with the Contract Documents on August 16, 1996 DATE OF SUBSTANTIAL COMPLETION A tentative list of items to be completed or corrected is attached hereto. This list may not be all-inclusive and the failure to include an item in it does not alter the responsibility of CONTRACTOR to complete all the Work in accordance with the Contract Documents. The items in the tentative list shall be completed or corrected by CONTRACTOR within N/A days of the above date do'ffSubstantial Completion. The ENGINEER recommends acceptance of the Certificate of Substantial Colnpiegon in Jcordapce Wtttt)the Contract Documents. THOMAS DEAN & HOSKINS INC. �1�11 (-(o /�yL/ c""� I/ " Z') Engineer 1734 Date The City of Kalispell accepts the work as Substantially Complete and will assume full responsibility there of on the day of 1997 at _ (time). CITY OF KALISPELL Owner By: Date Incorporated 1892 Telephone (406) 758-7700 FAX (406) 758-7758 Post Office Sox 1997 Kalispell, Montana Zip 59903-1997 Douglas Rauthe Mayor Clarence W. Krepps City Manager City Council Members: May 1, 1997 Gary W. Nystul Ward I Cliff Collins TO: Clarence Krepps, City Manager Ward I Norbert F. Donahue FROM: Glen Neier, City Attorney Ward 11 Dale Haarr Re: NuPac Change Ord quest on Woo and Court Project ward II Jim Atkinson Over the past several weeks I have been analyzing the Contract Documents for Site Grading, Ward 111 Street Paving and Water and Sewer Improvements for Woodland Court affordable housin�uren Granmo and III Project. You are aware that the Project was bid in three schedules with NuPac awarded Schedules I and II Site Grading and Drainage and Water and Sewer Improvements) at Pamela B. Kennedy ( g g p ) ward IV €, total price of $280,847.00. A-1 Paving received the bid for Schedule III at $108, 610.00. Duane Larson 4uPac has submitted a claim with the City for payment for extra work and materiaaard IV associated with the project which increases the Project costs by $69,002.00 to $349,849.00. For purposes of this discussion, I am only concerned with the NuPac claim extra compensation. I have been involved in at least two meetings with representatives from Thomas, Dean and Hoskins, the City's consulting engineers on the Project and one meeting with NuPac representatives to discuss the change order request. Suffice it to say there exists wide disparity between the recommendations of the TD&H and the demands of NuPac. Because alleged'extra engineering costs associated with the project, which TD&H suggests charging against NuPac the final recommended contract pay amount totals $276,736.50. The differences between the recommended pay amount of TD&H and the demand of NuPac is contained in seven (7) bid items of the contract. After meeting with representatives of TD&H and NuPac, I outlined the applicable contract specifications which described both the "work required to be performed" and the "measurement and payment"for work performed. After arriving at several conclusions based upon my interpretation of the contract documents, I asked an independent engineer, Jerry Hanson, to review the contract from an engineering prospective to determine whether "terms of art" used in the document would lead to a different conclusion. Hanson's analysis of the contract documents iAwp400dct.wpd Page 1 of 8 conformed to all but one instance to my conclusion. This report is based upon a thorough review of the contract documents from a legal perspective as well as engineering opinion as to the "standard in the industry" applicable to this type of contract. The discussion below contains an analysis of and my recommendations to the Council, concerning each individual item under dispute. Construction Specifications, Division I, General Requirements, Section 01000, Special Procedures, ¶ 11 states: All excavated materials shall be immediately loaded into trucks, removed from the site and disposed of by the Contractor. Excavated materials shall not be stockpiled on site. Native materials shall not be used as backfill. Trench backfill within the public right-of-way shall consist of imported select uncrushed material (Type A Trench Backfill) containing stones no larger than six (6) inches at its largest dimension. This material shall provide a uniform gradation mixture in accordance with the requirements of the current edition of the Montana Public Works Standard Specifications. Section 02230, Street Excavation, Backfill and Compaction, Imported Borrow Excavation states as follows: imported Borrow Excavation shall consist of excavation made from borrow areas outside the project limits and outside the normal grading limits for the completion of the embankments. Borrow areas, or areas outside the project pits from which the imported borrow may be obtained, will generally not be designated. However, any source chosen by the Contractor shall be subject to approval of the Engineer. Imported Borrow Excavation, if required, shall be paid for at