E2. Award 10th Ave W Water MainCITY OF KALISPELL MEMORANDUM To: Jarod Nygren, City Manager Cc: Susie Turner, PE — Public Works Director From: Graham Fell, EIT, Engineer 1 Re: 101 Ave W Water Main Replacement Project Meeting Date: April 20, 2026 BACKGROUND: The project includes furnishing all labor, materials, and equipment necessary to replace —1,498 linear feet of water main along loth Ave W between 4th St W and 8th St W. The bid was structured with a Base Bid and Bid Alternative 1. The Base Bid included full water main installation and restoration of all excavation areas, including repaving on the east side of the roadway and patching on the west side for service line connections. Bid Alternative 1 removed the requirement to repave the west side of the road, with the intent that City staff will complete full -width paving of the west side to achieve a uniform, patch -free roadway surface. Bid Alternative 1 was anticipated to reduce the overall contract cost while allowing for a higher -quality final pavement condition. BIDDING RESULTS: Bids were received and opened on April 9, 2026, at 3:00 pm. Five responsive bids were received and are summarized below. Base Bid Contractor Base Bid Price Bid Alternate 1 Base Bid + Bid Alternate 1 KG&T Septic and Excavation $1,070,195.30 $3,369.40 $1,073,564.70 Wesco Inc. $1,204,089.04 ($4,453.55) $1,199,635.49 Mike Coleman Construction, Inc. $1,234,248.81 ($2,716.99) $1,231,531.82 NCC Neumann Construction Co. $1,486,015.00 $98,012.00 $1,584,027.00 Strods Contracting $1,571,820.00 $30,081.00 $1,601,901.00 Engineer Estimate $1,641,167.00 ($11,984.00) $1,629,183.00 KG&T Septic and Excavation was the low bidder. References for projects of similar size and scope were reviewed, and the contractor is considered a responsible bidder that meets the minimum qualifications to successfully complete the project as specified. Public Works recommends awarding the Base Bid to KG&T Septic and Excavation. As Bid Alternative 1 resulted in an increased cost for the low bidder, staff does not recommend awarding Bid Alternative 1. ACTION REQUESTED: Motion to award the Base Bid for the 10th Ave W Water Main Replacement Project to KG&T Septic and Excavation for $1,070,195.30. FISCAL EFFECTS: Construction of the 10t1i Ave W Water Main Replacement Project is budgeted in FY 26 Water Fund in line item 5210-447-430550-971. ALTERNATIVES: As suggested and approved by the City Council. ATTACHMENTS: 10th Ave W Water Main Replacement Certified Bid Tab 201 1st Avenue E Phone (406)758-7720 Po Box 1997 Public Works Department Fax (406)758-7831 Kalispell, MT 59903 1 1 www.kalispell.com . . . . . . . . . .00 . . O -F 4N 4 cs .6 cs 6 16 li 4 cl q8 a 8. 8.ci 8 8 8 Iq Iq co? 19 10 o c; ci o o . . . . . o . o . . . -Q o ow of q 1 6 6 -i Ij 6 q oQmfc I? m al q Lq w . . w . . . . . . . a of 'k 8 6 'i 0 IR 4 4 n I-z 16 m � o ` c r4 q o U., w t ------- —-- q q $ q ui . . . . . . . . . . m m14 "ilm ui 'i "i :e 5 i ry q IP m Lq c? q 10 6 6 6 qj 6 4 6 c:� c:t — — — — - — — — - — o o o q . o o 0 op o op o op 0o l a% o . . . . . . . . o In t m, . . onr n o" �o Li o om. ct "I 14 ai r1t Iq m Ili lm� C� R rci a Ll� a Iq 00 . . o . . . . . . . . -o - al R o o "i zF Ili - - - - — — - IH —1 +fn my n��5 nl� J�5 J n JJ� J Z5 o o o ol > > o o o o > > w> > o >w o o u o -C u 0 D ;Z w W . . . . . . . . . . . I . w .1 �1117, I §� §{!\\\ §^ )!! u }\� E «p!/ ■ i \ � � k \\&&a J{ \ }}\\ V-4) vi -,aaa 7 \\ LTJ� --\ ))! (� TIT \ / 7 f�! §E9 _