06/06/97 Harrison/Floodplain Permit ApplicationThe Ciiy of Kalispell
incorporated 1892
Diana. Harrison
Zoning Adminisfrafor
Ry-MA-MINE
Tim Stulc
Springcreek Development, LLC.
East 608 Holland
Spokane, WA 99218-1255
Telephone1406D 758-7730
248 3rd Avenue East
P. ®. Box 1997
Zip 69903
IFax(406) 768-7739
RE: Kalispell Hampton Inn Floodplain Development Permit Application
Dear Mr. Stulc:
Thank you for submitting the Hampton Inn Floodplain Development Permit application
by the June 4, 1997 deadline.
Unfortunately, I am unable to process the application until I have received more
information from you regarding the development. In order to continue the review of the
application, I will require the following from you:
1) A project site map indicating the pre -development floodplain and floodway
boundaries and original cross sections with the flood elevations.
2) A scaled project map indicating everything that has been placed in the floodplain
such as fill, culverts, etc., their elevations, sizes and lengths. Also, indicate post -
development floodplain and floodway boundaries and the surveyed cross sections
used for the analysis. This map should also indicate adjoining property owners.
3) A computer water surface profile program model (such as HEC-2) input data and
output run which includes the changes in the flood elevations. Also, a table
showing the comparison of pre -development and post development 100 year flood
elevations, floodplain widths, and floodway widths.
Although a scaled project map was submitted to this office at an earlier date, indicating
items that have been placed in the floodplain, I would require that this map be updated to
show what is actually on -site. This revised map will need to show adjacent properties
and indicate post -development floodplain and floodway boundaries. (Item 92 above)
Once the above required information is received by this office, I will then ran a legal
notice in the local newspaper and notify adjacent property owners of the floodplain
development pen -nit application. Again, if there is significant concern from neighboring
property owners, I will have to schedule a public healing.
Please keep in mind that July 1, 1997 is the deadline to have this application processed.
Please let me know if I can do anything to help you.
Sincerely,
Diana Harrison
Zoning Administrati
cc: Virginia Motoyarna, FEMA
John Liou, FEMA
Craig Kerzinan, Building Official
Karl Christians, DNRC
Glen Neier, City Attorney
Mark Sawyer, FRDO