07-27-83 Parks Comm MinutesPARKS COMMITTEE
CONFERENCE ROOM 9:00 A. X. JULY 27, 1983
Present were Mayor McDowell; Councilmen Vidal, Ruiz, O'Boyle, Saverad, Nystul;
Park Supt. Brent and Engineer Dennis Carver.
Councilman Vidal explained that Supt. Brent has looked into specs for a new
bathhouse. Originally the plans were to build a 4000 sq ft bathhouse, but it
now looks possible to build on the present foundation which is 2600 sq ft
and still comply with State requirements. By raising the foundation to the
same level as the pool, rearranging the space and making all the plumbing
workable, it will accomodate the number of swimmers the pool accomodates.
The Cost Estimate for Bruckhauser Pool and bathhouse has been prepared by Carver
Engineering, William M. Smith & Associates, Inc., and Taylor, Thon, Thompson,
Peterson, Architects and is attached to this report. Total estimated cost is
$523,476.
Councilman Vidal explained that every source of revenue has been investigated
and nothing forthcoming - Flathead County denied the request for funds because
they have to build a new courthouse complex - the school district does not have
funds - the Youth Center group has some money, but is not interested in
putting it into a swim pool - this leaves going to the voters for a General
Obligation Bond. The purpose today is to decide on an amount.
Councilman Nystul reported talked to Kreg Jones with D. A. Davidson and been
advised that they can be hired as an advisor to assist with the resolution
language and financial portion of the bonds.
Question was asked if the voters approve the bond issue and we sell $550,000
and then get some money from another source, what do we do with the excess?
Councilman Nystul stated that it could be used to pay off bonds or put into
escrow until needed.
When construction starts, if anything shows up that needs to be replaced that
is not now visible, change orders will be necessary.
Architects who might be interested are to contact Carver Engineering.
Committee recommended no concession area.
Councilman O'Boyle would go with present size if it is adequate, meets require-
ments and will take care of future needs. O'Boyle stated he is looking at the
future of Kalispell and can face the public better if we prepare now for future
needs.
Final recommendation is to ask for $550,000, red -ace the bathhouse to $170,000 and
add $75,000 for contingencies.
Meeting adjourned at 9:45 A. M.
a
Consulting Engineers
720 Second Street East
Kalispell, Montana 59901
Phone (406) 257-6202
April 25, 1983
Mr. Pieter Drent
Kalispell City Parks Director
City Hall
Kalispell, Montana 59901
RE: Cost Estimate - Bruckhauser Pool Renovation
Dear Pieter,
Civil
Structural
Development
Environmental
Through the association of Carver Engineering, Inc., William M.
Smith & Associates, Inc., and Taylor, Thon, Thompson, Peterson,
Architects the following summary of estimated costs for the
renovation of the Bruckhauser Pool Facilities.is presented as
follows:
1) Enlarge the deck area on three
sides to include foundation walls
for future enclosure with middle
deck drains. _ S 43,000
2) Provide deck area around wading
pool. 8,700
3) Provide new chain link fencing
for new deck area and wading pool area_ 5,000
4) Remove gunite from shallow end and
replace with reinforced concrete.. 42,000
5) Fiberglass entire pool and paint
racing lanes and targets. 50,000
6) Reconstruct _surge .tank and add
valving for automatic make-up water. 6,000
7) Replace filters with automatic
backwash, high rate filter system. 38,000
8) Replace Boiler.
10,000
9)..Automatic chlorine and pH control
equipment;
10) New chlorination and pH equipment.
11) Lower pool deck approximately 4",
replace stainless steel return line and
provide precast stone on top of gutter
opening.
12) Provide eight new ladders..
13) Replace building with 4000 square
foot structure.
14) Architectural and engineering fees @ 8%
Total Estimated Cost
6,500
4,000
47,000
4,500
220,000
S 38,776
$523, 476
The project will include removing all existing deck areas and
replacing with new decks and deck drains. The deck width will be
expanded to provide deck widths of approximately 16'.
Foundations and foundation walls will be necessary to retain the
deck substructure on three sides of the pool. Continuous deck
drains will be placed under the decks and water will not merely
drain to the outside of the deck. Draining to outside of the
deck would require major modifications should you ever choose to
cover the pool or any portion of the pool.
The wading pool area will be provided with concrete decking, the
area will be ,fenced and access provided from the main pool area
or from the exterior.
