13. Award Bid - Sidewalk & Curbing ConstructionMEMORANDUM
Date: June 11, 1998
To: City Manager and City Counc' ers
From: Public Works Departmen
Re: 1998 Sidewalk and Cur id Analysis and Recommendation
This contract is intended primarily for residents and businesses wishing to take advantage of the
annual sidewalk and curbing construction program. Bids were received from Pack and Company and
Sandon Construction. Both bids are in order and contain the required bonding.
The major components of the bid are as follows:
Bid Item
Unit
Pack
Sandon
1997 Price
4" Sidewalk
SF
$2.90
$3.30
$3.30
6" Sidewalk
SF
$3.00
$3.50
$3.50
Curb & Gutter
LF
$7.00
$10.00
$8.00
Straight Curb
LF
$7.25
$9.00
$8.50
Pack and Company was the low bidder across the board. Pack's prices reflect an average reduction
in cost of 12% over last years prices. The Public Works Department recommends the contract be
awarded to Pack and Company.