Staff Report/Spring Creek Park Ph 2 & 3 Preliminary PlatKALisPEii. Development Services Department 201 1st Avenue East Kalispell, MT 59901 Phone: (406) 758-7940 Fax: (406) 758-7739 www.kalispell.com/plannine REPORT TO: Doug Russell, City Manager FROM: PJ Sorensen, Senior Planner SUBJECT: KPP-23-01 — Spring Creek Park Phases 2 & 3 Preliminary Plat MEETING DATE: March 6, 2023 BACKGROUND: GKM Associates, LLC, has submitted a request for preliminary plat approval for Spring Creek Park Phases 2 and 3, a major subdivision on approximately 49.6 acres located to the southeast of the intersection of Three Mile Drive and West Springcreek Road. The subdivision would contain 22 lots (18 attached single-family lots, three multi -family lots, and one commercial lot) as well as streets, parks and open space. It is anticipated that the multi -family lots would contain up to 464 dwelling units. The development proposal is consistent with a Planned Unit Development ("PUD") overlay approved by the Kalispell City Council on March 21, 2022 (Ordinance 1873), which provided for a total of 642 residential units (464 multi -family, 65 detached single-family dwellings, and 113 townhome/rowhouse dwellings), along with 2 commercial lots. The property can be described as Tract 1 of Certificate of Survey No. 20588, a tract of land, situated, lying and being in the Northwest Quarter of Section 11, Township 28 North, Range 22 West, P.M.M., Flathead County, Montana, excepting therefrom the subdivision plat of Spring Creek Park Phase IA, on file and of record in Flathead County, Montana, located in the northwest one quarter of Section 11, Township 28 North, Range 22 West, Principal Meridian, Montana, City of Kalispell, County of Flathead, Montana. The Kalispell Planning Board held a duly noticed public hearing on February 14, 2023, to consider the request. Staff presented staff report KPP-23-01 providing details of the proposal and evaluation. Staff recommended that the Planning Board adopt the staff report as findings of fact and recommend to the Council that the request be granted subject to 35 listed conditions. Other than from the applicant, no public comments were received at the public hearing, although two written public comments were submitted. The public comment generally focused on traffic. The public hearing was closed and a motion was presented to adopt staff report KPP-23-01 as findings of fact and recommend to the Kalispell City Council that the preliminary plat be approved subject to the 35 conditions. Board discussion concluded that the request was appropriate, and the motion was approved on a unanimous vote. RECOMMENDATION: PRELIMINARY PLAT: It is recommended that the Kalispell City Council approve Resolution 6121, a resolution approving a request from GKM Associates, LLC, for approval of the preliminary plat for Spring Creek Park Phases 2 & 3 (KPP-23-01), a major subdivision preliminary plat consisting of approximately 49.6 acres with 35 conditions of approval, which can be described as Tract 1 of Certificate of Survey No. 20588, a tract of land, situated, lying and being in the Northwest Quarter of Section 11, Township 28 North, Range 22 West, P.M.M., Flathead County, Montana, excepting therefrom the subdivision plat of Spring Creek Park Phase IA, on file and of record in Flathead County, Montana, located in the northwest one quarter of Section 11, Township 28 North, Range 22 West, Principal Meridian, Montana, City of Kalispell, County of Flathead, Montana. FISCAL EFFECTS: There are no anticipated fiscal impacts at this time. ALTERNATIVES: Deny the request. ATTACHMENTS: Resolution 6121 February 14, 2023, Kalispell Planning Board Minutes Staff Report Maps Application Materials Linked Here Public Comment Aimee Brunckhorst, Kalispell City Clerk RESOLUTION NO. 6121 A RESOLUTION CONDITIONALLY APPROVING THE PRELIMINARY PLAT OF PHASES 2 AND 3 OF SPRING CREEK PARK, DESCRIBED AS TRACT 1 OF CERTIFICATE OF SURVEY NO.20588, A TRACT OF LAND, SITUATED, LYING AND BEING IN THE NORTHWEST QUARTER OF SECTION 11, TOWNSHIP 28 NORTH, RANGE 22 WEST, P.M.M., FLATHEAD COUNTY, MONTANA. WHEREAS, GKM Associates, LLC, the owner of the certain real property described above, has petitioned for approval of Phases 2 and 3 of the Subdivision Plat of said property; and WHEREAS, the Kalispell City Planning Board and Zoning Commission held a public hearing on February 14, 2023 on the proposal and reviewed Subdivision Report #KPP-23-01 issued by the Kalispell Planning Department; and WHEREAS, the Kalispell City Planning Board and Zoning Commission has recommended approval of the Preliminary Plat of Phases 2 and 3 of Spring Creek Park, subject to certain conditions and recommendations; and WHEREAS, the city council of the City of Kalispell at its regular council meeting of March 6, 2023, reviewed the Kalispell Planning Department Report #KPP-23-01, reviewed the recommendations of the Kalispell City Planning Board and Zoning Commission, and found from the Preliminary Plat, and evidence, that the subdivision is in the public interest. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF KALISPELL, MONTANA AS FOLLOWS: SECTION 1. That the Findings of Fact contained in Kalispell Planning Department Report #KPP-23-01 are hereby adopted as the Findings of Fact of the city council. SECTION 2. That the application of GKM Associates, LLC for approval of the Preliminary Plat of Phases 2 and 3 of Spring Creek Park, Kalispell, Flathead County, Montana is hereby approved subject to the following conditions: The development of the site shall be in substantial compliance with the application submitted, the site plan, materials and other specifications as well as any additional conditions associated with the preliminary plat as approved by the city council. 