1. Presentation - Proposals for Development of North Fire StationKALISPELL FIRE DEPARTMENT
Randy Brodehl - Fire Chief
Jim Stewart - Assistant Cbief/Fire Marshal
Dee McCluskey — Assistant Chief/Operations
Date
REPORT
FROM
SUBJECT
MEETING DATE
BACKGROUND:
3/4/2004
Honorable Mayor and City Council
Randy Brodeh), Fire Chief
PO Box 1997
312 First Avenue East
Kalispell, Montana 59903-1997
(406) 758-7760
FAX: (406) 758-7952
Proposal presentations for the development of a north fire station
3/8/2004
The City of Kalispell solicited proposals for the project development of a north fire station. Five
proposals were received. After an extensive review process, two of the proposals were determined
to be the most complete, with the consultants having the experience and ability to complete the
project in an effective and timely manner. These two consultant teams are prepared to make
presentations to the Council on March 8th, regarding the process each is proposing. Presentations
are limited to 45 minutes, including a question and answer period.
The consultants chosen are:
Grover and Company, located in Whitefish, partnered with C+RA from Cincinnati, Ohio. Grover
and Company is a new business but C+RA has a long architectural history, with fire station design
being their primary focus. In the past seven years, C+RA has designed and managed over 45 fire
stations, so are very prepared to make this a successful project.
Architects Northwest, led by Don Counsell has been in Kalispell for fourteen years. They have been
the primary architects in projects such as the current expansion of Flathead Valley Community
College, Glacier Park International Airport Expansion, Lincoln County High School, and the
Kalispell Christian Center. They have teamed with Peck, Smiley, Ettlin (PSE) of Portland, Oregon.
PSE has completed thirty-five fire stations, and have others in the construction phase at this time.
Each of the teams will present their plan for providing the following required services:
1. Identify at least one location for a fire station that would address response needs as explained
by the Insurances Services Office, Inc., and provide maximum service to our community,
given the available resources. It is assumed that additional stations are needed, and response
standards will be as addressed in NFPA 1710.
2_ Develop the following process:
a. The City has not secured a funding source for this facility and the necessary staffing.
This request includes developing a logical process and timeline for funding, including
any necessary steps needed to process a bond issue or other successful funding
strategy.
b. Provide a sequential plan that identifies a logical sequence of development and
construction, implementation strategy, and period beginning with funding
confirmation and ending with facility acceptance.
c. Facility will be designed to include the following:
i. Drive through apparatus bay for two engines and two ambulances.
ii. Vehicle exhaust system.
iii. Dispatching system designed to work with the current dispatch system.
iv. Fire sprinkler system.
v. Police work station for one officer that includes an interview area. (This area
could double as the conference room.)
vi. Fitness room and budget for training equipment.
vii. Office area with two computer workstations for fire personnel.
viii. Conference room to seat 12 people.
ix. Work area with 3 additional workspaces for firefighters.
x. One or two person resting quarters to house up to S personnel.
xi. Kitchen and dining facilities.
xii. Day room.
xiii. Laundry facility.
xiv. Hose drying room with electric or gas hose dryer.
xv. Turnout washing area and washing machine.
xvi. Exterior public restroo.
xvii. This list is representative of the layout and equipment expected but is not
limited to the above.
d. Incorporate dispatch and communications systems to match the existing system used
by KFD.
e. Incorporate the management information systems to match the existing system used
by KFD.
f. Develop a marketing strategy, periods, and timelines as part of the plan. This
information should be based on probable available funding, and should develop a
strategy that fits the community needs. This plan should also identify who needs to
be involved and their roles.
Estimated Project Timetable
it is anticipated that the facility construction will be completed in 2006.
"Assisting our community in reducing, preventing, and mitigating emergencies. "
Fiscal Impac#
Typically, a project of this nature would be approximately 10 percent of the facility cost. A
representative facility would be a fire substation completed for the City of Billings in August of
2000. The cost for this 9300 square foot building was $784,346.92. Factoring an annual three
percent inflation increase over the past three years, the cost to develop and oversee this plan will be
approximately $125,000. $104,000 has been set aside to date, for this project. The additional
necessary funding would be included as part of the funding strategy.