Loading...
Revised Certificate of Completion Phase 2BUFFALO COMMONS PUD SITE DEVELOPMENT CERTIFICATION OF COMPLETION DECEMBER 18,1997 Revised: May 14, 1999 TO: NORTHWEST HEALTHCARE (OWNER) CITY OF KALISPELL FROM: ROBERT PECCIA & ASSOCIATES SUBJECT: COMMONS WAY (FORMERLY NORTMUDC:E DRIVE) STATION — 20+00 TO 34+48 The above cited portion of Commons Way (Formerly referred to as Northridge Drive in the Construction Contract Documents) has been designed and constructed in accordance with City of Kalispell approved plans and specifications and City Design Standards (April 1996). This Certification of Completion covers that portion of the Buffalo Commons PUD which is generally described as Phase II. All improvements have been completed. The Phase lI area includes water, sanitary sewer, storm sewer, paved streets, sidewalks and curb and gutter and underground utilities (electric, natural gas, cable tv, and telephone) are in place and stubbed to individual lots. Water Main / Services: Hydrostatic Tests as per Technical Spec 02713: All passed Chlorination and Bacteriological Tests: All passed --1,414 ft. - Water Mains: Northridge Drive 770 ft. - Water Mains (Phase II): A, B, C, D & E under driveways 2 ea - Fire Hydrants 8 ea - Water Services: off Northridge Drive 3 ea - Water Service: Irrigation Meter Pit 6 ea - Blowoff / Irrigation Meter Pits (Phase II) 29 ea - Water Services (Phase II): off A, B, C, D & E under driveways Sanitary Sewer Main / Services: Leakage, Deflection and Alignment (Light) Tests as per Technical Spec 02722: All passed - 1 348 ft. - Sewer Mains: Northridge Drive -- 735 ft. - Sewer Mains (Phase II): A, B, C, D & E under driveways 15 ea - Manholes (A I -B I -BC-C I -D 1-DE-E 1-F I ), Phase II: (AA I-AA2), BC2, CC2. (DDI-DD2), DE2 8 ea - Sewer Services: off Northridge Drive 29 ea - Sewer Services (Phase In: off A, B, C, D & E under driveways Page Two Certificate of Completion Buffalo Commons PUD Portion of Commons Drive (formerly Northridge Drive) from — Sta 20+00 to 34+48 Storm Drainage System: All storm drainage pipes, detention ponds and outlet structures have been installed in accordance with the approved plans ans specifications. Asphalt Pavement: All asphalt has been installed as per plans, Laboratory results of Marshall Density tests, held density tests, core density tests, and core thicknesses indicate that the pavement is in substantial conformance to the approved plans and specifications. —55,725 sf - 4" Asphalt Pavement: Northridge Drive Station 20+00 to 34+48 3,392 sf - 3" Asphalt Pavement: Phase H Driveways -- 4,910 sf - 3" Asphalt Pavement: North Parking Lot Portland Cement Concrete Pavement: Laboratory results of compressive strength tests and/or concrete cores indicate that the concrete sidewalks, curbs & gutter and driveway approaches are in substantial conformance to the approved plans and specifications --14,630 sf - Sidewalks: Northridge Drive: Station 20+00 to 34+48 — 3,275 1f - Curb and Gutter: Northridge Drive: Station 20+00 to 34+48 5 ea - Driveway Approaches: Attached to the December 18, 1997 Certification of Completion were the original approval letters from the Montana Department of Environmental Quality (DEQ) for both the overall Buffalo Commons PUD - Site Development and Phase Two work. I certify that the above statements are true: Philip Porrini, P.E. #4371 PE FASiTF.f EWNWHMONTAF)WRRPORMPHI1 0-R,WP,