E2. Fire Station 63 Task Order 2KALISPELL REPORT TO: Jarod Nygren, City Manager FROM: Jay Hagen, Fire Chief SUBJECT: Professional Services Recommendation and Contract Approval for New Fire Station 63 MEETING DATE: July6, 2026 BACKGROUND: The City previously completed Task Order 1 (Programming and Site Analysis) for the Fire Station 63 project. The project now proceeds into Task Order 2, which includes full design, permitting, procurement, and construction phase services for the new station at 490 Mountain Vista Way in Kalispell. Task Order 2 advances the project from conceptual planning into implementation and includes coordination of architectural, multidisciplinary engineering, and specialty consultant services required to deliver a fully constructed facility. REQUIRED SERVICES: The consultant will provide services for the following phases for this facility project as follows: • TASK ORDER 2: o Schematic Design $ 192,436.67 o Design Development $ 277,078.27 o Construction Documents $ 384,887.07 o Permitting/Procurement $ 66,793.00 o Construction Administration $ 311,682.40 o Subtotal $1,232,877.40 o Reimbursables $ 15,000.00 0 Total $1,247,877.40 • Schematic Design: Develop conceptual design and preliminary cost estimate and schedule. This phase explores the building's size, layout, and basic systems, and program alignment. • Design Development: The design is refined and coordinated in greater detail. Drawings and outline specifications are prepared to describe major building systems, materials, and quality levels. The budget and schedule are further reviewed and updated, including a more detailed cost estimate. • Construction Documents: Complete final drawings, specifications and contract documents for project procurement. These documents are used for permitting and form the basis for contractor bidding and the construction contract. Bidding Phase: Assist with public bidding, contract preparation, and permitting. • Construction Administration: Construction administration of the contract between the Owner and Contractor. Services include periodic site visits, review of shop drawings and submittals, responses to Requests for Information, review of pay applications and change orders, participation in progress meetings, and support through project closeout. RECOMMENDATION: Staff recommend approval of Task Order 2 with LSW Architects, PC to proceed with design, permitting, and construction phase services based on their demonstrated expertise and performance on Task Order 1, as well as their ability to provide comprehensive, coordinated professional services for this phase of the Fire Station 63 project. ACTION REQUESTED: Motion to approve Task Order 2 with LSW Architects, PC and authorize the City Manager to execute the professional services agreements for design, documentation, and construction phase services for Fire Station 63. FISCAL EFFECTS: Funding for the new station will come from the Emergency Responder Levy (Fund 2273) Line 2273-416-42400-947. ALTERNATIVES: As suggested by the City Council ATTACHMENTS: Professional Services Agreement, Task 2, and Exhibit A- Budget Summary TASK ORDER NUMBER TWO AGREEMENT TO FURNISH ARCHITECTURAL/ENGINEERING SERVICES to CITY OF KALISPELL for the A NEW FIRE STATION 63 DESIGN, DOCUMENTATION AND CONSTRUCTION PHASES This Task Order provides for professional architectural/engineering services to be performed by LSW ARCHITECTS, PC. (hereinafter the Consultant), for the CITY OF KALISPELL (hereinafter the City), in accordance with Professional Services Agreement for a NEW FIRE STATION 63, dated June 5, 2026 hereinafter the (Agreement). All provisions of the Agreement are incorporated by reference. This Task Order represents an authorization to proceed with the scope of services, schedule, and compensation described herein. This Task Order, when executed by both parties, shall become a supplement to and part of the basic Agreement. The Consultant agrees to furnish the following professional architectural/engineering services in connection with the NEW FIRE STATION 63, hereinafter referred to as the Project and generally described as follows: ARTICLE 1. PROJECT UNDERSTANDING The project scope will consist of approximately a single -story 7,600 square foot new construction fire station. The budget is approximately $7,075,000.00. See Exhibit A- Budget Summary Report for breakdown of budget into estimated Soft Costs, Hard Costs, Owner Contingency, Owner FF&E and Additional Costs. The primary objective of this task is to provide design, permitting and procurement, and construction phase services for Architectural, Civil, Landscape, Structural, Mechanical, Plumbing, Electrical, Fire Suppression, ICT, Cost Estimating, Acoustic, Envelope, and Owner's Representative services. This proposal also includes additional Traffic study services and a final Geotechnical report. Scope also includes community engagement process. The following is the list of probable project spaces and project characteristics: See Pre -Design and Programming Report dated