As a result of recent coring of the shallow end of the pool, it
was determined that the subgrade material was adequatef however,
the lower end cracking may have resulted from the gunite*being
underlain with gravel and placed with minimal reinforcement. It
is recommended that the gunite be removed in the shallow end
bottom and replaced with reinforced concrete.
Fiberglass will line the entire pool area to provide a smooth,
easily maintained surface. The racing lanes and targets can bel
painted on the fiberglass surface..
The steel surge tank in the mechanical room has corroded to the
point that it cannot be repaired. The concrete basin that holds
the surge tank can be modified to replace the steel tank and
valving can be added to provided make-up water.
I
The existing filters were found to be in poor repair and
replacement with a new high rate filter system having automatic
backwash is recommended. Continued use of a renovated filter may
find it ready for replacement within only a few years. A visual
examination of the boiler indicates that its condition is
workable, but its useful days are numbered and replacement is
suggested_ If the budget becomes extremely tight, you may
consider reuse of the above mechanical equipment, but bear in
mind that they will require renovation and that their complete
replacement will come early.
When the decks are removed, it is proposed that the new decks be
placed approximately 4" lower than they now exist. This will
allow easier and less costly addition of'the new gutter stone and
gutter renovations that are necessary to raise the water level in
relation to the'deck area and to provide an adequate skimming
system.
The exiting bath house and mechanical room has an approximate
area of 2680 square feet and the minimum recommended size of the
new bath house facility is 4000 square feet. We recommend that
the entire structure be removed, but to possibly save the
foundation and floor slab in the mechanical room. The bath house
currently is about 2 feet lower than the pool deck and will be
elevated to the same level as the pool. The entire construction
of the bath house must be done wi-th maintenance and durability in
mind.
Sizing of the structure is a variable that should be determined
.by the committee following preparation of the schematics and
prior to preparation of the working drawings. Basic plumbing,
electrical, and hardware items within the structure will not vary
and you should keep in mind that changing the size of the
building from 4000 square feet to 3000 square feet will not
necessarily reflect a proportional savings.
It is my recommendation that the above mentioned estimated figure
(based on $55.00 per square foot) for the bath house be used for
budgeting purposes, and that prior to preparation of final
working drawings and prior to bid, materials be carefully
reviewed to assure.that the necessities for your needs are not
exceeded.
In my recent discussions with you I realize that the building
costs have been a major item of concern. I'm sure part of the
difficulty comes in the cost of removal of the existing building
and the necessity of raising the building floor to match the
level of the pool deck. Again, we recognize the feeling that the
bath house should be a basic, functionable, durable structure and
not a monument and that is the attitude that will be predominant
during the design phase of the project.
-4-
The following schedule will give you an indication of the steps
you will need to take to allow completion prior to June 1, 1984:
May 15, 1988 July 31, 1983
Aug 1, 1983 Aug 31, 1983
Sept 1, 1983
Sept 7, 1983
Sept 21, 1983
June 15, 1984
Design Phase
Regulatory Review
and advertisement
Bid Opening
Award Bid
Construction Phase
The construction period is too long if you consider continuous
work throughout the time shown above. Some portions of the work*
will need to be completed during the warmer weather period in the
spring, and thus the long construction.period.
I'm sure you and the committee will have a number of questions
regarding the above and I will attempt to answer them at the
Committee meeting on Tuesday the 26th.
Sincerely,
CARVER ENGINEERING, INC.
Dennis F. Carver, P.E.
LeRoy E. McDowell
Mayor
P.O. Box 1035
Zip 59901-1035
Telephone (406) 755-5457
THE CITY OF KALISPELL , M O N T A N A
TO: FLATHEAD COUNTY COMMISSIONERS
FROM: KALISPELL CITY COUNCIL
SUBJECT: FUNDS FOR SWIM POOL RECONSTRUCTION
AND NEW BATHHOUSE
DATE: JULY 27, 1983
The City of Kalispell will be placing a request for General
Obligation Bonds on the General Election Ballot on November 8,
1983 for the purpose of reconstructing our swim pool and
building a new bathhouse.
The total estimated cost is $550,000. We are requesting Flathead
County Revenue Sharing Funds in the amount of $100,000. This
will reduce our request from City of Kalispell taxpayers to
$450,000 and have a better chance of passing.
Thank you.
5
Le oy E. McDowell, Mayor
"Vacation City'