2. Wells Fargo Building UpdateCi"ty of Kalispell
Post office ,fox. 1997 -- Kalispell, Montana 599 -1997 µ Telephone 75 -7 Fax - 75 -77 8
REPORT TO: Honorable Mayor and City Councfl
FROMP James H. Patrick, City Manager
SUBJECT: Update on Remodeling the former Wells Fargo Bank Building
MEETING : July 14, 200
BACKGROUND: The purpose of this item is to update Council on the plans for the remodel
of the former Wells Fargo Bank building. Chad Grover will be in attendance to show the current
plans. Construction costs have increased by more than twenty percent in the last year. fart o
the discussion will be looking at options for remodeling the facility.
1. Increase the remodel budget.
2. Phase it in over two years and phase in the move.
3. Leave as is and only move in as many Department"s that will fit.
Your guidance will be greatly appreciated.
Respectfully submitted,
James H. Patrick, City Manager