2. The preliminary plat approval shall be valid for a period of three years from the date of approval. 3. The storm water ponds shall be designed in a way that they become a visual interest to the development. Chain link fencing surrounding the retention pond as the dominant fixture shall not be allowed without mitigation. The developer shall work closely with the Parks Department and Public Works to develop a design that is both visually appealing and meets the required safety guidelines. It is intended that when the project is developed the ponds will act as features, particularly along the roadways, rather than a private maintenance utility facility. 4. The developer shall submit to the Kalispell Public Works Department for review and approval a storm water report and an engineered drainage plan that meets the requirements of the current city standards for design and construction. Any open storm water facilities should have an elevated aesthetic design to be reviewed and approved by the city Architectural Review Committee. Prior to final plat, a certification shall be submitted to the public works department stating that the drainage plan for the subdivision has been installed as designed and approved. 5. The developer shall submit to the Kalispell Public Works Department prior to construction an erosion/sediment control plan for review and approval and a copy of all documents submitted to Montana Department of Environmental Quality for the General Permit for Storm Water Discharge Associated with Construction Activities. 6. The developer shall submit water and sanitary sewer plans, applicable specifications, and design reports to the Kalispell Public Works Department and the Montana Department of Environmental Quality for concurrent review, with approval of both required prior to construction. 7. New infrastructure required to serve the subdivision shall be designed and constructed in accordance with the City of Kalispell's Standards for Design and Construction. All design work shall be reviewed and approved in writing by the Kalispell Public Works Department prior to construction. This infrastructure shall include but not be limited to streets, street lighting, street signage, curb, gutter, boulevard and sidewalks. 8. Water and sewer main extensions shall be designed and constructed in accordance with the City of Kalispell's Standards for Design and Construction and in compliance with the city's facilities update and extensions of services plans. The water and sewer main extension plans shall be reviewed and approved by the Kalispell Public Works Department. Prior to final plat, a certification shall be submitted to the Public Works Department stating that the water and sewer mains have been built and tested as designed and approved. 9. Per city standards, the water mains shall be extended within the adjacent frontages to the far property line. The main in West Springcreek shall be extended with Phase 2. The main may need to be upsized, and the city would participate in the upsize cost. 10. Any water rights associated with the property shall be transferred to the City of Kalispell. The water rights shall be allocated proportionally for each phase of the development prior to final plat. 11. The full length of the sewer main within West Springcreek shall be installed in conjunction with Phase 2. Due to topography, a full extension to the south property line will likely not be required, but will be subject to review and approval by the Public Works Department. 12. The developer shall submit the street designs to the Kalispell Public Works Department for review and approval prior to construction. Street designs shall meet the city standards for design and construction. 13. Three Mile and West Springcreek shall be upgraded for the length of the frontage to a minor arterial standard. Improvements may include, but would not necessarily be limited to, widening travel lanes, bike/pedestrian paths, landscape boulevard, streetlights, and curb/gutter. Dedication of additional right-of-way will be required for improvements for the adjoining roadways, as well as for the roundabout at the intersection of Three Mile Drive and West Springcreek. Improvements for both Three Mile and West Springcreek shall be installed with Phase 2. 14. Internal streets would include streets built to local/collector design standards pursuant to the Standards for Design and Construction including, but not limited to, sidewalks, landscape boulevard, streetlights, and curb/gutter. At the west end of Triple Creek Drive, there shall be a hammerhead turnaround or other approved alternated design to accommodate snow plowing and emergency access. 15. A turning movement distribution shall be provided if a compact roundabout internal to Phase 2 is to be built. lfjustified, adequate right-of-way shall be dedicated to provide a single lane, compact roundabout with a minimum 80-foot diameter. 16. Alleys included within the plat shall be maintained as private alleys with public utility easements. Any lot located on the collector with an alley shall access only from the alley. 