June 5th, 2026 for full program requirements. Fire Station 63: • Two full-length drive -through apparatus bays with a third bay to be designed as an Add -alternate. • Kitchen, dining, and dayroom areas • Three Individual sleeping rooms with Two additional designed as Add -alternates Page 1 of 9 • Toilet and shower facilities • Fitness • Conference/Training room as Add -alternate • EMS supply and operational storage • Personal protective equipment storage • Decontamination and cleaning areas The site is located at 490 Mountain Vista Way, Kalispell. As part of Task 1, a survey and initial Geotechnical investigation has been completed. ARTICLE 2. ASSUMPTIONS It is assumed the Architect will provide Design, Documentation, Permitting and Construction Phase services consistent with industry and the Architect's professional standards. Additionally, it is assumed that Civil Engineer will provide drawings based on Engineer's drafting standards with a sheet border to be provided by the Client. Technical specifications for Site Civil items will be based on Montana Public Works Standard Specifications (MPWSS), Th Edition and City of Kalispell Modifications to MPWSS. All design work will be in conformance with the City of Kalispell Standards for Design and Construction. ARTICLE 3. SCOPE OF SERVICES The Architect agrees to furnish the following professional services in connection with theNEW FIRE STATION 63 —CITY OF KALISPELL, hereinafter referred to as the Project. A. PROJECT MANAGEMENT & OWNERS REPRESENTATION The Consultant will perform project management throughout the duration of this phase. The Consultant will maintain the project on their computer system and maintain project files. The Consultant will keep an electronic record of the project throughout the task order duration. At the end of the project, the Consultant will archive the electronic and hard copies of the project records and provide the city with all digital copies. Throughout the task order, the Consultant will coordinate with the City to obtain their comments, reviews, and approvals for a general direction on how to proceed. The Consultant will prepare monthly invoices, including an invoicing summary sheet, that will show the work amount completed and amount remaining. The Consultant will prepare and update project schedules and project budgets as part of this task order. Deliverables: Agreements, agendas, project meeting minutes. Monthly Invoices and Page 2 of 9 Invoice Summaries. Updated Project Schedules and Project Budget. This will be transferred to the City via PDF's, along with any digital documents in the appropriate software platforms. B. BASIC SERVICES Basic Services include Schematic Design, Design Development, Construction Documents, project manual specifications, permit submittal and response, and Construction Phase services for Architectural, Structural and MEP scope of services. 1. ARCHITECTURAL SERVICES LSW Architects & TCA Architecture + Planning, Inc. Scope to include Architectural design and documentation consistent with industry and the Architect's profession standards for Schematic Design, Design Development, development of Contract Documents drawings and specifications, Permitting and Procurement submittal, responses to Agency comments, responses and review of RFIs, submittals, and Construction Administration services. Deliverables to include 100% Schematic Design drawings and narratives, 100% Design Development drawings and outline specification, Construction Documents 50% or 75% set to be verified in coordination with either GC/CM or pricing estimate project delivery method to be determined during Schematic Design, Permit Set, and Bid Set. 2. STRUCTURAL ENGINEERING SERVICES Morrison Maierle Scope to include selection, design and engineering of a structural system. Development of foundation based on the structural framing system and geotechnical recommendations. Deliverables: design narratives, milestone review sets and stamped and signed construction documents. Permitting and Construction Phase services include responding to Agency review comments, review of RFIs, shop drawings and submittals for structural scope of work. 3. MECHANICAL, ELECTRICAL AND PLUMBING ENGINEERING Morrison Maierle Mechanical, Electrical, and Plumbing Engineering design work including full design of air distribution and control system for heating and cooling, as well as design of design of plumbing system, fire protection sprinkler performance specifications, power and lighting distribution systems, fire detection and alarm system performance specification, radon and low -voltage system rough -in all to be provided by owner/contractor. Mechanical to include: design of heating, ventilation, and air conditioning (HVAC) Page 3 of 9 systems for the building. Electrical to include: Design of the electrical service entrance equipment for the building including initial estimated load calculation and final NEC calculated demand loads. Electrical site and lighting plan for the area surrounding the building. Power system