07-06-26 City Manager Report, KFD Report1
City of Kalispell
OFFICE OF THE CITY
MANAGER
Information Memorandum
7/6/2026
Parks & Recreation
Park staff have completed flail mowing of tall grass in non-irrigated areas at Western Park, Dry
Bridge Park, the hillside above Woodland Water Park, and the creek corridor south of the Archie
Roe and Kalispell Lakers baseball fields. Weed management has also been completed at all City
playgrounds to maintain safe and attractive recreational spaces. In addition, staff completed
string trimming along the nature trail at Lawrence Park, improving visibility and enhancing the
overall experience for park visitors.
At DJKYAC, staff have taken advantage of the interval between
major tournaments to complete several facility improvements.
Maintenance activities included adding clay and conditioner to
nine baseball pitching mounds and applying infield mix to
correct low spots throughout the infields. Staff also painted and
installed new trim boards on the backstops of the Majors baseball
fields.
Following the Firecraker Tournament 4th of July, staff will have a
limited turnaround to restore the fields to playing condition in
advance of the 9U–12U State Tournament scheduled for the
following week.
The Urban Forestry crew continues its systematic pruning of mature street trees along 6th
Avenue West. In addition to routine pruning operations, crews have completed pruning and
mulching of trees throughout the core downtown area to promote tree health and enhance the
appearance of the streetscape, while also responding to numerous tree-related work orders
throughout the community. As warmer, drier weather continues, staff have also begun watering
approximately four hundred City-planted trees to support their establishment and improve long-
term survival.
Adult Tennis continues each Wednesday at 6:00 p.m. on the south courts at FVCC. The program
provides adults of all skill levels with an opportunity to stay active, develop their tennis skills,
and connect with others through recreational play throughout the summer.
2
The 35th season of Picnic in the Park kicked off on June 24 with a performance by the Kenny
James Miller Band, drawing approximately 350 attendees. In conjunction with the evening
concert, a drop-in community art activity hosted by Jenna Justice Art Studios attracted
approximately forty-five participants.
Beginning July 1, the series expands to a full day of programming, including a noon concert by
the David Walburn Duo, afternoon community art projects hosted by the Glacier Art Museum,
drop-in lawn games and family activities, and an evening concert by the Brent Jameson Duo.
This expanded schedule will continue each Wednesday through August 5. On July 8, Park Side
Credit Union will sponsor a special Community Ice Cream Social as part of the event.
Camp Woodland continues to provide engaging, hands-on educational and recreational
experiences for participants throughout the summer. During Nature Week, campers participated
in an interactive presentation by the Flathead Lake Biological Station, exploring local
ecosystems and environmental science. During STEAM Week, campers enjoyed a field trip to
the Amazing Fun Center and participated in interactive science demonstrations led by STEM
educators from Flathead Valley schools.
Upcoming camp themes include Western Week, Animal Week, History Week, Water Week,
Carnival Week, Hero Week, and others, offering a diverse range of activities designed to
promote learning, creativity, and outdoor recreation throughout the summer.
The Girls Flag Football Camp was held June 22–25 at Lawrence Park. Led by Flathead High
School Head Flag Football Coach Jess Hensley, with assistance from members of the Flathead
High School Flag Football Team, the camp welcomed thirty-seven participants. Throughout the
four-day program, participants developed fundamental skills, built confidence, and were
introduced to the rapidly growing sport of girl’s flag football.
Skateboard Camp was also held June 22–25 at the Woodland Park Skatepark. Led by Lindsey
Taylor of Spirit Skate Shop, campers participated in age- and skill-appropriate instruction
designed to build confidence and improve skateboarding skills. Campers also enjoyed a surprise
visit from Officer Haworth, who joined them for a skate session and handed out stickers for their
skateboards.
3
The 3v3 Basketball League began June 16 at Thompson Memorial Park. The league provides
sixth- and seventh-grade boys and girls with organized recreational competitions, with staff
facilitating five games each evening throughout the season.