17. Pursuant to Sec 28.3.25 of the subdivision regulations, the final plat shall include a note stating that "The owners hereby waive the right to protest the creation of an SID for the purpose of financing improvements to area roads which specifically benefit this subdivision." 18. Prior to final plat, all mitigation recommended as part of the approved traffic impact study relative to the given phase shall be completed. All improvements shall be reviewed and approved by the Public Works Department. Per the city Standards for Design and Construction, the development shall maintain or improve the existing level of service for the affected roadways rather than simply maintaining an acceptable level of service. Improvements necessary to maintain the existing level of service will be required. 19. Based on the Traffic Impact Study ("TIS") and city review of the TIS, there are several areas which require mitigation. (a) Intersection of Three Mile Drive and West Springcreek: A roundabout shall be installed with Phase 2 at the intersection. The roundabout will require dedication of additional right-of-way. The specific design of the roundabout is subject to MDT review and approval, as well as review and approval by the Kalispell Public Works Department. (b) Intersection of the internal collector road and Three Mile Drive: The intersection shall include a northbound right turn lane. (c) Intersection of Camp Crook Avenue and Three Mile Drive: Northbound left-hand turns shall be restricted. This improvement, which is also a condition of Phase 1, shall be installed prior to the final plat of Phase 2 (d) Intersection of Heaven's Peak and Three Mile Drive: The developer shall provide a 14-hour intersection turning movement study and install a signalized intersection at Three Mile Drive and Heaven's Peak Drive when warrants are met per Manual on Uniform Traffic Control Devices and MDT. (e) Intersection of Stillwater Road and Three Mile Drive: The developer shall provide a 14-hour intersection turning movement study to determine if a signal is warranted. When warranted, staff recommends a regional SID to construct the signal. 20. The recommendations in the Geotech report shall be followed. 21. Basements are not allowed within the development unless appropriately designed with waterproofing and other design elements required by the Kalispell Building Department. All building sites within the development shall be subj ect to additional review if required by the Kalispell Building Department including, but not necessarily limited to, site specific geotechnical investigation. 22. Under Section 28.3.06 of the subdivision regulations, the development shall maintain a minimum 100-foot setback from wetlands to any proposed lot boundaries. Under Section 28.3.07, the development shall limit uses within the 50-foot setback from the stream. 23. Prior to final plat, a letter from the Kalispell Public Works Department shall be submitted stating that all new infrastructure has been accepted by the City of Kalispell, any private infrastructure has been constructed per city standards, and a proper bond has been accepted for unfinished work. 24. All existing and proposed easements shall be indicated on the face of the final plat. Utility easements for city water and sewer shall be provided to allow for the logical extension of utilities from this subdivision to adjoining properties. A letter from the Kalispell Public Works Department shall be obtained stating that the required easements are being shown on the final plat. 25. The following statement shall appear on the final plat: "The undersigned hereby grants unto each and every person, firm or corporation, whether public or private, providing or offering to provide telephone, telegraph, electric power, gas, cable television, water or sewer service to the public, the right to the joint use of an easement for the construction, maintenance, repair, and removal of their lines and other facilities, in, over, under, and across each area designated on this plat as "Utility Easement" to have and to hold forever." Developer's Signature 26. Prior to filing the final plat, a letter from the US Postal Service shall be included stating the Service has reviewed and approved of the design and location of the mail delivery site. The mail delivery site shall be installed or bonded for prior to final plat. In addition, the mail delivery site and improvements shall also be included in the preliminary and final engineering plans to be reviewed by the Public Works Department. The mail delivery site shall not impact a sidewalk or proposed boulevard area. 27. A homeowner's association (HOA) shall be formed and established to provide for the maintenance of the common areas, including, but not necessarily limited to, roads, parks and open space. Maintenance of any private roads and alleys shall include both short term and long-term maintenance including, but not necessarily limited to, snow plowing, landscaping, sidewalks, street repairs, overlays, and rebuilds of the street. 28. A letter from the Kalispell Fire Department approving the access, placement of the fire hydrants and fire flows within the subdivision shall be submitted prior to final plat. 29. A letter shall be obtained from the Parks and Recreation Director approving a landscape plan for the placement of trees and landscaping materials within the landscape boulevards of the streets serving the subdivision, common area, and adjoining rights -of -way. The approved landscape plan shall be implemented or a cash -in -lieu payment for installation of the street trees and groundcover be provided to the Kalispell Parks and Recreation Department. 