03. Bid Award - Armory Well Generator ReplacementREPORT TO: Mayor and City Council TO: Susie Turner, P. E. FROM: Mark Crowley, Construction Manager SUBJECT: Contract Award — Armory Well Generator Replacement Project MEETING DATE: May 7, 2012 BACKGROUND: Armory Well is one of five production sites which produces water for Kalispell's lower water zone. Only four of the production sites in the lower water zone have backup generators. During power outages it is essential to have Armory Well online to meet the demands in the water system. This project replaces the old and out of service generator at the Armory Well site with a new diesel generator. The new generator will allow the City to maintain water production and fire flows in the event of a power outage. The City advertised an Invitation to Bid on April 26, 2012, and received three Bids from the following local contracting firms. The Bids are as follows: American Electric, Inc. $69,200.00 Nelson Electric, Inc. $62,219.00 Northwest Power Systems, LLC $64,900.00 The bid from Nelson Electric was deemed to be non -responsive because specified testing and safety features were not included in the bid price. Based upon reference checks, bid specification submittals, and a discussion with the Bid contractors, Public Works Department staff recommends the contract be awarded to Northwest Power Systems, LLC. ACTION REQUESTED: At Council Meeting May 7, 2012— Motion to award the Armory Well Generator Replacement Project to Northwest Power Systems, LLC. FISCAL EFFECTS: The Armory Well Generator CIP has a Fiscal Year 2011/2012 budget of $90,000 and is managed within the Water Operation Budget. ALTERNATIVES: As suggested by the City Council i me , l;. E. CharlieLball Interim Pubf is Works Director Interim City Manager