E2. Change Order for Tank and Wells Project CITY OF )poor KALISPELL MEMORANDUM To: Doug Russell —City Manager CC: Susie Turner, PE—Public Works Director From: Keith Haskins, PE—Deputy Director Public Works Re: Schedule 4—2023 Kalispell Tank and Wells Project Meeting Date: 1/16/2024 BACKGROUND: In April of 2023, Council awarded Schedule 4 of the 2023 Kalispell Tank and Wells Project to S&L Underground for$2,471,184. Schedule 4 is for final development and construction of the well facility located near the entrance to the Buffalo Hill Golf Course. Construction of this schedule started in earnest in September and is currently approaching 50% completion. At the time of bidding of the project, well development of the North Main Well was incomplete. The contractor responsible to drill and develop the well (O'Keefe Drilling), encountered higher than expected concentrations of sand during well development. O'Keefe Drilling completed additional "air-bursting" techniques in an attempt to remove sand and increase yield but were met with limited success. Subsequently, a second contractor(Viking Pumps)was brought in to "block surge" the well for an additional 40 hours. Ultimately, an acceptable well yield was achieved, but sand concentrations are still above optimal. For these reasons, modifications to the specifications for the well pump and a sand separator were designed and added into the project. The well pump specifications were changed to require stainless steel impellers and more robust bearings to extend the life of the pump. A sand separator is necessary to remove sand before it enters into the water storage tanks or distribution systems. Currently, the City has two other sand separators in its water production system. One is installed at the Grandview Wells Facility, and one is installed at Old School Station Facility. The separators use a centrifugal filtration to remove sand and sediment. In order to add the sand separator into the project, design modifications also had to be made to the foundation, above floor facility piping, electrical, and below floor drainage piping. An additional change that was identified after bid award was the absence of a requirement for the contractor to provide and install a transducer for the wells on the project. The transducer provides staff instantaneous water depths inside the well which allows staff to monitor drawdown and recharge of the wells. In order to accomplish this, staff negotiated with the contractor to provide and install the stilling well conduit for the transducer. Water Division staff will procure and install the transducer prior to programing and startup of the facilities. 201 1'Avenue E Phone(406)758-7720 Po Box 1997 Public Works Department Fax(406)758-7831 Kalispell,MT 59903 1 1 www.kalispell.com A jib-crane was added to the project for future maintenance of the sand separator. Because the foundation was being poured during the design of the separator and prior to pricing from the contractor, the contractor was directed to proceed with the modifications to the foundation and those modifications require reimbursement. Ultimately the jib-crane was removed from the project due to the price provided by the contractor. If a jib-crane is required for future maintenance, a design has been completed and the foundation bolts are in place for its installation. City staff will procure and install the jib-crane, if necessary, at that time. The Engineer on the project, Robert Peccia and Associates, has negotiated and recommended a change order to complete or reimburse the contractor for the work described above. The change order detailing the costs is attached. REQUESTED ACTION: Motion to approve Change Order 1 for Schedule 4 of the Kalispell Tank and Wells Project for an increase in the contract price of$95,374.83 for a total contract price of$2,566,558.83 and the addition of 15 calendar days. FISCAL EFFECTS: Contingency funds were budgeted and are adequate to cover this increase in contract price. CHANGE ORDER NO.: 1 Owner: City of Kalispell Owner's Project No.: Engineer: Robert Peccia&Associates Engineer's Project No.: 20706.000 Contractor:S&L Underground, Inc. Contractor's Project No.: Project: 2023 Kalispell Tank and Wells