30. A park plan shall be created and approved by the Parks and Recreation Director prior to final plat of Phase 2. 31. A note shall be placed on the final plat indicating a waiver of the right to protest creation of a park maintenance district. This district shall only be activated in the event that the property owners' association defaults on their park and open space amenity conditions. The assessments levied within the maintenance district shall be determined by the Parks and Recreation Department with approvals by the Kalispell City Council. 32. A note shall be placed on the final plat indicating a waiver of the right to protest creation of a stormwater maintenance district. This district shall only be activated in the event that the property owner(s) default on the maintenance of the approved stormwater facilities. The assessments levied within the maintenance district shall be determined by the Public Works Department with approvals by the Kalispell City Council. 33. A minimum of two-thirds of the necessary infrastructure for the subdivision shall be completed prior to final plat submittal. 34. All utilities shall be installed underground and in locations that are approved by the Kalispell Public Works Department in accordance with the Kalispell Standards for Design and Construction. 35. All areas disturbed during development shall be re -vegetated with a weed -free mix immediately after development. SECTION 3. Upon proper review and filing of the Final Plat of said subdivision in the office of the Flathead County Clerk and Recorder, said premises shall be a subdivision of the City of Kalispell. PASSED AND APPROVED BY THE CITY COUNCIL AND SIGNED BY THE MAYOR OF THE CITY OF KALISPELL THIS 6TH DAY OF MARCH, 2023. ATTEST: Aimee Brunckhorst, CMC City Clerk Mark Johnson Mayor KALISPELL CITY PLANNING BOARD & ZONING COMMISSION MINUTES OF REGULAR MEETING February 14, 2023 CALL TO ORDER AND ROLL The regular meeting of the Kalispell City Planning Board and Zoning CALL Commission was called to order at 6:00 p.m. Board members present were Chad Graham (chair), Pip Burke, Kevin Aurich, Doug Kauffman, Rory Young, Kurt Vomfell, and Joshua Borgardt. PJ Sorensen and Jarod Nygren represented the Kalispell Planning Department. Keith Haskins representing the Kalispell Public Works Department. APPROVAL OF MINUTES Vomfell moved and Borgardt seconded a motion to approve the minutes of the January 10, 2023, meeting of the Kalispell City Planning Board and Zoning Commission. VOTE BY ACCLAMATION The motion passed unanimously on a vote of acclamation. HEAR THE PUBLIC None. KA-22-09, KPUD-22-05, KPP-22-08 A request from Timberwolf Ridge, LLC, for annexation, initial zoning of TIMBERWOLF RIDGE RA-1 (Residential Apartment) with a Residential Planned Unit Development ("PUD") overlay, and major preliminary plat on approximately 20.1 acres of land. The development, called Timberwolf Ridge, would contain up to 400 multi -family dwelling units in six (6) buildings on six (6) lots along with parking, recreational amenities, and open space. The property is located at 605 Stillwater Road at the intersection of Stillwater Road and Timberwolf Parkway and can be described as Parcel A of Certificate of Survey Number 16743, situated, lying and being in the Southwest Quarter of the Southwest Quarter of the Northwest Quarter and the Northwest Quarter of the Northwest Quarter of the Southwest Quarter of Section 36, Township 29 North, Range 22 West, P.M.M., Flathead County, Montana. STAFF REPORT PJ Sorensen representing the Kalispell Planning Department reviewed Staff Report #KA-22-09, KPUD-22-05, & KPP-22-08. Staff recommends that the Kalispell City Planning Board and Zoning Commission adopt Staff Report #KA-22-09, KPUD-22-05, & KPP-22-08 as findings of fact and recommend to the Kalispell City Council that the property be annexed and the zoning for the property be RA-1 (Residential Apartment), with a PUD overlay, the preliminary plat be approved, and that the preliminary plat be approved. BOARD DISCUSSION Graham requested to see the presentation from the applicant that shows how they arrived with their design. David Koel from Cushing Terrell gave the presentation. PUBLIC COMMENT None. MOTION — KA-22-09 Vomfell moved and Kauffman seconded that the Kalispell Planning Board adopt staff report #KA-22-09 as findings of fact and recommend to the Kalispell City Council that the property be annexed and the zoning for the property be RA-1 (Residential Apartment), with a PUD overlay. BOARD DISCUSSION None. Kalispell City Planning Board Minutes of the meeting of February 14, 2023 Pagel ROLL CALL Motion passed unanimously on a roll call vote. MOTION — KPUD-22-05 Kauffman moved and Vomfell seconded that the Kalispell City Planning Board and Zoning Commission adopt Staff Report #KPUD-22-05 as findings of fact and recommend to the Kalispell City Council that the Timberwolf Ridge PUD be approved subject to the conditions listed in the staff report. BOARD DISCUSSION Young felt that the condition for the stormwater ponds being a visual interest is very subjective. Sorensen advised that detailed plans are typically not provided at this stage and that this verbiage has been used for PUDs in previous years. Nygren stated that it is difficult to design them without a full engineered design due to many variables. They do have some good templates that guide developers