Loading...
04-16-26 Site Development Review Committee MinutesSITE DEVELOPMENT REVIEW COMMITTEE SUMMARY Thursday, April 16, 2026 First Floor Conference Room 201 First Avenue East ATTENDING: Kari Barnhart, Planner II Patrick Jentz, Engineer III PJ Sorensen, Assistant Development Services Director Donnie McBath, Planner II Fred Bicha, Assistant Parks Director Dale Westphal, Commercial Plans Examiner Jason Landis, Fire Plans Examiner GUESTS: HEAR THE PUBLIC: None. PERFORMANCE BOND REMINDERS: None. OLD BUSINESS: Stillwater Bend Apartments – 2890 US Hwy 93 N – Comments were sent 4/14; the committee is waiting for a response. This will be on the agenda next week. Aesthetica Med Spa – 3201 US Hwy 93 N – Public Works has a minor comment regarding the irrigation meter pit out. Building review is complete. Fire stated that a fire extinguisher on the second floor will need to be added. This will be on the agenda next week. New Business: CoK Stormwater Decant Facility – 2580 US Hwy 93 S – Public Works and Parks are working together. Building needs plans for the foundation and pre-fab building. This will be on the agenda next week. Flathead County Detention Center – 225 Snowline Lane – Plans are in all departments’ queues. The committee discussed document organization since there were so many documents uploaded into the portal. This will be on the agenda next week. Kalispell Outpost Apartments – 40 Appleway Drive – Plans are in all departments’ queues. This will be on the agenda next week. OTHER: PRELIMINARY COMMENTS - Stillwater 360 Development – The committee discussed PUD limitations for the commercial element of the project, project layout, access from Stillwater Rd, recreational amenities, building height limitations, and geotech requirements with Joshua Bourgouin from Windsor Engineering. Fire has concerns with aerial access and access to the back of building. Planning advised that PUD variance approval from City Council and a traffic impact study would be required. Building advised that 3 geotech samples per building would be required and recommended that the developer contact the 911 center. North Meadows Fire Access – Planning advised Garrett Muonio (Jackola Engineering) and Jeremy Peterson that this change would need to go through Planning Commission and City Council for approval and that setbacks and snow storage would be required. Public Works discussed access to the sewer main with them as well. Garrett and Jeremy will advise Planning if they want to continue pursuing this option. The meeting was adjourned at 10:52 AM. cc: Police City Manager City Clerk Building Fire Community Development Planning Parks Public Works MDT