Loading...
06-20-24 Site Development Review Committee MinutesSITE DEVELOPMENT REVIEW COMMITTEE SUMMARY Thursday, Thursday, June 20, 2024 First Floor Conference Room 201 First Avenue East ATTENDING: Kari Barnhart, Planner II Patrick Jentz, Engineer III PJ Sorensen, Senior Planner Rick Parker, Plans Examiner Dan Pearce, Fire Chief GUESTS: None. HEAR THE PUBLIC: None. PERFORMANCE BOND REMINDERS: Planning is working with Public Works to clean up the current list of performance bonds. OLD BUSINESS: Casa Mexico – 1600 US Hwy 93 S – TI expansion/parking lot – Public Works is working through an easement. The landscaping is still pending approval. This will be on the agenda next week. Samaritan House – 1110 2nd St W – new apartment and community building – Public Works can conditionally approve pending the mailbox location issue. Plan Review is still waiting on the truss information. This will be on the agenda next week. Everhome Suites – 1900 Jefferson Blvd – new hotel – Parks, Fire, and Public Works are approved. Plan Review advised that the plans are still pending approval. This will be on the agenda next week. Village Loop Mixed Use – 63 Village Loop – new mixed use bldg. – Public Works received correspondence from them. Plan Review received comments from them. This will be on the agenda next week. VA Clinic – 750 Reserve Pl – new clinic –Plan Review is complete. Planning advised that there are new landscape comments in Parks’ queue. This will be on the agenda next week. Beehive Homes PH 3 – 242 Stillwater Rd – new building – Public Works has new resubmittal in their queue. Plan Review is in process. This will be on the agenda next week. Stillwater Crossing Apts Ph 2 – Four Mile/Stillwater Rd – new apartments – Plan Review is in process. Public Works advised that the subdivision is not approved. The committee decided to remove this from the agenda. Greater Valley Health Center – 1933 3rd Ave E – bldg. & site remodel – Public Works is working through the submittal. Plan Review is complete. Planning advised that the number of parking spaces meets the minimum requirement and that they won’t be ready for a building permit until early July. This will be on the agenda next week. MSU College of Nursing – 331 Heritage Way – Public Works is missing the design report. Fire is working with them on the KnoxBox and control panel location. This will be on the agenda next week. Peak Fitness – 637 E Idaho St – fitness center – Public Works and Plan Review advised that the submittal is incomplete. This will be on the agenda next week. Red Eagle Hangar – Ryan Lane – city airport – Plan Review has this in their queue. NEW BUSINESS: None. PLANNING OFFICE ITEMS: None. OTHER ITEMS: None. The meeting was adjourned at 10:12 AM. cc: Police City Manager City Clerk Building Fire Community Development Planning Parks Public Works MDT