but there are plans to do some updates. ROLL CALL Motion passed unanimously on a roll call vote. MOTION — KPP-22-08 Vomfell moved and Young seconded that the Kalispell City Planning Board and Zoning Commission adopt staff report #KPP-22-08 as findings of fact and recommend to the Kalispell City Council that the preliminary plat for Timberwolf Ridge be approved subject to the conditions listed in the staff report. BOARD DISCUSSION None. ROLL CALL Motion passed unanimously on a roll call vote. KPP-23-01— SPRING CREEK A request from GKM Associates, LLC, for preliminary plat approval for PARK PHASES 2 & 3 Spring Creek Park Phases 2 and 3, a major subdivision on approximately 49.6 acres located to the southeast of the intersection of Three Mile Drive and West Springcreek Road. The subdivision would contain 22 lots (18 attached single-family lots, three multi -family lots, and one commercial lot) as well as streets, parks and open space. It is anticipated that the multi- family lots would contain up to 464 dwelling units. The development proposal is consistent with a Planned Unit Development overlay approved by the Kalispell City Council on March 21, 2022 (Ordinance 1873). The property can be described as Tract 1 of Certificate of Survey No. 20588, a tract of land, situated, lying and being in the Northwest Quarter of Section 11, Township 28 North, Range 22 West, P.M.M., Flathead County, Montana, excepting therefrom the subdivision plat of Spring Creek Park Phase IA, on file and of record in Flathead County, Montana, located in the northwest one quarter of Section 11, Township 28 North, Range 22 West, Principal Meridian, Montana, City of Kalispell, County of Flathead, Montana. STAFF REPORT PJ Sorensen representing the Kalispell Planning Department reviewed Staff Report #KPP-23-01. Staff recommends that the Kalispell City Planning Board and Zoning Commission adopt staff report #KPP-23-01 as findings of fact and recommend to the Kalispell City Council that the preliminary plat for Spring Creek Park Phases 2 and 3 be approved subject to the conditions in the staff report. Kalispell City Planning Board Minutes of the meeting of February 14, 2023 Page 12 BOARD DISCUSSION Young asked staff if Phase 3 could be platted before Phase 1. Sorensen and Nygren advised that it could be but the improvements would be done based on the associated PUD. Graham asked staff if there is something to trigger improvements. Sorensen advised that MDT bases warranted improvements on actual traffic volumes and the uniform traffic manual. MDT requires studies done before and would likely require the developer to put some funds into escrow or bond for it to cover the cost of the required improvements. Once warrants are in, they would install them. Graham confirmed with staff that part of the Phase 2 & 3 improvements would be going in as part of the PUD. Graham also stated that this project was previously approved and is not a new project. Sorensen added that all 5 traffic mitigation conditions were part of the 2022 PUD approval; there is no additional density and there is the same number of lots. PUBLIC COMMENT Mike Brodie, representing the developer, advised the Board that they conducted a warrant study for Phase 1 and a traffic signal is not currently warranted, but after they conducted a sensitivity analysis, a signal would be warranted after Phase 2. They are working with MDT on roundabout. MOTION — KPP-23-01 Vomfell motioned and Burke seconded that the Kalispell City Planning Board and Zoning Commission adopt staff report #KPP-23-01 as findings of fact and recommend to the Kalispell City Council that the preliminary plat for Spring Creek Park Phases 2 and 3 be approved subject to the conditions listed in the staff report. BOARD DISCUSSION None. ROLL CALL Motion passed unanimously on a roll call vote. KA-23-01— FOUR MILE WELL A request from the City of Kalispell for annexation and initial zoning of SITE R-2 (Residential) of a property located at 850 Four Mile Drive. The property is intended to be used as a well site which would be part of the city water system infrastructure. The property can be described as a tract of land located in the Northwest Quarter of the Northeast Quarter of Section 2, Township 28 North, Range 22 West, P.M.M., Flathead County, Montana, and further described as Tract 1 of Certificate of Survey No. 12112, containing 1.52 acres, more or less, as filed in the office of the Clerk and Recorder of Flathead County, Montana, on February 24', 1995, as Document No. 9505515180. STAFF REPORT PJ Sorensen representing the Kalispell Planning Department reviewed Staff Report #KA-23-01. Staff recommends that the Kalispell City Planning Board and Zoning Commission adopt Staff Report #KA-23-01 as findings of fact and recommend to the Kalispell City Council that the property be annexed and the zoning for the property be city R-2 (Residential). BOARD DISCUSSION Young asked if there is additional R-2 zoning outside of the subject property. Sorensen advised that the suburban residential designation generally supports R-1, R-2, R-3, and R-4. The property immediately adjacent to the east is currently city zoned for R-2. Vomfell asked how the city determines if there is adequate water supply. Sorensen advised that the facilities, transportation, water, and stormwater plans are all incorporated in the growth policy. Haskins advised that prior to approving Kalispell City Planning Board Minutes of the meeting of February 14, 2023 Page13 a