Certification of Completion Phase 3BUFFALO COMMONS PUD
SITE DEVELOPMENT
CERTIFICATION OF COMPLETION
January 5,1998
TO: NORTHWEST HEALTHCARE (OWNER)
CITY OF KALISPELL
FROM: ROBERT PECCIA & ASSOCIATES
SUBJECT: COMMONS WAY (FORMERLY NORTHRIDGE DRIVE) STATION 10+00 to 20+00
COMMONS LOOP (FORMERLY NORTHRMGE LOOP) STATION 10+00 to 19+76.7
COMMONS LOOP (FORMERLY HERITAGE WAY) STATION 10+00 to 16+07.31
The above cited portion of Commons Way (formerly referred to as Northridge Drive in the
Construction Contract Documents), and Commons Loop (formerly referred to as Northridge
Loop and Heritage Way) have been designed and constructed in accordance with City of
Kalispell approved plans and specifications and City Design Standards (April 1996).
This Certification of Completion covers that portion of the Buffalo Commons PUD which is
generally described as Phase III. All improvements have been completed.
The Phase III area includes water, sanitary sewer, storm sewer, paved streets, sidewalks and curb
and gutter and underground utilities (electric, natural gas, cable tv, and telephone) are in place
and stubbed to individual lots.
Water Main / Services: Hydrostatic Tests as per Technical Spec 02713: All passed
Chlorination and Bacteriological Tests: All passed
2,423 ft. - Water Mains: Northridge Drive, Northridge Loop, and Heritage
Way
5 ea - Fire Hydrants
1 ea - Water Service: Irrigation Meter Pit
19 ea - Water Services
Sanitary Sewer Main / Services: Leakage, Deflection and Alignment (Light) Tests
as per Technical Spec 02722: All passed
2,783 ft. - Sewer Mains: Northridge Drive, Northridge Loop and Heritage
Way
12 ea - Manholes: (A2, A3, A4, B2, B3, B4, B5, B6, B7, C2, C3, and C4)
20 ea - Sewer Services: off Northridge Drive, Northridge Loop and
Heritage Way
930 ft. - Sanitary Sewer Force Main Relocation
Page Two
Certificate of Completion
Buffalo Commons PUD
Portion of: COMMONS WAY (FORMERLY NORTHRIDGE DRIVE) STATION 10+00 to 20+00
COMMONS LOOP (FORMERLY NORTHRIDGE LOOP) STATION 10+00 to 19+76.7
COMMONS LOOP (FORMERLY HERITAGE WAY) STATION 10+00 to 16+07.31
Storm Drainage System: All storm drainage pipes, detention ponds and outlet structures have
been installed in accordance with the approved plans ans specifications.
Asphalt Pavement: All asphalt has been installed as per plans. Laboratory results of Marshall
Density tests, field density tests, core density tests, and core thicknesses indicate that the
pavement is in substantial conformance to the approved plans and specifications (pending final
punch list items in the spring/summer of 1998).
34,530 sf - 4" Asphalt Pavement: Northridge Drive Station 20+00 to 34+48
42,622 sf - 3" Asphalt Pavement: Northridge Loop Station 10+00 to 19+76.7,
including South Parking Lot,
21,778 sf - 3" Asphalt Pavement: Heritage Way Station 10+00 to 16+07.31.
Portland Cement Concrete Pavement: Laboratory results of compressive strength tests and/or
concrete cores indicate that the concrete sidewalks, curbs & gutter and driveway approaches are
in substantial conformance to the approved plans and specifications (pending final punch list
items).
—21,900 sf - Sidewalks: Northridge Drive, Northridge Loop and Heritage Way
5, 1651f - Curb and Gutter: Northridge Drive, Northridge Loop and Heritage
Way
1 ea - Driveway Approaches
Approval letters from the Montana Department of Environmental Quality (DEQ) for the overall
Buffalo Commons PUD - Site Development are attached.
I certify that the above statements are true:
Philip Porrini, P.E.
#4371 PE