E3. Early Work Contract RecommendationCITY OF KALISPELL MEMORANDUM To: Doug Russell, City Manager From: Susie Turner, PE, Director of Public Works Re: Early Work Contract Recommendation - Kalispell AWWTP Dewatering Improvement Project Meeting Date: August 18, 2025 BACKGROUND: The City of Kalispell is enhancing its biosolids dewatering capabilities as part of the Advanced Wastewater Treatment Plant (AWWTP) Biosolids Dewatering Improvement Project. For this project, Council approved the use of the alternative project delivery method General Contractor/Construction Manager (GCCM). The complete project scope includes: • Demolishing outdated equipment • Installing new solids dewatering equipment • Reconfiguring existing solids dewatering equipment and piping for potential future dryer equipment installation (if needed) • Updating the polymer unit • Improving pumping and piping to support new dewatering operations Under the GCCM method, a qualified contractor is selected early in the design process through a Request for Qualifications (RFQ) and Request for Proposals (RFP), in accordance with Montana Code Annotated (MCA) 18-2-503. The City conducted a two-step procurement process and selected Swank Enterprises from among three proposers following evaluation and interviews. As an initial step in the GCCM process, the City contracted Swank Enterprises for preconstruction services at a cost of $39,885.00. As part of these services, early procurement of long lead-time equipment and an initial work package were identified as items that would benefit the project by allowing work to proceed ahead of final design completion, helping to meet tight deadlines. The cost of the early work package will be deducted from the Guaranteed Maximum Price (GMP) when finalized at 90% design. EARLY WORK CONTRACT: Swank Enterprises provided work authorization and pricing for the early work package, which has been reviewed by AE2S, the Engineer of Record. The early work package will support the installation of a temporary biosolids loadout facility. The proposed scope includes: • Installation of temporary facilities, including a cake loadout structure located outside the existing volute press garage bay • Demolition of the DAF tank (west of the existing Belt Filter Press) and associated process piping and appurtenances 201 1" Avenue E Phone (406)758-7720 Po Box 1997 Public Works Department Fax (406)758-7831 Kalispell, MT 59903 1 1 www.kalispell.com • Demolition of the WAS pipe in the southeast corner • Preparation of shop drawings and as -built piping plans • Procurement of valves • Conveyor submittals AE2S has reviewed the early work package for completeness and compliance with technical requirements and recommends approval. FISCAL EFFECTS: The project's funding sources and FY 26 budget allocations are sufficient to award the Early Work Contract amounts described as follows: • WWTP Fund 5310-455-430640 Line Item 930: Capital Outlay — Biosolids Treatment//Disposal $429,846 • WWTP Impact Fee Fund 5311-455-430644 Line Item 930: Capital Outlay — Biosolids Alternate Disposal Eng. $281,207 • WWTP Fund 5310-455-430640: 930 SRF Bonded Debt — Biosolids Facility $5,086,243 ACTION REQUESTED: Motion to award the Early Work Contract to Swank Enterprises in the amount of $357,398.00, contingent upon DNRC-SRF and DEQ review and approval. ALTERNATIVES: As suggested and approved by the City Council. ATTACHMENTS: AE2S Recommendation of Award Memo. 2 1 P a g e www.ae2s.com August 11, 2025 Ms. Susie Turner Public Works Director 201 Is'Ave E Kalispell, MT 59901 Re: Recommendation of Award for Swank Enterprises Kalispell AWWTP Dewatering Improvements Protect: Work Authorization No. 1- Early Work Package Dear Ms. Turner: RECOMMENDATION: AE2S recommends that the City of Kalispell Award the Contract for Work Authorization No. 1- Early Work Package to Swank Enterprises. Swank Enterprises' Lump Sum Compensation for the Work Authorization No. 1 - Early Work Package is $357,398.00. We are confident that Swank Enterprises meets the qualifications required to supply the goods and scope of work requested for the AWWTP Dewatering Improvements Project. Swank Enterprise's Proposal for the Kalispell AWWTP Dewatering Improvements Project was received on July 3, 2025, and included the following required bid documentation: • Proposal Bond in the amount of 10% of the Estimated Guaranteed Maximum Price (GMP) • Acknowledgement of all addenda issued to the Bidding Documents. • Supporting materials, including a list of relevant projects, references, schedule, and thorough understanding of the project. • Estimated cost of work of $2,427,000.00 (Excluding contingency. Note that the cost is currently part of a non -binding Guaranteed Maximum Price (GMP), the final cost of the work and GMP will be determined in late fall 2025) Following proposal review, Swank Enterprises was selected as the General Contractor/Construction Manager (GCCM) for the Kalispell AWWTP Dewatering Improvements Project and is currently under contract for Preconstruction Services for the lump sum amount of $39,885.00. As part of preconstruction services, early procurement of long lead time equipment and an initial work package were identified as early work scope that will benefit the project ahead of construction to meet tight project deadlines while final design is completed. Compensation for the Early Work Package will be deducted from the current Estimated cost of work of $2,427,000.00 and Final Guaranteed Maximum Price (GMP) once final design is completed. Compensation for Work Authorization No. 1 - Early Work Package includes bonding and insurance, project support costs, labor, submittals, a temporary cake loadout facility, piping, and equipment. Advanced Engineering and Environmental Services, Inc. 1288 North 14th Avenue, Unit 103 • Bozeman, MT 59715 • 406-219-2633 Kalispell AWWTP Dewatering Improvements Work Authorization No. 1— Early Work Package Recommendation of Award Page 2 of 2 WORK AUTHORIZATION NO. 1 - EARLY WORK PACKAGE SCOPE SUMMARY: Swank Enterprise will perform the following scope of work: • Installation of temporary facilities to include cake loadout structure located outside of the existing volute press garage bay • Demolition on DAF tank (west behind existing Belt Filter Press) and associated process pipe and appurtenances • Demolition of WAS pipe in southeast corner • Shop Drawings and As -built Piping • Procure Valves • Conveyor Submittals • Exclusions: Demolition of process pumps, pipes, equipment in use. Existing conveyor will remain unmodified and fully operational throughout the duration of Early Work Package. Substantial completion for this work is within 45 days of authorization. Substantial completion will be met following completion of: Milestone: Successful installation of temporary cake loadout facility. PROPOSAL & WORK AUTHORIZATION EVALUATION: Swank Enterprise's project proposal was found to be responsive and complete. Swank Enterprise was selected as the GCCM for the Kalispell AWWTP Dewatering Improvements Project Award and is currently contracted for Preconstruction Services. Award will lead to successful completion of the initial project scope of work and keep the project on track. REQUESTED CITY OF KALISPELL COUNCIL ACTION: AE2S recommends moving to approve the Work Authorization No. 1— Early Work Package. AE2S appreciates the opportunity to provide the City of Kalispell with professional engineering services for this important project. If you wish to discuss any of this information or have questions prior to issuing the Notice of Award, please do not hesitate to contact me. Sincerely, AE2S Scott Buecker, PE Wastewater Practice Leader Encl.: Work Authorization https://ae2s.sharepoint.com/sites/Kalispe11WWTPBiosolidsTreatmentDisposaf/Shared Documents/04.0 Project Work/04.08 GCCM/Agreement - Work Authorizations/2 - Early Work Package/Early Work Package - Recommendation of Award 250812.dou