07/16/05 Construction Progress and Inspection ReportU.S. Department CONSTRUCTION PROGRESS AND INSPECTION REPORT
of Transportation
Federal Aviation AIRPORT GRANT PROGRAM
Administration
Name: Kalispell City Airport: Kalispell, Montana
umD npprovea azu-uuo.)
Period Ending (soturday)
July 16, 2005
Project Number
Project Description: Construction of New Contractor's Name: Schellinger Construction Co., Inc.
Taxiways, Aircraft Parking Apron, New Taxiway P.O. Box 39
Marking and Markers, New Access Road Columbia Falls. MT 59912
1. Rough Estimate of Percent Completion to Date of Construction Phases (Include items such as clearing, grading, drainage, base, surface, lighting. etc.)
Final/
Item
Completed
Unit
Percent
No.
Quantity
Quantity
Unit
Description
Completed
125
23,610
15,000
CY
Topsoiling, Stripping, Stockpiling and
Placing (T-905)
63.5%
2. Work Completed or In Progress This Period
About 5% of the project has been completed. This is a cost based estimate from planned vs. final quantities.
3. Brief Weather Summary This Period Including Approximate Rainfall and Periods of Below Freezing Temperature (On earthwork jobs include soil
conditions)
Started construction on July 14, 2005. Weather has been mostly sunny with highs in the mid 80's and lows in the 50's. Winds
have been out of the southwest at about 10 mph.
4. Contract Time
45 Day Contract
No. Days
Charged
To Date
3 Days Charged
0 Days Shutdown
DAYS CHARGED
3 Calendar Days
Last Working
Day Charged
(Date)
Saturday
ulv 16. 2003
5. Summary of Laboratory and Field Testing This Period (Note failing tests and any
retests. Summarize out -of -tolerance material. Identify material subject to pay reduction.)
RPR checked benchmarks for elevation and was on -site part-time during this
period.
6. Describe Anticipated Work by Contractor for Next Period
Schellinger will continue to strip topsoil from Apron, Taxiway, and surrounding drainage areas. Schellinger is to prepare the west
side of the two new "T" hangers for a staging area for the hanger construction crew. Kootenai Surveying is planning to start
construction staking the Apron, Taxiways and Storm Drainage. Contractor plans start installing storm drain.
7. Problem Areas/Other Comments (Revisions to plans and specifications approved or denied, delays, difficulties, etc. and actions taken)
None.
SPONSOR'S INSPECTOR OR REPRESENTATIVE
Date Typed or Printed Name and Title Signature
July 16, 2005 Brandon M. Theis, E.I. — On -Site Representative
FAA FORM 5370-1(8-89) Supersedes Previous Edition FAAIRPORTMALISPELL CITY-2003\NORTH END SURFACING\contadmin\progress-rpts\PR#t.doc
U.S. Department of Transportation CONSTRUCTION PROGRESS AND INSPECTION REPORT
Federal Aviation AIRPORT GRANT PROGRAM
Administration
Name: Kalispell City Airport: Kalispell, Montana
um Hpprovea zizu-uuo.)
Period Ending (Saturday)
July 23, 2005
Project Number
Project Description: Construction Of New Contractor's Name: Schellinger Construction Co., Inc.
Taxiways, Aircraft Parking Apron, New Taxiway P.O. Box 39
Marking and Markers, New Access Road Columbia Falls. MT 59912
1. Rough Estimate of Percent Completion to Date of Construction Phases (Include items such as clearing, grading, drainage, base, surface, lighting, etc.)
Final/
Item
Planned
Completed
Unit
Percent
No.
Quantit
Quantity
Unit
Description
Completed
101
1
0.5
LS
Mobilization (Special Provisions)
(Shall not exceed 5%)
50.0%
102*
14,010
10,000
CY
lUnclassified Excavation (P-152)
71.4%
104
1,772
553
LF
18" RCP Class III (D-701)
31.2%
106
7
1
EA
48" Storm Drain Inlets (D-751)
14.3%
115
2
2
EA
Catch Basin Removal
100.0%
116
36
27
EA
Tie -down Removals
75.0%
125*
23,610
15,000
CY
Topsoiling, Stripping, Stockpiling and Placing
(T-905)
63.5%
*Estimates based on field observations. Actual measurements for these quantities will be surveyed in the cut by Kootenai Surveying.
2. Work Completed or In Progress This Period
About 10% of the project has been completed. This is a cost based estimate from planned vs. final quantities.
3. Brief Weather Summary This Period Including Approximate Rainfall and Periods of Below Freezing Temperature (On earthwork jobs include soil
conditions)
Weather has been mostly sunny with highs in the mid 80's and lows in the 50's. Winds have been out of the southeast at about 10-
20 mph.
4. Contract Time DAYS CHARGED 5. Summary of Laboratory and Field Testing This Period (Note failing tests and any
45 Day Contract 10 Calendar Days I retests. Summarize out -of -tolerance material. Identify material subject to pay reduction.)