Registration remains open for several upcoming recreation programs, including an additional
session of Skateboard Camp, Youth Tennis Lessons beginning the week of July 13, UK Soccer
Camp, Intro to Kayaking, and a variety of other summer recreation opportunities.
The first session of swim lessons concluded on June 26, with nearly two hundred children
successfully completing the program. Three additional swim lesson sessions are scheduled
throughout the summer, providing continued opportunities for youth to develop essential water
safety and swimming skills.
Open swim began on June 16. Despite the temporary closure of the Lazy River during
resurfacing improvements, attendance has remained strong. The Lazy River is currently being
refilled, with water quality testing and mechanical system evaluations underway in preparation
for reopening.
Public Works
Capital Project Review-Engineering: Public Works engineering staff are currently managing
more than twenty active capital projects across the City’s water, sewer, storm and street systems,
representing roughly a budget of $33.1 million in active construction value. The sections that
follow summarize projects by utility and distinguish projects the City delivers in -house from
those led by a consulting engineer of record. The following summarizes the status of each
project.
Value of In-House Engineering
A significant portion of the City's capital improvement program is being designed, bid, and
managed in house by City engineering staff without a consulting engineer of record. Six in house
designed projects, representing approximately $4.2 million in construction value, are currently
under construction, with an additional five projects in design or preparing for bid.
Things to Note: City consultant led projects have averaged engineering costs of
approximately 21 percent of construction value. Applying that rate to the current $4.2
million of in house work represents an estimated $880,000 in avoided consultant fees, with
additional savings expected as projects currently in design advance to construction.
These savings reflect consultant costs the City did not incur, offset by staff time. In house
engineering allows more capital dollars to be invested directly in infrastructure while improving
responsiveness, reducing project delivery time, and maintaining greater control over project
quality.
4
City staff have the capability to deliver many projects from field survey and design through
construction and closeout. However, larger or more complex projects requiring specialized
expertise, such as structural, electrical, or instrumentation and controls engineering, or projects
generally exceeding $3 million, require consultant support due to staffing capacity and resource
limitations.
Even on consultant led projects, City engineering and maintenance staff remain actively involved
in design review, construction oversight, change orders, pay applications, traffic control, public
communications, testing, progress meetings, and review of consultant deliverables to ensure the
completed infrastructure meets the City's long term operational and maintenance needs.
Sewer
In-House Projects
• Lift Station #36 Upgrade (Strods Contracting; AE2S provided specialty design support &
construction inspection) is a major upgrade to one of the City’s key lift stations. Staff are managing
construction with AE2S. Pump and generator deliveries have pushed the completion of this project;
completion is anticipated in November 2026.
• 2025 Inflow & Infiltration Mitigation (Insituform; WGM provided construction inspection
services) rehabilitates sewer mains to keep groundwater out of the collection system. Designed in -
house, the project is substantially complete, with staff issuing final substantial completion.
• Sewer Shop Roof Replacement (Ace Roofing) is one half of a single in-house-designed roofing
contract. The Sewer Shop scope roof removal, decking replacement, insulation, TPO replacement,
and half of mobilization.
• 2nd Alley W Sanitary Sewer Replacement was designed in-house; plans are in internal review
ahead of submittal to MDEQ.
Consultant-Led Projects
• Biosolids Disposal at the wastewater treatment plant (Swank; AE2S) is nearing completion, with
punch-list work identified by staff and the engineer underway. Completion is anticipated at the end of
summer 2026.
Water
In-House Projects
• Lead Service Line Replacement, Phase 1 (Utilities One) was designed in-house to remove lead
service lines in compliance with federal requirements. Staff are coordinating the start of service
replacements; completion is anticipated in October 2026.
• Lead Service Line Replacement, Phase 2 is designed in-house and is being prepared to bid.
• Grandview Well Roof Replacement (Ace Roofing) is the companion scope to the Sewer Shop roof
in the same in-house-designed contract — roof removal, decking replacement, TPO replacement, and
half of mobilization.