new development, Public Works reviews firm capacity and storage tank capacity and the demand that a new development would require and that they are adding new development into the models for facility plans. Young confirmed with staff that the city must follow DEQ and the State of Montana requirements. Nygren advised that they allocate density to certain areas within the urban growth boundaries and that they are planning out to 75 to 100 years of growth. Developers pay the impact fees that are used for the construction of the well sites and water storage. PUBLIC COMMENT None. MOTION — KA-23-01 Kauffman motioned and Vomfell seconded that the Kalispell City Planning Board and Zoning Commission adopt Staff Report #KA-23-01 as findings of fact and recommend to the Kalispell City Council that the property be annexed and the zoning for the property be city R-2 (Residential). BOARD DISCUSSION None. ROLL CALL Motion passed unanimously on a roll call vote. OLD BUSINESS Nygren advised that the city was awarded a planning grant to make Main Street more pedestrian friendly. The planning process will take 2-3 years and will require working with the County, MDT, and USDOT, . NEW BUSINESS Sorensen updated the board on the upcoming March 14, 2023 Planning Board Meeting. ADJOURNMENT The meeting adjourned at approximately 6:58 pm. Chad Graham President APPROVED as submitted/amended: Kirstin Robinson Recording Secretary Kalispell City Planning Board Minutes of the meeting of February 14, 2023 Page 14 SPRING CREEK PARK PHASES 2 & 3 MAJOR SUBDIVISION - STAFF REPORT #KPP-23-01 KALISPELL PLANNING DEPARTMENT FEBRUARY 8, 2023 A report to the Kalispell City Planning Board and the Kalispell City Council regarding a request from GKM Associates, LLC, for major preliminary plat for Phases 2 and 3 of the development on approximately 49.6 acres. A public hearing has been scheduled before the Planning Board for February 14, 2023, beginning at 6:00 PM in the Kalispell City Council Chambers. The Planning Board will forward a recommendation to the Kalispell City Council for final action. BACKGROUND INFORMATION This report regards a request from GKM Associates, LLC, for preliminary plat approval for Spring Creek Park Phases 2 and 3, a major subdivision on approximately 49.6 acres located to the southeast of the intersection of Three Mile Drive and West Springcreek Road. The subdivision would contain 22 lots (18 attached single-family lots, three multi -family lots, and one commercial lot) as well as streets, parks and open space. It is anticipated that the multi- family lots would contain up to 464 dwelling units. The development proposal is consistent with a Planned Unit Development ("PUD") overlay approved by the Kalispell City Council on March 21, 2022 (Ordinance 1873), which provided for a total of 642 residential units (464 multi -family, 65 detached single-family dwellings, and 113 townhome/rowhouse dwellings), along with 2 commercial lots. A: Applicant: GKM Associates, LLC 208 1st Ave E Kalispell, MT 59901 B: Location: The property can be described as Tract 1 of Certificate of Survey No. 20588, a tract of land, situated, lying and being in the Northwest Quarter of Section 11, Township 28 North, Range 22 West, P.M.M., Flathead County, Montana, excepting therefrom the subdivision plat of Spring Creek Park Phase IA, on file and of record in Flathead County, Montana, located in the northwest one quarter of Section 11, Township 28 North, Range 22 West, Principal Meridian, Montana, City of Kalispell, County of Flathead, Montana. - 7 Kalispell Zoning KALISPELL Spring Creek Park Phase 2 R-3+PUD Residential ID WiWithPutl Re,-sidjd ential R-3 With Putl Residential ��i Puo Neighborhood Business wtli Putl R-3 Residential Subject Pai - RA�IJiDjResitlential hpartrnentrARHi Pud R-3/PUD R—krtal With PDd ®w B-I Re�6odnod B.9— wl Puo w2 "idcmal"PUD w3 R> idem,l w3 Psldei,l wrPw - MI R.A—A APartlrmt wiYnD D� sor,: Iw-, M14 N I) 137-5275 550 125 liadrevd c ry his Feet Oty d Kall�4 6L% Basema p: AmW B,d,uski-0JJ1712tI23 Esri Community Maps, ArcGIS.com C: Existing Land Use and Zoning: The subject property is currently vacant, but has a history of agricultural use as farmland producing dryland wheat. The current zoning for the property is city RA- 1 (Residential Apartment), R-3 (Residential) and B-1 (Neighborhood Business), all with a PUD overlay approved in 2022. The RA-1 zone is "a residential district intended to provide for urban areas for multi- family use and compatible non- residential uses of medium land use intensity. It should be served with all public utilities and be in close proximity to municipal services, parks, or shopping districts. This zoning district would typically be found in areas designated as urban residential or high density residential on the Kalispell Growth Policy Future Land Use Map." The R-3 zone is a "district intended to provide lot areas for urban residential development. This district should have good thoroughfare access, and be in proximity to community and neighborhood facilities, i.e., schools, parks, shopping areas, etc. Development within this district must be served by all public utilities. This zoning district would typically be found in areas designated as suburban residential or urban residential on the Kalispell Growth Policy Future Land Use Map." The B-1 zone is "business district intended to provide certain commercial and professional office uses where such uses are compatible with the adjacent residential