05. Resolution 4292 - Teton Terrace Change OrderRESOLUTION NO. 4292 A RESOLUTION TO ALTER AND AMEND THE PLANS AND SPECIFICATIONS OF CONTRACT WITH SANDON CONSTRUCTION COMPANY ON THE TETON TERRACE PROJECT. WHEREAS, the City on July S, 1996 did enter into a contract with Sa ndon construction Company of 1600 Montana 35 East, Kalispell, Montana for construction of the Teton Terrace project, and WHEREAS , upon the advice and recommendation of Ian Bailey, who is the City's consultant on said project, certain changes and alterations of design and specifications have been found necessary and advisable and in the best interests of the City; and said changes and alterations could not have been necessarily foreseeable when the original design and specifications were prepared on this phase of the construction of the Teton Terrace project, and said changes are contained in Exhibit "A",, attached hereto and are by this reference made a part hereof; and WHEREAS, it appears in the best interests of the City to approve said changes and alterations, NOW THEREFORE, pursuant to the provisions of Section 7-5- 4308(1) MCA be it hereby resolved: 1 , The Alterations and modifications of the specifications and plans of the contract between the city of Kalispell and Sandon Construction Company, dated August 19, 1996, as set out in Exhibit "At' attached hereto are hereby approved, and 2, As soon as the price to be paid for said alterations and modifications are agreed to in writing, signed by the contractor, as hereby approved by the council, this approval thereof shall be in effect, PASSED AND APPROVED BY THE CITY COUNCIL AND MAYOR of THE CITY of KALISPELL THIS DAY OF , 1996, Douglas D. Rauthe, Mayor ATTEST: Debbie Gifford, CMC Clerk of Council N .61 fro ..0 d -W .r W f ;.I —4 ► F V V 1 THOMAS, DE & HOSKINS INC. ENGINEERING CONSULTANTS 690 'forth Nl rldar: Su4$ ' CA & Kaliscoll, V0-,ta,,,1 599�Cl • ;405; 75.E.5265 ■ FAX (406) 752-5230 MEMORANDUM August 20, 1996 To: Susan Moyer FROM: Ian Bailey, P.E. RE: Teton Terrace Development Change order No. 1 Change order No. I includes labor and rnatenials for two separate items l . Electrical utility conduit and trenching from the transformers to the meter base locations at each residence. 2. An additional 6" gate valve to be used with the fire hydrant relocation on Iris Court. Justif catiorn is as follows: l . The M" sftallation of electrical service trench and conduit has been moved from the act -al home construction portion of the project to the infrastmetore portion of the project to avoid requiring each home builder to dig electrical service trench through the graded and seeded common area. The change will also consolidate the electrical work der a Single contractor versus up to 11 separate contractors. Are ultimate pro,�ect sav wgs should be realized sm€ce the infrastructure contractor can install many of the service Ues in a common trench with tither electrical service lines and the backbone electric lines. The change will result in less trenching and less disruption of finish graded areas. 