layout and circuiting for the building. Luminaire design: Interior/exterior lighting control system layout that meets the International Energy Conservation Code (IECC) requirements. Design of a fire alarm system in the building will be delegated design. The Contractor will be responsible for battery calculations, wiring layouts, and manufacturer - specific design. Telephone/data system rough -in design with boxes and conduit stubbed to the accessible ceiling, coordinated with the ICT design. Provide a diesel fuel type generator backup system design sized for the whole building, with allowance for planned future expansion loads, and provisions for load -shedding. Electrical exclusions include: Design of EV charging stations, UPS backup power system, alternative energy system such as solar photovoltaic or wind, Arc Fault calculations and printing of labels, and coordination study of overcurrent protective devices. Electrical Deliverables to include: stamped and signed construction documents consisting of general notes, mechanical equipment schedules, details, duct or pipe plans, and 3D views/section views, load calculations and final NEC calculated demand loads. Plumbing to include: design of the following plumbing systems or components: Water service entrance riser, Domestic water distribution system, Domestic hot water heating equipment, Sanitary waste and vent piping, Roof drainage systems, Sand -oil interceptor for the apparatus bay trench drains, Grease waste piping and grease interceptor for the domestic kitchen, if required, Radon abatement systems. Provide plumbing fixture options for the Architect and Owner's selection to meet the needs of the building. The plumbing fixture selection will be limited to two revisions. The plumbing design will extend up to 5-feet from the exterior perimeter of the building, where the site civil engineer will show all work from that point to their connection/ termination. Plumbing exclusions include: Design of roof drainage scuppers, gutters, and downspouts, and Foundation drainage systems. Plumbing Deliverables to include: Deliver PDF stamped and signed construction documents consisting of general notes, plumbing schedules, pipe plans, details, and/or 3D views/section views. C. ADDITIONAL CONSULTANT SERVICES Additional Consultant Services include Schematic Design, Design Development, Construction Documents, project manual specifications, permit submittal and response, and Construction Phase services for Civil and Landscape, Acoustics, Envelope, Cost Estimating, Page 4 of 9 Fire Suppression, Geotechnical, Transportation, ICT, and Owner's Representative Advising services. Additional scope outside of basic services for Architectural, Structural and/or MEP are also included within Additional Consultant Services. 1. CIVIL ENGINEERING AND LANDSCAPE ARCHITECT SERVICES DJ&a Civil engineering design services, including grading and drainage, stormwater management, and utility design. Landscape architecture design services, including site planting plans, irrigation design, and streetscape improvements. This scope of work includes civil engineering, landscape architecture, and associated coordination necessary to produce a complete, permitted, and stamped set of civil and landscape contract documents suitable for construction bidding and permitting. Deliverables include preparation and submittal of a 50% Design Development (DD) package, a Draft 90% Contract Documents (CD) package, and a Final Stamped 100% Contract Documents (CD) package. Design parameters for this phase will be based on the findings, recommendations, and conceptual site design developed during the pre -design phase, updated to reflect any revised building programming, geotechnical findings, or direction from the City and project team. Civil/Site Schematic Design (SD) phase services are currently being performed under the Task One scope and agreement and are not included in this scope of work. Any work associated with the SD phase, including SD deliverables, review, and coordination, will continue to be governed by that existing agreement. 2. FIRE SUPPRESSION Morrison Maierle Provide a fire suppression design set that outlines the location of fire sprinkler piping and fire sprinkler heads. Fire suppression drawings will include the following: References to applicable codes and standards, Classification of protected commodities, Confirmation of adequate water supply and fire service line sizing, Fire riser location(s) with riser valving schematic, Location of fire department connection, Location, type, and the number of sprinklers for the project, Location, type, and pipe size for the entire project, Location, type, and size of hangers, sleeves, and seismic bracing, Location of all drainpipes, flush connections, and test connections, Hydraulic and seismic bracing calculations. Provide engineering recommendations on the following systems: Site fire hydrant locations (confirming existing locations are adequate), Hydrant fire now requirements, advice on meeting building fire