2. Award Bid - Willows Stormwater Improvements Project2011" Avenue East PO Box 1997 Kalispell, MT 59903 Phone: 406-758-7720 Fax: 406- 758- 7831 www.kalispell.com Ipublic—works Date: August 27, 2013 TO: Doug Russell, City Manager3R FROM: Keith Haskins, PE, Senior Civil Engineer CC: Susie Turner, PE, Director of Public Works, City Engineer SUBJECT: The Willows Stormwater Improvements Project MEETING: September 3, 2013 BACKGROUND. The Willows Stormwater Improvement Project brings the existing undersized and problematic storm sewer system for the Willows subdivision Lip to current City standards as a requirement for City ownership and maintenance. The project involves installation of 2 stormwate,r treatment devices, pond slope stabilization and grading, installation of 2 skimmer structures in the pond, installation of about 1,250 linear feet of storm main, 6 manholes, an outlet into the Stillwater River, and other related appurtenances and construction activities. Bids were received and opened on August 27, 2013 at 2:00 PM, Four responsive bids were received from local contractors. The bid results follow in order of price: Contractor Total Bid Price Shellinger Construction Co., Inc. $238,350.00 NCC Neumann Construction Co. $242,592.00 LHC, Inc. $297,065.00 Sandry Construction $348,789.00 The engineer's estimate was $346,600 and was developed from bid prices of projects of similar size and scope. References for Shellinger Construction were checked and they were determined to be a responsible contractor, successfully completing prcjects of similar scope and magnitude, STAFF RECOMMENDATIONS: Award the bid for The Willows Stormwater Improvements Project to Shellinger Construction Co. Inc. in the amount of $238,350.00. ACTION REQUESTED: Motion to award The Willows Stormwater Improvements Project to Shellinger Construction Co., Inc. in the amount of $238,350.00. FISCAL EFFECTS: The project will be funded by a combination of a Special Improvement District, a State Revolving Fund Loan, Storm Sewer Impact Fees, and the Storm Sewer Fund (953-Willows Stormwater Improvement Project). TERNATIVES: As suggested and approved by the City Council. i isie Turne urne sie , P. E. Keith Ha ins, PE Public Works Director Senior Civil Engineer ATTACHMENTS: Bid Analysis 4 W a w ry n $ 8 S S r G %A 69 69 69 b3 69 69 V! n g S S b s9 M w V9 N" 49 iA (A w in ci eA a 6A N ?A ci 6A a vi 69 rn 69 v o 69 69 6pp9 6pp9 fpoFl 6pp9 5oF1 b9 69 b9 69 VI F 1 V} O S S O O C C] pw C] L47 Cp7 'Qp�J� 1p.1 S N �CpS pNU Q. Mpp Npd 6po9 fpoR Hpb3 6pp9 VpOi 6A 691 V Vpp1 7 VI O 69 N 6.9 O, EpG9 O S O c7 O P O P P 4 4 O o P P a C U r P Dcri ll� � co r� eo r� o D b N M N 00 4'i h 6 n fV (V P M Yi 64 W [j r�i b3 L9 69 U 69 b9 6A V +A A k6 69 69 6 69 � O p p S S S p S S p S p S p S pp 4 pp P S S p 6 pp O O CDC Vh c9 Vi 69 sp9 H3 FH GpAf V3 ?AA 660 (ni IA (A pA C �y g 25 g Z5 g g N G O d SpgG4 S g g S p�pSS A CS CgQ p$ Gg pg Cg 7. Pi Yl n MS An IA aA r'3 Vol V) N V! N N w eA V] N 0 6 G w O V9 Is y 69 69 dA 69 iA E9 69 6A 4] 69 69 G0 6A W t9 .l. y O pp pO P P CC�� P P pp 4 pO O pp P pp P pp O pp O O F+ pp p � n 8 pp P � pp p C Z�� 69 69 ii] fA fA W V3 69 E9 A dH 69 A eq 69 r c. d rrrr�� .-1 .w] J LQt] W rr�� .-1 rr��77 .•7 W W x H a w z x w Gpa V La �o� ❑a❑a�1❑si in, u IL aW 0 .3F u 3 U 'a Sf awl w �a E z J z D d C1 W ❑x a F F F v F y �v�'�'�n����nn F F F F F F n w� p -z�zz �t-.❑ z mro m zu�z��zaz?x�.zW �n 'A mua~• �❑� � ,,,w'-'ash �❑z � � Sao F¢" pFq U �.Zui�,a 4? ¢ W a^ A? �C7� Xp�zZF-. O� q a ❑ xw¢wQ]¢ ❑ F (] N F �p�U,�ai eN�Ne�� Q �L a' F •E p q' W Q ¢ 1-• Q � Q' y`j `C sx+ C' �t�7 Q pC C' vi�U�T/a� z a+ w .7�C7c4Z�5z vx, vxi x Wri1�ZZ3z vxid � vxiRvxi¢ai W v�iI�- z ySi Zr—y zZ�D¢z D Z �AA�n qWa apQ 0oz pQd'Z z eZ ropp6V;LRV-) W vspp ¢ W o o o a p� E,. n N N N N n N N N rY C•� M1 --save"l- August 28, 2013 Keith Haskins, P.E. City of Kalispell 201 First Avenue East Kalispell, MT 59901 RE: City of Kalispell Willows Subdivision Stormwater Improvements WPCSRF Program #: C307191 Keith, This letter will acknowledge receipt on August 28, 2013 of the request to award bid