• 6th St W Water Main Replacement (Mike Coleman Construction) was designed in-house and is
under construction.
5
• 10th Ave W Water Main Replacement (KG&T Septic) was designed in-house; submittals are in
review and contract time begins July 6, with completion anticipated in October 2026.
Consultant-Led Projects
• Lower Zone Reservoir 1 (Preload; MMI) is in close-out, with staff overseeing the final punch
list and repainting of the tank dome. Completion is anticipated at the end of June 2026.
• Lower Zone Reservoir 2 (Preload; MMI) is progressing, with site piping and this week’s
disinfection and flushing underway. Completion is anticipated in March 2027.
• Emerging Contaminant Water Supply Wells (Coldwater Drilling & Pump; RPA) advances the
City’s PFAS response. Development of the NE well was completed June 19 and well -sealing is next;
completion is anticipated in December 2026.
• Emerging Contaminant Water Transmission Mains, Schedule 1 (Neumann Construction;
RPA) is complete, with staff completing the final walkthrough and issuing substantial completion.
• Emerging Contaminant Water Transmission Mains, Schedule 2 (Sandry Construction; RPA)
is paused for the season while staff and the engineer finalize a realignment design, with construction
set to resume in the fall. Completion is anticipated in spring 2027. ($1.50 million)
• Emerging Contaminant Water Transmission Mains, Schedule 3 (Sandry Construction; RPA)
is progressing, with service tie-ins between 6th and 8th and main installation continuing south of 8th
Street. Completion is anticipated in September 2026.
Storm & Streets
In-House Projects
• 8th Street W Drainage (Wesco) was designed in-house and is awaiting contractor submittals.
($920,327)
• Grandview & Hwy 93 Storm (AE2S providing modeling support) is set to begin design later
this fall, pending additional information from MDT following staff’s recent coordination meeting.
• Sherwood–Wedgewood Storm is being designed in-house, with stormwater modeling and
design underway.
• 3rd Ave E (Center to 6th) was designed in-house and is being prepared for bid, planned for late
July with award anticipated in September.
• W Montana St Improvements is designed in-house and ready to bid pending the go-ahead.
• Wyoming Alley will be designed in-house and will likely be constructed by the Streets Division.
The project is currently being surveyed.
• 50/50 Sidewalks Program (Sandon)is managed in-house. Construction includes 50/50 work
orders as well as work orders for water, sewer, and street utility projects. (~$100,000+ annually)
• Milling and Paving (LHC, Inc.) is managed in-house. Engineering staff support the bidding,
construction contracts, work order management, as-constructed quantities, and pay
applications($84,280).
• Chip Seal (Pavement Maintenance Service, Inc.) is managed in-house. Engineering staff support
the bidding, construction contracts, work order management, as-constructed quantities, and pay
applications ($196,408).
6
Consultant-Led Projects
• Decant Facility (Jackson Contractor Group; RPA) is in construction, with the engineer adding
code-required battery-backup lighting. ($1.86 million)
• 2 Mile Drive Reconstruction (MMI) is in design.
Planning
The Planning Commission will be holding a public hearing on July 14 for the Birchwood
Planned Unit Development. Birchwood is a residential development consisting of approximately
ninety-five (95) residential units including townhomes, cottages, and detached single-family
residences on approximately 21 acres located west of Northland Drive, south of Four Mile Drive,
east of the U.S. Highway 93 Alternate (Kalispell Bypass), and north of Northridge Drive.
Building
In the last 3 weeks we have issued permits for 13 single-family homes, 17 townhouses, 1 duplex,
and 1 ADU. That will keep the total of new single-family/duplex and townhouse units for the
year at 131 compared to 63 last year at this time. There have been 96 multi -family housing units
issued so far this year compared to 35 last year at this time.
There were a total of 362 combined building and/or fire inspections completed in the last 3
weeks.