protection code requirements for Occupancy Classification(s), General building heights and areas, and Fire separations. The fire suppression design will begin at the interior flange of the fire service line. Fire suppression drawings shall be used to obtain both the building permit and the fire sprinkler permit. Fire Sprinkler Contractor is required to submit our drawings to obtain a Page 5 of 9 fire sprinkler permit eliminating the need for them to provide their own design. Deliverables to include stamped and signed construction documents consisting of general notes, specifications, schedules, details, pipe plans, 3D views, and/or section views. Exclusions include: Design is based on following prescriptive code criteria of applicable NFPA Codes and local jurisdiction requirements; Insurance requirements, waivers, and equivalencies; Commissioning or testing of fire protection system(s); Hydrant now testing (to be completed by others); Loose material list and fabrication reports; Provide cistern site development and installation design; Site fire service piping design; Pump house structure and foundation design; and Design of site fire hydrants. 3. INFORMATION AND COMMUNICATIONS TECHNOLOGY (ICT) Morrison Maierle Provide design of category 6/6A cabling infrastructure, which includes the following: Horizontal cabling with conduit / j-hook / cable tray infrastructure and cable pathways/routing throughout the building. Horizontal cabling includes work area outlet, conduit infrastructure to ceiling, and cabling pathways back to a patch panel inside a rack with testing requirements; IT equipment room design includes the design of equipment racks with patch panels, cable management, ladder rack, backboards, and grounding. Passive equipment only; Wi-Fi layout, including cabling, jacks, and faceplates. Provide access control system design, including cabling, controllers, I/O boards, card readers, power supplies, access cards, request -to -exit devices, and door position switches. Coordinate with the electrical engineer on power requirements and the Architect -provided door hardware schedule. Provide design of the video surveillance system, which includes camera layout and design with Owner direction for coverage required, rack -mounted video recording, and the video management system. Provide design of the overhead paging system, including head -end equipment, speaker selection, and cabling design. Exclusions include: Design of any active equipment including wireless access points, Ethernet switches, servers, UPS', firewalls, and routers; Design of intrusion detection system; Design of Audio -Visual systems, including sound systems (a subconsultant would need to be engaged by architect if required); Design of Distributed Antenna Systems (DAS) (a subconsultant would need to be engaged by architect if required); Design of Emergency Responder Communication Enhancement Systems (ERCES)(a subconsultant would need to be engaged by architect if required). 4. ACOUSTICS Listen Acoustics Acoustical engineering and audiovisual (AV) design work for the described project needed to accommodate and/or serve the proposed project. Scope of consulting includes Page 6 of 9 Room Acoustics: (conceptual sketches and descriptions of room shaping and room finishes, and sound control details to provide useful sound reflection where practical, avoid echo -producing sound reflections, and control reverberation as necessary), Noise and Vibration Control (recommendations, sketches, details, product descriptions and specification information for all major HVAC, plumbing, and electrical equipment items to limit noise and vibration to the building spaces, including critical acoustical spaces. Recommendations for major air handling systems to mitigate fan or airflow noise in critical acoustical spaces), Sound -Isolation Construction (detailed concepts, sketches, product descriptions, specification information, and review of building shell construction, walls, windows, doors, and floor/ceiling assemblies and interior partitions to minimize exterior noise from mechanical equipment, vehicles, and to control sound transfer between interior spaces, AV Systems Design for Sound and Video systems. ENVELOPE CONSULTING SERVICES Element Building Envelope Consultants Scope includes third -party building envelope consultation services related to the development's exterior building envelope systems. Services will occur during design and construction stages. During the design stage, Consultant will review deliverable documents at specific project milestones in alignment with the Architectural deliverables. During the construction stage, Consultant will assist the project team with the construction administration service, conduct periodic field review to assist the contractor with the construction of mock-ups and verify general compliance of the construction with the construction documents, witness field performance testing and assist with project closeout. 