No. Days Last Working Several soil density tests have been performed on unclassified excavation and
Charged Day Charged embankment. One failing density test was taken at Station 12+00 of Taxiway
To Date (Date)
10 Days Charged Saturday A'. subgrade is pumping at this location and will need special attention.
0 Days Shutdown July 23, 2003
6. Describe Anticipated Work by Contractor for Next Period
The Contractor will continue to excavate to subgrade elevation over the Apron and Taxiways. Storm Drain installation will
continue throughout the period. P-154 (subbase) is planned to arrive onsite on Thursday for Taxiway `A' south and the Apron.
7. Problem Areas/Other Comments (Revisions to plans and specifications approved or denied, delays, difficulties, etc. and actions taken)
After striping the topsoil from the southern end of Taxiway `A', the underlain subgrade became weakened and started to pump
severely in several locations. Different remedies are currently being utilized to firm up the subgrade to provide support for the new
Taxiway section. Further efforts over the course of the next period will be taken in improving these areas along with close
observations and monitoring of adjacent areas to assure that the problem does not worsen.
SPONSOR'S INSPECTOR OR REPRESENTATIVE
Date Typed or Printed Name and Title Signature
July 23, 2005 Brandon M. Theis, E.I. — On -Site Representative
FAA FORM 5370-1 (8-89) Supersedes Previous Edition FAAIRPORTSWALISPELL CITY-2003\NORTH END SURFACING\contadmin\progress-rpts\PR#2.doc
uain nanrovea uzu-uuoo
U.S. Department CONSTRUCTION PROGRESS AND INSPECTION REPORT Period Ending (saturday)
of Transportation
Federal Aviation AIRPORT GRANT PROGRAM July 30, 2005
Administration
Project Number
I Airport Name: Kalispell Citv Airport: Kalispell. Montana I
Project Description: Construction of New Contractor's Name: Schellinger Construction Co., Inc.
Taxiways, Aircraft Parking Apron, New Taxiway P.O. Box 39
Marking and Markers, New Access Road Columbia Falls. MT 59912
1. Rough Estimate of Percent Completion to Date of Construction Phases (Include items such as clearing, grading, drainage, lease, surface, lighting, etc.)
Item
No.
Planned
Quantity
Final/
Completed
Quantity
Unit
Unit
Description
Percent
Completed
101
1
0.5
LS
Mobilization (Special Provisions)
(Shall not exceed 5%)
50.0%
102*
14,010
12,000
CY
Unclassified Excavation (P-152)
85.7%
103
1,251
625
SY
Remove Existing Asphalt pavement (P-101)
50.0%
104
1,772
400
LF
18" RCP Class III (D-701)
22.6%
106
7
1
EA
48" Storm Drain Inlets (D-751)
14.3%
109
33,418
10,483
SY
Subsurface Separation Fabric (P-670)
31.4%
110
11,139
3,000
CY
Sub radeMaterial(P-154)
26.9%
115
2
2
EA
Catch Basin Removal
100.0%
116
36
27
EA I
Tiedown Removals
75.0%
125*
23,610
10,000
CY I
Topsoiling, Stripping, Stockpiling and Placing (T-905)
42.4%
CHANGE ORDERS:
1-1 3,273 1322 CY Muck Excavation & Haul 40.4%
1-2 3,273 1322 CY Fill Replacement in Sub -excavated Areas 40.4%
'Estimates based on field observations. Actual measurements for these quantities will be surveyed in the cut by Kootenai Surveying.
2. Work Completed or In Progress This Period
About 30% of the project has been completed. This is a cost based estimate from planned vs. final quantities.
3. Brief Weather Summary This Period Including Approximate Rainfall and Periods of Below Freezing Temperature (On earthwork jobs include soil
conditions)
Weather has been mostly sunny with highs in the mid 80's to lower 90's and lows in the 50's. Winds have been out of the
southeast at about 10-25 mph.
4. Contract Time DAYS CHARGED
45 Day Contract 17 Calendar Days
5. Summary of Laboratory and Field Testing This Period (Note jailing tests and any
retests. Summarize out -of -tolerance material. Identify material subject to pay reduction.)
Soil density testing has been performed on P-154 and P-152. Random
No. Days
Last Working
Charged
Day Charged
elevation checks have been performed on the Storm Drain `A' during
To Date
(Date)
17 Days Charged
Saturday
installation to assure grade has been met.
0 Days Shutdown
Julv 30. 2003
6. Describe Anticipated Work by Contractor for Next Period
The contractor plans to continue hauling in and placing P-154 for the Apron and Taxiways on the southern portion of the project.
The contractor plans to finish installing the Storm Drain along alignment A and also being installing some of the 12" diameter
lateral connectors. Subgrade "Dig -outs" are scheduled to continue to take place to remove pumping subgrade material along
Taxiway A, B, C, D & E.
7. Problem Areas/Other Comments (Revisions to plans and specifications approved or denied, delays, difficulties, etc. and actions taken)
We are currently performing "Dig -outs' in the areas where subgrade pumping has occurred. These areas are very sensitive and are
beiu monitored closely. A Chance Order was administered to account for the work of di)?Rin)z out the pumping subgrade areas.
SPONSOR'S INSPECTOR OR REPRESENTATIVE
Date Typed or Printed Name and Title Signature
July 30, 2005 Brandon M. Theis, E.I. — On -Site Representative