the contract unit price for Imported Borrow. Imported Borrow Excavation shall be handled and placed as specified in Section 02230.04 EMBANKMENT. NuPac is claiming that it handled and properly placed 3527 CY of material meeting the definition of imported borrow. TD&H disputes this claiming that only 2648 CY of material meeting the definition of imported borrow was placed on the site. A substantial part of the discrepancy revolves around material removed from the trenches on site and placed on lots within the Woodland Court subdivision. TD&H alleges that NuPac, TD&H and the City agreed that NuPac could deposit trench excavation materials on site, at no extra cost to the City. NuPac disputes, and claims that it rejected the "no cost" proposal. Documents made iAwp\woodct.wpd Page 2 of 8 ' available to this office indicate a discussion of depositing trench materials on site, there is no indication of any agreement by NuPac to do so at no cost. Further, if an agreement to dispose of material on site, in contravention of ¶ 11, above, was made, there should have been a corresponding change order adjusting the haul costs because NuPac under the contract was required to remove a excavated materials from the site. Construction Specifications, General Requirements, Section 01010, Measurement and Payment, ¶ 2.1.5 Disposal of Waste Material and If 3.4.5 Imported Borrow states as follows: 2.1.5 Disposal of Waste Material No separate measurement or payment will be made for disposal of waste materials. All costs related to disposal of materials shall be merged and included in the contract price for related bid items. Waste material meeting the requirements of imported borrow shall be wasted on -site. Disposal on -site shall be behind the curbs from the sidewalk lotward. 3.4.5 Imported Borrow. Approved material accepted in place for site grading shall be measured in place and paid for at the contract unit price of "Imported Borrow". Price shall include all labor, equipment, and incidental items necessary to complete the work. Material removed from the storm water retention area bordering the south side of lots 10 through 16 shall be included as imported borrow. Under the provisions of these paragraphs it is not clear whether or not payment should be made for "Waste material meeting the requirements of imported borrow shall be wasted on site." Placement of borrow for embankment purposes involves more than simply hauling the material away and dumping it. No document available to this office indicates that the material removed from the trenches was placed as other than embankment. It further appears that for purpose of site grading material accepted in place was to be paid for at the unit price for "imported borrow" The difference in amount of borrow between NuPac and TD&H cannot be reconciled. Ambiguity in the contract will be construed against the City, as TD&H , the City's agent drafted the contract documents. I don't believe that the City can rely on the fact that some, maybe even a substantial amount of the material, removed from the trench and placed on the site as reason to deny payment on this item. If the material met the requirements of imported borrow placed as embankment, it should have been paid for at the unit price of "Imported Borrow". NuPac therefore is entitled to a change order totaling $4,043.00 under Schedule II, Item 2. iAwp\woodct.wpd Page 3 of 8 2. Schedule I, Bid Item 2, Excavation Type 1 w/ Type A Backfill According to documents in my possession the estimated quantity was 40 CY at $7.00 per yard for a total bid of $280.00. In a letter to Clarence Krepps dated March 18, 1997, TD& H calculates the quantity at 31.1 CY. The difference between the quantities amounts to $62.30. Rather than haggle over $62.00 it is advisable to pay the amount and issue a change order for $62.30 under Schedule II, Bid Item 3. •r : i rIII r11111 r ;�, , Construction Specifications, General Requirements, Section 01010, Measurement and Payment ¶'s 3.16.1 Section 02713, Water Mains and 3.16.4 provide as follows: 3.16.1 WATER MAINS. Measurement of water mains shall be made in lineal feet along the center line of pipe through all valves, fittings and appurtenances. Payment for water mains will be made at the contract unit bid price bid per lineal foot for "Water Main, in Place" for the various sizes called for, which price shall include furnishing and installing pipe Type 1 or Type 2; excavation and Tvne A backfill, furnishing and placing Type 1 pipe bedding; and all other work !lecessary or incidental for completion of the item. 3.16.4 Imported Backfill. Imported backfill accepted in place for water mains shall be measured by suitable means and paid for at the contract unit price of Imported Backfill. Price shall include cost of all imported material, labor, equipment, and incidental items necessary to place and compact backfill material to the contract specifications. Imported material