Airport Neighborhood Plan Implementation CostsImplementation Costs
Land Acquisition (South)
Excavation and Pavement
Runway
Taxiway
Increase Taxiway Width
Overlay
Strobe KGEZ Towers
Install PAPI System
I stall New Lighting
Fence Airport Perimeter
Land Acquisition (North)
Remove Objects in RPZ
Neighborhood Plan Preparation
Surveys
A.ppraisals
Advisory Board Expenses
Relocate Ballfields
s u btotal
'i 0% contingency
$570,117.30
$92,000.00
$25,000.00
$13,000.00
$55,000.00
$3,400.00
$15,000.00
$120,000.00
$136,200.00
$180,000.00
$15,000.00
$5,000.00
$6, 065.00
$9,500.00
$500.00
$827,369.00
$2,073,161.30
$207, 315.13
$2,280,466.43
NOTE: The plan also recommends the hiring of an airport manager;
this expense is not included herein.
aimort2