and supporting documents for the above -referenced project. You may consider this letter authorization to award the construction contract to Schellinger Construction Co. Inc., the low responsive, responsible bidder. The total amount of the contract is $238,350.00 of which $238,350.00 is eligible for SRF loan assistance. We also approve Addendum No. 1 for the above -referenced project and have enclosed an approved copy for your records. This authorization to award is provided contingent upon the adoption of a bond resolution that signifies the borrower is eligible and authorized to borrow loan funds from the Montana State Revolving Fund. Construction may now begin at your convenience. Please furnish this office with one copy of the authorization to the contractor to begin construction and one copy of the executed contract documents as described in the enclosed Department of Environmental Quality (DEQ) Policy Statement No. 9 dated September 18, 2002. The borrower must forward copies of subcontracts and purchase agreements/orders, which the project contractor(s) and the architectural and engineering firm(s) execute with Minority and Women Business Enterprise (MBEIWBE) firms, to the undersigned project officer. If additional MBEIWBE subcontractors or purchases are made after work has begun, this information is required and should be forwarded to the project officer within 15 days of their execution_ The approved MBEMIBE participation for this project is listed below: MBEIWBE Contractor Approximate Amount Kootenai Surveyors Inc. (WBE) $3,600.00 The contract documents require the contractors maintain adequate fire and extended coverage (where approp(ate), worker's compensation, public liability and property damage, and "all risk" builders risk insurance (including blasting where appropriate) during the construction phase of City of Kalispell — Willows Subdivision Stormwater Improvements Page 2 the contract. Please send the workers` compensation and insurance certificates and performance and payment bonds. Also assure that contractor's wage determinations are properly posted: at the construction site. We will be monitoring construction progress and are planning to attend the preconstruction conference. Please advise us as soon as the preconstruction conference is scheduled. If any questions arise please call me at 444-5323. Sincerely, Jerry Paddock, P.E. Environmental Engineer Technical & Financial Assistance Bureau Enclosure: Policy Statement No. 9 cc: Jeff Cicon, PE, Morrison Maierle, Inc., Kalispell POLICY STATEMENT NO. 9 TO: State Revolving Fund (SRF) Loan .Borrowers and Consultants FROM: Water Pollution Control .Revolving Fund Technical and Financial Assistance Bureau Planning, Prevention and Assistance Division DATE: September 18, 2002 SUBJECT: Executed Contract Documents for SRF Projects Pur W This policy statement is intended to ensure that all necessary executed contract documents for State Revolving Fund (SRF) loan projects are submitted to this office. Discussion A review of contract documents is made to ensure compliance with approved project specifications, and the applicable laws and regulations. The documents are to be submitted for inclusion in the approved specifications following award of the contract and prior to the initiation of construction. One (1) copy of the following executed documents should be submitted to the Technical and Financial Assistance Bureau, WPCSRF Program Staff: Executed Agreement 2. Notice to Proceed 3. Workers Compensation and Insurance Certificate including: a) Fire and extended coverage (if appropriate) b) Public liability and property damage c) All risk builders (including blasting where appropriate) 4. Performance and Payment Bonds Further, copies of subcontracts and purchase agreements/orders signed with Minority and Women Business Enterprise (MBEIWBE) firms should be forwarded to the Technical and Financial Assistance Bureau within 15 days of award of contract. If additional subcontracts or purchases are made after work has begun, the information should also be forwarded.