01. Council Minutes - Regular Meeting - March 19, 2012March 23, 2012 REPORT TO: Mayor and City Council FROM: Fred Zavodny, Project Manager SUBJECT: Award Bid — Colorado Street Water System Improvement Project BACKGROUND: The Colorado Street Water System Improvement Project connects/loops the dead end water mains on Colorado Street to the overall water distribution system. Additionally, the project will replace an existing inadequate 2" water main with a standard 8" water main. These improvements will provide dependable fire flows, water pressure levels, and improve water quality to the residents along Colorado Street. Bids were opened on Wednesday, March 21, 2012. Six responsive bids and one non- responsive bid were received. The Bid results for the Colorado Street Water System Improvement Project from the responsive bidders are as follows: CONTRACTOR BID NCC Neumann Construction, Kalispell, MT $ 178, 131.00 Thompson Contracting, Libby, MT $ 178, 788.00 Sandry Construction, Bigfork, MT $ 193, 284.00 LHC Inc., Kalispell, MT $ 200, 631.25 Les Schlegel Enterprises, Kalispell, MT $ 215, 190.20 Settle Contracting, Kalispell, MT $ 243, 114.20 STAFF RECOMMENDATION: Award the bid for Colorado Street Water System Improvement Project to NCC Neumann Construction in the amount of $ 178,131.00. PROJECT TO NCC NEUMANN CONSTRUCTION. FISCAL EFFECTS: The project will be funded by the Westside Tax Increment Capital Project Fund. ALTERNATIVES: As suggested Respectfully submitted, Fred Zavodny Project Manager Director of Public Works C"/ Charles Harball Interim City Manager