Project Contract Name: 2023 Kalispell Tank and Wells Project Schedule 4 North Main Well Date Issued: 1/2/2024 Effective Date of Change Order: 1/2/24 The Contract is modified as follows upon execution of this Change Order: Description:This Change Order is for Schedule 4 of the Kalispell Tank and Wells project and includes the labor and materials to install the level transducer stilling well and conduit,well pump upgrades,the sand separator and piping modifications,the sand separator drain line catch basin, and the concrete and foundation work for the sand separator drain line and jib crane.The contractor has requested an additional fifteen (15)contract days to complete the work listed above. Attachments: Change order request from S&L Underground Change in Contract Times [State Contract Times as either a specific date or a Change in Contract Price number of days] Original Contract Price: Original Contract Times: Substantial Completion:200 Calendar Days $2,471,184.00 Ready for final payment:60 Calendar Days Increase from previously approved Change Orders- Increase from previously approved Change NONE: Orders-NONE: Substantial Completion: N/A $0.00 Ready for final payment: N/A Contract Price prior to this Change Order: Contract Times prior to this Change Order: Substantial Completion:200 Calendar Days $2,471,184.00 Ready for final payment: 60 Calendar Days Increase this Change Order: Increase this Change Order: Substantial Completion:15 Calendar Days $95,374.83 Ready for final payment: 15 Calendar Days Contract Price incorporating this Change Order: Contract Times with all approved Change Orders: Substantial Completion:215 Calendar Day $2,566,558.83 Ready for final payment:60 Calendar Day Recommended by gine (if req fired) Accepted by Contractor By: Kaela Murphy, PE � [n��l)�15EY1 9aa'1i1� Title: Project Engineer ere,i'dt'i1 Date: 1/2/24 2 Authorized by Owner Approved by Funding Agency(if applicable) By: N/A Title: N/A Date: N/A EJCDC®C-941,Change Order EJCDC®C-941,Change Order,Rev.1. Copyright02018 National Society of Professional Engineers,American Council of Engineering Companies and American Society of Civil Engineers.All rights reserved. 5 0 range LS $ (11,000.00) 1 $ (11,000.00) I Upgrade LS $ 5,396.03 1 $ 5,396.03 mpeller LS $ (8,000.00) 1 $ (8,000.00) !aring W/SS Backing LS $ 3,076.92 1 $ 3,076.92 S&L Completed Items 6 iipment Cost LS $ 42,577.43 1 $ 42,577.43 HIR $ 102.00 130 $ 13,260.00 iteer DAY $ 425.00 1 $ 425.00 DAY $ 95.00 5 $ 475.00 id Tools DAY $ 135.00 5 $ 675.00 nstalling Unit- Specialty Hoist LS $ 1,750.00 1 $ 1,750.00 LS $ 325.00 1 $ 325.00 rnent Pad Materials and Rebar LS $ 750.00 1 $ 750.00 -ical for Sand Separator LS $ 990.00 1 $ 990.00 Catch Basin 3 LS $ 1,839.00 1 $ 1,839.00 HIR $ 102.00 50 $ 5,100.00 DAY $ 750.00 3 $ 2,250.00 ne From Bonners Ferry LS $ 500.00 1 $ 500.00 'to rDAY $ 375.00 1 $ 375.00 DAY $ 95.00 3 $ 285.00 DAY $ 165.00 3 $ 495.00 YD $ 32.50 20 $ 650.00 'ete Work/Foundation 2 s LS $ 275.00 1 $ 275.00 Stem Wall LS $ 175.00 1 $ 175.00 Crane Footings LS $ 425.00 1 $ 425.00 is LS $ 75.00 1 $ 75.00 r and epoxy into stem wall LS $ 375.00 1 $ 375.00 YD $ 32.50 8 $ 260.00 (cavator HR $ 45.00 8 $ 360.00 r DAY $ 165.00 1 $ 165.00 f Saw DAY $ 85.00 1 $ 85.00 Excavator HR $ 45.00 5 $ 225.00 :ker DAY $ 165.00 1 $ 165.00 HIR $ 102.00 60 $ 6,120.00 DAY $ 95.00 2 $ 190.00 is Saws DAY $ 135.00 1 $ 135.00 2 LS $ 14,000.00 0 $ - H R $ 102.00 0 $ - DAY $ 95.00 0 $ - DAY $ 135.00 0 $ - rklift DAY $ 425.00 0 $ - ware LS $ 750.00 0 $ - r Items Subtotal $ 81,751.43 )verhead 15% $ 12,262.71 Deduct $ (10,527.05) Jition $ 8,662.50 $ 92,149.59 LU O O LO O LOix) CO Z N O ` O Iti M (D Z .� co IT 00 LO I KJ LO Q L O KJ Q9 Q9 Q9 Ef} 60 N J � U J Z ~ 0 0 0 0 0 0 O 0 0 0 0 0 0 O O IT 0 0 0 0 OD O 00 O O O O 00 0 0 0 0 0 O O Ln O Lr)- -i nJ N O ti O ti ti QU r � 00 LO I IT Z L Ef} Q9 60 Q9 60 Q9 N 0 C7 � o O 0 000000m C) 0000000 O IT 0 0 0 0 IT L N O 00 O O O O I` = d Z3 O 0 0 0 0 M '-' C)) O O LO O LO LO O ti O ti M 06 EfJ Efl Efl Efl Efl Efl N O II � (Q L O U }, O Z5 U C/) M c LO O N M O -O LO c N 0 LO O LL .N O m Q)LO U x O L O U) c6 Y U) O * N U Q) 70 M _ cu _ (Q 0) (Q .0 (6 Q L C: CU C _ U UQ UO 0 > L (D O (Q mUci� � w � a CO c Q) O M M M M co += J J J J J