Change Order - South Woodland Phase IIncorporated 1892
Planning, Economic &
Community Development Department
P.O. Box 1997
Kalispell, MT 59903-1997
To: Larry Gallagher, Director, PECDD
From: Susan Moyer, Housing Manager
Subject: Change Order - South Woodland Phase I
248 Third Avenue East
(406) 758-7740
(406) 758-7739 (office fax)
(406) 758-7758 (City Hall fax)
March 25, 1996
The attached letter from Thomas, Dean and Hoskins is self-explanatory. The funds covering this
work, with the exception of $8,411, have been included in the overall project budget since the
beginning -- just in a different item than the sewer and water development. These costs
traditionally are handled by the utility companies with the developer. To offset the $8,411
increase brought about by Pacific Power's new design requirements over and above those in
place at the time the project was estimated, we can cover this through an eligible expenditure
from 2880-480-470240-710 (Community Development Loan Revolving Contingency).
I'MU
EUU.4t nQUS-. G
OPP;!RV INRY
INC.
i fawh E ENGINEERING CONSULTANTS
690 North Meridian, Suite 101 • Kalispell, Montana 59901 • (406) 752-5246 e FAX (406) 752-5230
Susan Moyer
City of Kalispell
P.O. Box 1997
Kalispell, MT 59903-1997
RE: Woodland Court
Change Order Letter
Dear Susan:
Change Order No. 1 (Schedule III)
completed to include construction
Schedule III contract.
March 19, 1996
of the Woodland Court project was
of the electrical system in the
The electric, telephone, and television backbone system was not
included in the project bid. The developer generally deals
directly with the utility companies for these items and
construction is typically separate from the water, sewer, and
street improvements.
We solicited bids for improvements based on estimated quantities at
unit prices from both primary contractors upon receipt of PP&L's
design. The difference between the accepted bid ($22,809.50) and
high bid was 15%.
The project budget included separate items for utility trench
construction, street lighting, and phone service ($31,750). Actual
cost for these items is $45,671. The phone service fee ($5,510) is
recoverable as the development fills, reducing the service utility
cost to $40,161. The net increase over budget for these items is
$8,411.
The power company has required all electrical underground lines to
be encased in conduit for the last 8 to 12 months. Previously
conduit was only required at street, sidewalk, and driveway
crossings. The change was instituted because of construction
related problems associated with maintaining open trenches. The
budget was based on previous requirements. The increase due to
100% conduit use is $7700, accounting for 92% of the budget
overrun.
OFFICES IN GREAT FALLS, BOZEMAN, KALISPELL AND SPOKANE
Susan Moyer
3/19/96
Page 2
Please contact us if you have any questions.
Very truly yours,
THOMAS, DEAN & HOSKINS, INC.
iie Phillips P.B.
FAP:mj
K94-46-4
a:susanco.ltr
Encl:
DATE 2/5/96
AGREEMENT DATE: 11/15/95
NAME OF PROJECT CITY OF KALISPELL MT
"WOODLAND COURT PROJECT" MT HOME M94-SG300117/MT-CDBG-94HR-06
OWNER CITY OF KALISPELL
CONTRACTOR A-1 PAVING
The following changes are hereby made to the CONTRACT DOCUMENTS:
Add utility trench construction (electrical, telephone, television) to Schedule III Contract, based on
unit prices as shown on Exhibit A.
Change to CONTRACT PRICE:
Original CONTRACT PRICE: $ 80,056.00
Current CONTRACT PRICE adjusted by previous CHANGE ORDER:$ 80,056.00
The CONTRACT PRICE due to this CHANGE ORDER will increase: $ 22,809.50
The new CONTRACT PRICE including this CHANGE ORDER will be $ 102,865.500
CHANGE of CONTRACT TIME:
The CONTRACT TIME will increase by 12 dUs.
The date for completion of all work will be 42 days after the 1st day Schedule III contract time.
Requested By:
Recommended By:
Accepted By:
Mohl, A-1 Paving
Phillips, P.E., Thomas, Dean & Hoskins, Inc.
Al Thelen, Interim City Manager, City of Kalispell
Woodland Court Project
K94-46-4
31—Jan-96
Schedule III
Contractor: A-1 Paving
Change Order No. 1
EXHIBIT A
Utility trench construction, conduit, pull ropes, bases
ITEM
EST OTY UNIT
IFNIT
u• U ► 1
1. Electric Utility Trench 1850 LF $3.50 $6,475.00
2. Conduit 2" 2000 LF $2.45 $4,900.00
3" 1950 LF $3.45 $6,727.50
3. Pull Rope included in item 3.
4. Set transformer Bases 3 EA $650.00 $1,950.00
5. Sweeps
3" long radius 30 EA $78.00 $2,340.00
2" long radius 3 EA $139.00 $417.00
TOTAL $22,809.50