Residential – 82 Plumbing – 31
Commercial – 41 Mechanical – 69
Electrical – 33 Fire – 106
Community Development
The City accepted the obligation of funds for the Montana Disaster & Emergency Services'
Montana Resiliency Funding Grant. The award is for the installation of a backup generator at the
public safety building.
The Economic Revolving Loan Fund Committee met June 25th regarding loan terms for the
Outpost at Kalispell TIF project. The committee approved the loan and the developer is planning
to begin construction of the project later this summer.
Communications
Social Media Audience & High-Impact Content
The City’s primary audience has grown to 13,900 followers on Facebook and 5,290 followers on
Instagram. Recent high-performing content highlights the broad reach of our community
updates, public safety recruitment, and hearing notices:
7
•Montana Law Enforcement Memorial Parade: A video reel capturing the parade
achieved exceptional reach, surpassing 57,500 views, after 95 shares on Facebook, and
1,800 views on Instagram.
•Public Safety Recruitment: A reel announcing four open firefighter positions had 6,100
views with 77 link clicks back to the city job page on Facebook and 1,600 views on
Instagram.
•Community Engagement: A June 25 feature highlighting Officer Cat Edson spending
time with Girls on the Run garnered 12,200 views on Facebook and 1,200 views on
Instagram.
Girls on the Run then spoke with NBC Montana offering details and the following story
ran garnering additional positive outreach: Police officer runs with campers after
harassment scare at camp
•Public Notices & Infrastructure:
o A public hearing announcement regarding city facility plans reached 1,800
views on Facebook and 444 views on Instagram.
o A critical construction alert for Three Mile Drive generated 9,000 views on
Facebook and 415 views on Instagram.
In addition to Facebook and Instagram, residents can find official city updates, video coverage,
and professional listings on our growing YouTube and LinkedIn channels.
Connect With Us
•Facebook: facebook.com/CityofKalispell
•Instagram: @cityofkalispell
•YouTube: Kalispell.com/YouTube
•LinkedIn: Kalispell.com/LinkedIn
Stay Informed: "Notify Me" Alerts
Residents are encouraged to sign up for direct notifications delivered straight to their email or
smartphone. Subscriptions are customizable and cover a wide variety of municipal topics,
including:
•Press Releases, Announcements, and News
•The twice-monthly City Manager Report
•City Council Agendas
•Advisory Board and Committee Agendas
•Construction Alerts
To customize your notification preferences, visit
kalispell.com/NotifyMe.
Photo Caption: It's not always crime fighting at KPD!
KPD is passionate about building community
relationships. Officer Cat Edson spent time with Girls on
the Run Western Montana this week.
Kalispell FD MT
Address: 312 1st Ave E, Kalispell, MT, 59901
Incident Count by Primary Incident Sub Group 06/10/2026 - 06/30/2026
PRIMARY INCIDENT GROUP / PRIMARY
INCIDENT SUB GROUP
COUNT
Fire 9
Fire - Outside Fire 2
Fire - Structure Fire 4
Fire - Transportation Fire 3
Hazardous Situation 7
Hazardous Situation - Hazard Non-Chemical 1
Hazardous Situation - Hazardous Materials 4
Hazardous Situation - Investigation 2
Medical 226
Report ID: 118208 This report was generated on : 07/01/2026 07:46 AM Page: 1 of 2
Incident Count by Primary
Incident Sub Group
Kalispell FD MT
Address: 312 1st Ave E, Kalispell, MT, 59901
PRIMARY INCIDENT GROUP / PRIMARY
INCIDENT SUB GROUP
COUNT
Medical - Illness 161
Medical - Injury / Trauma 62
Medical - Other 3
Public Service 31
Public Service - Citizen Assist 28
Public Service - Alarms (Non Medical)5
No Emergency 25
No Emergency - False Alarm 12
No Emergency - Cancelled 13
Total 298
Powered by TCPDF (www.tcpdf.org)