shall be a granular material meeting the requirements of Type II Bedding. NuPac claims that the Contract -Documents contain no specific wording regarding excavation of trenches for water mains. NuPac, therefore, claims a quantity of 1594 CY of material based upon measurement and total tickets. TD&H calculated backfill requirements, at 881.3 CY, based upon Type 1 or Type 2 trench, excavation and Type A backfill. Section 02221, 04, B, and D, Montana Public Works Standards describes TYPE 1 TRENCH EXCAVATION as follows: B. Excavation performed as Type 1 will not be shored or sheathed. The sides of all trenches greater than 5 feet in depth shall be sloping back to the angle of repose to preclude collapse, in accordance with Table P-1, Section 1926.653 of OSHA Safety and Health Regulations for Construction as shown on Standard Drawing No. 02221- iAwp\woodct.wpd Page 4 of 8 1. In no case shall trench walls above the 5 foot level be slopped steeper than one foot rise per one foot horizontal (1: 1), except for rock excavation. D. TRENCH DIMENSIONS. Trench dimensions shall be as specified below. (1) Width. The width of the trench shall be such to provide adequate working room for men to install and join the pipe in the specified manner. The width of that portion of the trench ... (b) from the bottom of the trench to a maximum of 5 feet above the bottom of the trench shall for Type 1 Trench Excavation, shall be as follows: a) A minimum of 3'-6" for pipe sizes 12 inches and under. b) A minimum of 2'-0" plus the outside diameter for pipe sizes greater than 12 inches or a greater minimum width as specified by the pipe manufacturer. c) A maximum width as specified in the Special Provisions. Section 02221, 05, C, (2) reads as follows: Type A. Trench Backfill. Materials used for backfill shall be carefully deposited in layers as specified above, wetted to within 3% of optimum moisture content, and compacted to at least 95 percent of maximum dry density, as determined by AASHTO T-99 or, for material which does exhibit a typical well-defined moisture -density curve, 70 percent relative density as determined by ASTM D4253 and D4254. Standard Drawing No. 02221-1, Montana Public Works Standards and the Sections quoted above from the Standards describe the work to be performed in trench excavation Type 1, with Type A Trench Backfill. Method of payment for the work is set forth in Section 3.16.1 and Section 3.16.4. It is acceptable industry standard to measure the work to be performed by determining the dimensions of the trench and calculating the backfill required based upon the placement of appropriate material back in the ditch. Nothing contained in the representations of TD&H or NuPac indicate to me, that any other method of payment was appropriate. A contractor should not be compensated for over excavation resulting in an increase in the amount of backfill required, when the over excavation was occasioned for the convenience of the contractor. The monetary difference between the amount claimed by NuPac and the amount *ecommended for payment by TD&H amounts to $9,265.00. Based upon the contract i:\wp\woodct.wpd Page 5 of 8 language, I would respectfully decline to recommend a change order on the NuPac claim. 4. Schedule II, Bid Item 11, Cast Iron Fittings In Place NuPac has requested a change order for 2165 # of cast iron fittings in place at $3.00 per pound.. TD&H recommended payment for 2010--41. According to my notes it was agreed NuPac's claim was well taken. The difference of 155# amounts to $465.00. I recommend a change order based upon the NuPac claim. 5. Schedule II, Bid Item 12, Type II Pipe Bedding In Place NuPac claims a pay quantity of 76 CY of Type II Pipe Bedding which is according to the Montana Public Works Standards used in to replace soft, spongy or otherwise unsuitable material in the trench bottom. NuPac indicates that it encountered groundwater in the trench because the existing sanitary sewer was set up as a "french drain". I am not sure that the NuPac can be held responsible for site conditions which were not at all observable upon inspection or anticipated. Over excavation may have been necessary because of the infusion of ground water from the existing sewer. TD&H has recommended payment for 18 CY of material. The difference in money amounts to $1,044.00. I would recommend a change )rder to NuPac based unforseen circumstances. Caveat: If NuPac knew or should have known, with the exercise of reasonable diligence, of the groundwater problem, there is potentially a defense to the claim. This would involve, however, require an involved fact-finding process. 6. Schedule II, Bid Item 13, Imported Backfill, Sewer NuPac has requested a change order for placement of 5550 CY of imported backfill involved the sewer excavation on the Woodland Court project. TD& H has recommended payment for 3074 CY. The situation here is very similar to the situation discussed in 3 above. Additionally, Construction Specifications, General Requirements, Section 01010, Measurement and Payment, ¶ 3.4.4.1, states as follows: 3.4.4 Excavation. 