areas. This district would typically serve as a buffer between residential areas and other commercial districts. Development scale and pedestrian orientation are important elements of this district. This district is also intended to provide goods and services at a neighborhood level. The district is not intended for those businesses that require the outdoor display, sale and/or storage of merchandise, outdoor services or operations to accommodate large-scale commercial operations. This zoning district would typically be found in areas designated as neighborhood commercial or urban mixed use on the Kalispell Growth Policy Future Land Use Map." 2 D. Size: The subject property is approximately 49.6 acres. E: Adjacent Zoning: North: R-3/PUD; R-2/PUD; B-1/PUD East: R-3 South: County AG-80 West: County SAG-10 F: Adjacent Land Uses: North: Single-family residential East: Single-family residential South: Vacant West: Large tract single family residential; undeveloped G: General Land Use Character: The subject property is located between Three Mile Drive and Two Mile Drive to the east of West Springcreek Road. It is in a transitional area between urban residential development and single-family homes in existing county subdivisions and tract land. The general area has included significant residential growth over the past 20 years, as well as the addition of the bypass to the east that includes an interchange with Three Mile Drive. Kalispell Growth Policy RZALIMPELL Spring Creek Park Phase 2 ilCl:l / r ■111111 � � i1111111 1 ■ Suburban nIJ—d Feet H: Relation to the Growth Policy: The Kalispell Growth Policy Future Land Use Map designates the subject property as Neighborhood Commercial, High Density Residential, and Suburban Residential. The City of Kalispell Growth Policy Plan -It 2035, Chapter 4A on Housing, encourages a variety of residential development that provides housing for all sectors and income levels within the community. Chapter 4B on Business and Industry provides for neighborhood commercial areas designed to address the daily needs of the immediate neighborhood. City services including sewer, water and streets are in the vicinity and available to the subject property. The property also falls within the Kalispell West Neighborhood Plan, which was adopted in 2009. The plan anticipates this portion of the plan area 3 to be developed to accommodate growth in the short -to -medium term from the plan's adoption (within 15-20 years), and the area was also included within the annexation boundary established in the growth policy (the subject property was annexed in 2018). It was anticipated that development would utilize the existing and proposed road arterial system and allow for neighborhood shopping centers. L• Availability of Public Services and Extension of Services: Water and sewer services are available to the property. Water service is located within Three Mile Drive and extends through the property. The Westside Interceptor was extended through Phase 1 of the PUD providing access to sewer service. Sewer: City of Kalispell Water: City of Kalispell Refuse: City of Kalispell Electricity: Flathead Electric Cooperative Gas: NorthWestern Energy Telephone: CenturyTel Schools: School District 91 (West Valley)/Glacier High School Fire: City of Kalispell Police: City of Kalispell SUBJECT-''q PROPERTY I A4.. SFINFR Mgft-E MAIN = PURP. WATER,MAIN = BLUE 4 OVERALL PUD LAYOUT The Spring Creek Park PUD was approved approved by the Kalispell City Council on March 21, 2022 (Ordinance 1873), which provided for a total of 642 residential units (464 multi -family, 65 detached single-family dwellings, and 113 townhome/rowhouse dwellings), along with a commercial area. The Phase 1 preliminary plat was also approved at that time and consisted of the southeastern area of the overall development, containing single-family attached and detached homes. The northwestern portion with the multi -family dwellings, commercial area, and 18 attached single-family/townhome units, are Phases 2 and 3 of the development. 120A S t2 W A745 �6yl�if5 r 1J9 AD rMi 44�i imrc � ia.rrra { C 1 — IMACM IA.WTf r�•' �� . i7i5 F4Rli y �uwli SF - +' {. r� CDOWAMULL L6f1 i .. _Pq ;wfi ... OP[Ir r111Q r �MId Caracas La6 7rLlLAM ]l7 ALMS JFfr, ..$iIR mSUEK RUo WfiMC.FIdiJR ' 5 REVIEW AND FINDINGS OF FACT FOR THE MAJOR PRELINHNARY PLAT A. Effects on Health and Safety: Fire: The property would be considered to be at low risk of fire because any building constructed within the subdivision would be built in accordance with the International Fire Code and have access which meets city standards. The area to be built upon does not have steep slopes or woody fuels. Hydrants will be required to be placed in compliance with the requirements of the fire code and approved by the Fire Chief. Access: The access to Phases 2 and 3 will primarily be from Three Mile Drive and West Springcreek. As part of Phase 1, there would also be two extensions of existing streets in Spring Creek Estates (Battle Ridge Drive and Pine Draw Avenue) allowing for interconnectivity and access to the north in addition to a connection to Two Mile Drive. There is also a connection from Phase 2 into Spring Creek Estates via Westland Drive. Access and roads are discussed in more detail in part D below relative to effects on local services. Geology: The overall site is generally flat without any major topographical or geological features limiting development. A Geotech report was prepared in 2017 by Alpine