2. The 6" gate valve is required at the fire hydrant relocation on Iris Court to avoid disruption of service and disinfection procedures on the existing min serving Hawthorn West residents. There is no way to shut down the existing main close to the new constriction. The entire existing mafn will require a 24 hour disinfection process if the existing valve is removed. The expense of the new valve is outweighed by the cost of temporary services disinfection and aggravation to water users in Hawthorn west. The contractors prica for the above items are reasonable and consistent Frith the original bid prices. We rec+omrnend approval of this Change Order. Post -it" Fax Note 7671 c'2s0 q2:� Lges op Phone # Phone r� ax x` THOMAS, DEAN & HOSKINS, INC. i Ian ,I} Ba y, P,E. KALISPELL. SPOKANE AND LE ISTON AL CC 4Y_ Z.12- CITY OF KA.I,ISPELL Seto � D MEMO AUGUST 20, TO: IAN BAILEY j'+ �o 7s:;2 ..5,2, 3 a FROM: Carol Grigg FOR SUSAN MOVER RE: SANDON" S CHANGE ORDER NO. 1 — (¢ 4° f'j 3 PER YOUR FAX ON 8/19/96 REGARDING TIHE CHANGE ORDER FOR ° ELEC. SERVICE CONDUIT AND TRENCH PLUS AN ADDITIONAL GATE VALVE. 3}� I TALKED WITH SUSAN MOVER 8/20/96 REGARDING THIS C.O., N AND THERE SHOULDN"T BE A PROBLEM GETTING TIC 2 COUNCIL"S APPROVAL, BUT SUSAN HAS REQUESTED THAT YOU (y PREPARE A MEMO AS TO WHY AND HOW TIC CHANGE ORDER � CAME ABOUT, I.E., PACIFIC POWERS. REQUEST THAT THE ELEC. a METERS WILL BE LOCATED FROM THE FRONT OF THE HOUSES TO ALONGSIDE, ETC., AND WHY THE ADD FOR 6" AUXILIARY = GATE VALVE AND -VALVE BOX, IN -PLACE. PLEASE PREPARE THE MEMO ASAP AS THE NEW CITY MANAGER HAS REQUESTED THIS INFORMATION BEFORE THE CLERK OF COUNCIL CAN PUT IT ON THE WORKSHOP AGENDA. PLEASE FAX TOME AT 758-7739. COUNCIL'S WORKSHOP MEETING 8/26/965 BUT WON'T BE APPROVED LJN'TIL COUNCIL MEETING 9/9/96 (REG. MONDAY IS A HOLIDAY, SO MEETING MOVED UP A WEEK). WHAT DO YOU WANT TO DO REGARDING SANDON WANTING TO DO THE WORK NEXT WEEK?? THANKS.. ASAP THANKS u � - r_a..E� '�•t�s� 6-' .� .•;�•. :..xr{., " `: f-•:=•t 2•. •r.y Rj�yy:..G��:r�•. '.�.-sue • s:;y�;t. `r�.:�`.'- _ _' THOMAS, DEAN & HOSKINS INC. ENGINEERING CONSULTANTS 690 North meridian, Suite 1 * 1 ' KartupU , bltm dw ti 5991 - (4 ) 702.5240 # rAX (" 752-' FA�CSIMII.F. f:nVF,l2 SHF;FT DATE: � 46 L9 T' 7 coa .. i w.� r I �dsx F Thocnw, oew & Howm inc. 690 North Meridian,, SVft 101 ""Ila MT 59WI FAX No: (4W) 7W-523D 1 d-l'o / I/ I Cv ! � : tC 3 0 V+ c ho� %--a OFFICES IN GREAT FALLS, BOZEMAN, KALISPELIA D SPQKANE DATE ,9,nPst I9 199G �� AGREE&MNT DATE: Mv 1226 40 NAME OF PROJECr. . - ��DE��QPMENT OWNER:....Q.. .. KALISPEIJL CONTRACTOR: _ _S NDt)!N C4?3�STRUCiIOi�t CQMPANY. INC. The following changes are hereby made to the CONTRACT DOCUMENTS: Add. 0" AuxlHary Crate Valve & Valve Box, In- &w I . ttpflfflizfi aEi .. ,gym: 535 L.F. Electrical SaMce Trmch, In -place s Add. 968 L.F. 30 El=umal Condu1 y In -place Ic e4p 44 Re U-S e- 3pl;L Existing 611 gate valve to be left i� place to mainWn baaerioiogcal integrity of adjacent existing main.} Elocftic sorvice work is adcled to fateilitate mbscq=nt home corotmcdon bids and avoid excavation of fi&sh gmded commn areas. Change to CONTRACT PRICE: Elvarical Service Treeach, In Place 535 LF (p $2.00ALF $ 1,t?70.00 3" EleCtT1C&1 Conduit, In Place 968 LF 9D $4,75/LF 4,598.00 6" Auxilii�rry Crate Valve &Valve Box, In Ph.ce 1 EA @ $630/EA 0.00 TOTAL $ 619$.00 FWVf ::. - IL mm . - -Z� 3 W.V �: ��� - � � 1111,1111 --- ip 12L52- $5....7 � went CONTRACr PRICE adjusted by prcyiom CHANGE ORDIER: No C jgW3p. The CONiRACT PRICE due'to this CRANGE ORDER will be m"emased by: The new CONTRACT PRICE imIuding this CHANGE ORDER will be $197.823.76 01"'ANGE of CONTRACT TIME: The CONTRACT TIME will increase by Q.-days. The date for Completion of all work will remain October 17, 19964 7* L, ." �10 '.J mt Ian Bailey-O P.B., Thomas, Dean & Hoskins, Inc. Z L Susan Moyer, Project City of Kalispell Grog SaWon, Sandon ConWuction Co.,, Inc. TOTRL P.03