3.4.4.1 Trench Excavation and Backfdl for Sanitary Sewers, Service Lines and Storm Drains. Trench excavation and backfill shall be measured by the cubic yard of excavated material in its -riginal for and condition prior to removal. The volume of excavation and backfill shall be iAwp\woodct.wpd Page 6 of 8 t computed in the following manner: The length of trench shall be determined by measuring along the centerline of the pipe from the face of the manhole through all manholes to the end of the pipe being installed. Three feet will be added to the trench length at each service lines. The width of intersecting trenches will be subtracted if that width was previously included in trench excavation quantities. 2. The depth of the excavation shall be determined by measuring from the ground or payment surface down to the flowing of the pipe. Measurement to the flowline of the pipe shall be increased by 0.4 feet to allow for bedding material and pipe wall thickness. All measurements shall be to the nearest 0.1 feet. 3. The width of the trench shall be considered to be as shown on Construction Standard No. 02201-3 (Does not exist) for Type 1 Excavation or 3.50 feet for Type 2 excavation for the full depth of the trench regardless of the actual trench width or shape actually constructed. 4. Excavation for manholes shall be considered to be 25 S.F. times the depth from the top of the manholes to a point 0.4 below the manhole base. The measured numbered of cubic yards of trench excavation for sanitary sewers, service lines, and storm drains will be paid at the contract unit price per cubic yard for "Excavation Type 2 with Type A Backfill" or Type 1 Excavation with Type B Backfill" as shown on the proposal form and on the drawings. The contract bid price shall include the cost of all excavating, select backfill, backfill, compaction shoring, bracing, dewatering, asphalt and concrete removal, disposal of unusable materials, asphalt, and concrete and all other items incidental or necessary to the complete work except as otherwise provided in these specifications. One problem with the above, as noted is that Construction Standard No. 02201-3 does not exist. A scrivener's error will not create an ambiguity in a contract. Additionally, it should be noted that Section 02221, Montana Public Works Standards contains the necessary language describing the work to be done, and references Construction Standard No. 02221- 1. Any ambiguity created by the typo -error is cleared up in Section 02221. Contracts shall generally be construed as a whole so as to not create an ambiguity. NuPac requested change order amounts to 2476 CY @ $13.00 per yard for a total of $32,188.00. Based upon the foregoing, I believe TD&H's analysis to be correct and recommend that the Council deny the change order under Schedule 11, Bid Item 13. iAwp\woodct.wpd Page 7 of 8 7. Schedule III, Bid Item 1, Subbase Course Material in Place NuPac is claiming a change order for placement of 1807 CY of subbase course material placed upon the site as subbase course material under the Street Paving Improvement portion of the contract. TD&H recommends that the City deny the claim because the work was under the Schedule awarded to A-1. A couple of questions present themselves on this issue. Was NuPac directed by TD&H to deliver the material? Was the material subbase course material or borrow? Why was there not a corresponding reduction in A-1 contract for the material? TD&H states that the material placed by NuPac was imported borrow for which NuPac was compensated under Schedule I, Bid Item 2. Because the resolution of this issue involves a - factual dispute, not subject to either legal or engineering resolution, I must respectfully decline to recommend payment for this change order in any amount. The disputed amount involves $22,134.00. _ In total I am recommending NuPac receive a change order for Schedule I, Bid Item 2, (Imported Borrow), Schedule I, Bid Item 2, (Excavation Type 1 w/ Type A Backfill, Schedule II, Bid Item 11, (Cast Iron Fittings), and Schedule II, Bid Item 12,( Type II Pipe Bedding In Place) totaling $5,614.00. In reviewing the contract documents and related documentation within my possession for this memo, I have reason to question some of drafting techniques and construction administration practices employed by TD&H. While on most points, I have agreed with TD&H's assessment, I cannot say that the practice of letting change orders go until the contract has been completed and then having what appears to be a catch-up change order is an acceptable practice. Further it appears that day-to-day monitoring of the construction process seems to have been weak because the City was not informed of problems in a timely manner. i:\wp\woodct.wpd Page 8 of 8