REPORT TO: Mayor and City Council
FROM: James C. Hansz, P.E., Director of Public Works
SUBJECT: Award Bid-2009 Sidewalk and Curbing Contract
MEETING DATE: May 18, 2009
BACKGROUND: Three bids were received for the 2009 sidewalk and curbing contract that is used for
replacements of sidewalks by residents and businesses participating in the 50/50 sidewalk program. In
order to properly analyze the bids, typical project costs were estimated for installation of 250 square feet
of residential sidewalk replacement, 250 SF of residential in -fill, and 250 SF of downtown business
frontage sidewalk. These are summarized in the attached bid analysis. The analysis shows that for typical
residential work done in the City (50/50 program records for the period 2005-2008 show that 92% of
work was residential), the bid submitted by Sandon Construction results in the most favorable price for
the largest number of Kalispell citizens utilizing this contract for their sidewalk replacement needs.
The recommendation is to award the bid to Sandon Construction.
ACTION REQUESTED: AT CITY COUNCIL MEETING OF MAY 18", MOTION TO
AWARD OF THE 2009 SIDEWALK & CURBING BID TO SANDON CONSTRUCTION
OF KALISPELL.
FISCAL EFFECTS: Project expenditures will be on a 50/50 basis with property owners and may total
$35,000 of City Gas Tax funds for the 2009/2010 fiscal year, with an additional $19,000 carried over
from the 2008/2009 fiscal year.
ALTERNATIVES: As suggested by the City Council
JatZe�-C Hansz, P.E.
Director of Public Works / City
Attachment: Staff Memo
ebb
Interim City Manager
May 8, 2009
To: James Hansz, PE, Director of Public Works/City Engineer
From: Fred Zavodny, P 16JI t a a r
Re: 2009 Sidewalk & Curbing i sis and Recommendation
This contract is designed to assist property owners wishing to replace or construct new infill sidewalks
adjacent to their property utilizing the 50150 cost sharing program. The 50/50 cost sharing program
was established by the City Council to encourage sidewalk replacement and infill by equally dividing
the cost between the City and the property owner. The City has $19,000 remaining in the current
budget for 50150 sidewalk work. A $35,000 appropriation is requested for the 2009/2010 fiscal year.
Bids for Sidewalk and Curbing Construction for the year ending December 31, 2009 were opened on
Thursday, May 7, 2009. Bids were received from Sandon Construction, T&M Contracting, and Knife
River. All bids were in order and contained the required Bid Bond.
The Bid Price from each bidder to replace an average 250 SF residential sidewalk is as follows:
Bid Item
Sandon
Knife River
T&M
Sidewalk Removal
312.50
375.00
300.00
Concrete Placement
1375.00
1875.00
1282.50
Landscaping
250.00
225.00
3500.00
Total
$1937.50
$2475.00
$5082.50
The Bid Price from each bidder to install an average 250 SF infill residential sidewalk is as follows:
Bid Item
Sandon
Knife River
T&M
Concrete Placement
1375.00
1875.00
1282.50
Landscaping
250.00
225.00
3500.00
Total
$1625.00
$2100.00
$4782.50
The Bid Price from each bidder to replace an average 250 SF downtown business frontage sidewalk is
as follows:
Bid Item
Sandon
Knife River
T&M
Sidewalk Removal
312.50
375.00
300.00
Concrete Placement
1375.00
1875.00
1282.50
Total
$1687.50
$2250.00
$1582.50
A review of performance during the period 2005 through 2008 indicates that 92% of the work
completed under this contract is residential type 50150 sidewalk replacement. Therefore, the bid
analysis is residential oriented. I recommend the bid for Sidewalk and Curbing Construction for the
Year ending December 31, 2009 be awarded to Sandon Construction Company Inc.