6. GEOTECHNICAL SERVICES Alpine Geotechnical Final Geotechnical Analysis: Conduct additional geotechnical drilling, sampling, more comprehensive laboratory testing including strength and consolidation testing, final geotechnical analysis, and preparation of the final geotechnical report. This final report budget also includes two (2) infiltration tests per City of Kalispell requirements for final stormwater design. 7. OWNER'S REPRESENTATIVE SERVICES Tell Construction Advisors Owner Representative Services include: Independent budget oversight and financial accountability, Schedule discipline and decision tracking, Contractor procurement strategy and execution, Construction -phase financial oversight (pay applications, change orders, contingency), Project closeout and operational turnover and support the project from SD through project closeout. 8. TRANSPORTATION ENGINEERING SERVICES Heath & Associates Scope to include Data Collection and Traffic Analysis at the intersection of Farm to Market Road & Mountain Vista Way for Signal Warrant Analysis. Page 7 of 9 9. COST ESTIMATING SERVICES CDK Enterprise Inc Scope and role in providing Full Design and Procurement Phase includes: Participation in a collaborative review including redline comments throughout the design process at critical stages, Schematic Design, Design Development and Permit & Bid Set. Review and update preliminary construction budget at critical design stages, Schematic Design, Design Development and Permit & Bid Set. Conduct a preliminary bid process to validate budget estimates for critical construction scopes; Civil/Site, Foundation, Structure, MEPFS and General Contractor Fees. Identify and evaluate cost-effective alternatives & value -engineering opportunities (as warranted and needed). Assist architect & client with the review, vetting, and selection of a General Contractor. Assist/supplement the general contractor with an independent bidding process focused on delivering the project on time and on budget. Generate and provide material take -offs, purchase order worksheets, and detailed scope of works to be shared with General Contractor, Subcontractors and Suppliers to ensure consistency throughout the bidding process. Provide supporting role throughout the bidding process to ensure the final project cost is in alignment with budget expectations. Potential Additional Services (at Client's request; not included in Lump Sum Fee): • FF&E consulting and/or procurement assistance is not included in this Task scope but can be added as additional service • 3d digital or physical models other than itemized in Scope of Services • Scope changes due to deviations from defined Scope of Project • Changing or editing previously prepared documents due to unforeseen conditions • Services necessitated by decisions of the Client not rendered in a timely manner or any other failure of performance on the part of the Client or Client's consultants and contractors. Summary of Services Not Provided: • Specialty lighting selection, structural support • Hazardous material identification, testing, and/or abatement • Permit/Agency Process fees • Professional services that the Architect and/or Consultants are not licensed to perform. ARTICLE 4. SCHEDULE It is anticipated that those services listed above will be completed based on the durations indicated below from the date of a signed agreement: Schematic Design: 8 weeks Design Development: 14 weeks Construction Documents: 16 weeks Permitting/Procurement: 20 weeks* Construction Administration: 16 month construction duration** Page 8 of 9 *Note: The timeliness of agencies having jurisdiction reviews/approvals and contractor bidding/construction are not controlled by the Architect and may vary. **Note: Construction duration to be determined by GC. Fees are based on estimated duration shown and may be adjusted once confirmed. The schedule may be modified to accommodate the City's calendar or Owner feedback, if the Consultant foresees a potential impact to the schedule the Consultant will communicate with the Owner and work collaboratively to maintain a mutually agreeable schedule to meet the needs of the project. ARTICLE 5. REIMBURSABLE EXPENSES Reimbursable expenses for large format printing, travel over 50 miles, and associated lodging (if required) will be invoiced at cost without mark-up, not -to -exceed $15,000 for this phase of services. Supporting documentation for all reimbursement will be provided with invoices. ARTICLE 6. COMPENSATION A. BUDGET AND PAYMENT The budget for those services described above under Article 3, Scope of Services, shall be paid on an Lump Sum Fee basis not to exceed $1,232,877.40. The Consultant will invoice the City on a monthly basis for work completed. The City will make payments within 30 calendar days of the invoice. The budget for those services described above under Article 5, Reimbursable Expenses, shall not exceed a ceiling of $15,000.00. The total potential compensation shall not exceed $1,247,877.40. DATED this 5th day of June, 2026 CITY OF KALISPELL By:_ Title: LSW P By: Casey Wyckoff, P mciple Page 9 of 9