Geotechnical covering the overall project area. The report found groundwater varying from about 5 feet deep in the southeastern corner to about 10.5 feet in other areas. The presence of groundwater at those depths "will likely impact installation of underground utilities," and consideration should be given to design and timing of underground utility improvements. Also, "given the documented groundwater levels, basements are not advised for the planned residential structures in the proposed development." Furthermore, the study found that "in general, the subgrade materials on the site are not considered to be high - quality fill materials with which to construct building pads," and that the report "recommends that individual investigations be performed on each lot and recommendations be developed based on the specific foundation loading and subgrade conditions at each building site." Additionally, the report contains recommendations which should be followed relative to geotechnical considerations, earthwork, and pavements. Appropriate measures should be provided for utility construction in high groundwater, which may include pipe ballast, trench plugs and structural buoyancy calculations for manholes. With those conditions noted in the Geotech report, basements should not be allowed within the development unless appropriately designed with waterproofing and other design elements required by the Kalispell Building Department. All building sites within the development should be subject to additional review if required by the Kalispell Building Department including, but not necessarily limited to, site specific geotechnical investigation. B. Effects on Wildlife and Wildlife Habitat: There is a creek and associated wetlands along the southwestern side of the property which would provide some aquatic and riparian habitat. There does not appear to be any significant wildlife impacts. The Resources and Analysis Section of the Kalispell Growth Policy includes information from the Montana Department of Fish, Wildlife and Parks relating to deer, elk and moose habitat. As with the majority of the Kalispell area outside of the core downtown, the maps show a whitetail deer density of 5 to 30 per square mile, but no significant elk or moose habitat. The creek and wetlands would be protected with a 100-foot required setback to any property lines from the wetlands, and a 50-foot setback from the creek that allows only limited uses. Prior to construction, the developer will need to submit an erosion/sediment control plan for review and approval which will help protect the habitat during construction. C. Effects on the Natural Environment: Surface and groundwater: The subdivision will be served by public water and sewer thereby minimizing any potential impacts to groundwater. Per the Geotech report, the static groundwater is generally from 5 to 10.5 feet below the surface. Potential impacts to the development are addressed in the section relating to geology above. Drainage: Roadways will be paved and curb/gutter will channel runoff to designed low points, where storm water will be collected and routed to storm water ponds. Any open storm water facilities should have an elevated aesthetic design to be reviewed and approved by the Parks and Public Works Departments. Storm water runoff from the site shall be managed and constructed per the City of Kalispell Standards for Design and Construction and storm water management program. Final design will be approved by the Kalispell Public Works Department prior to development. A condition of approval requires that a property owners' association be created for the maintenance of the common area which would include the common area drainage easements. As part of the storm easement areas, the association will be required to mow the area to reduce fire hazard and reduce spread of noxious weeds. In order to help ensure the continued maintenance of the storm water facilities, a note shall be placed on the final plat indicating a waiver of the right to protest creation of a stormwater maintenance district. This district shall only be activated in the event that the property owner(s) default on the maintenance of the approved stormwater facilities. The assessments levied within the maintenance district shall be determined by the Public Works Department with approvals by the Kalispell City Council. Lastly, the developer is required to submit to the Kalispell Public Works Department an erosion/sediment control plan for review and approval. These plans provide for managing storm water on the site and include stabilizing the construction site through an approved revegetation plan after site grading is completed. Wetland and Watercourse Setbacks: Under Section 28.3.06 of the subdivision regulations, a minimum 100-foot setback is required from wetlands to any proposed lot boundaries. Under Section 28.3.07, a minimum 50-foot setback from the intermittent stream which allows only limited uses. Based on a 2017 RESPEC Wetland Identification and Delineation Report, the required setbacks would be met. WGM .ouP - — ,&-,tAND.4FOR"A„or, LU 3 1 � J} U ❑ Y 2! W � Lr- CL CO Y G PU61.6 D. Effects on Local Services: Water: Water to the subdivision will be provided by the City of Kalispell. The developer will tie into an existing water main extension that runs through the subject property and extend the main throughout the development. The water system for the subdivision will be reviewed and approved by the Kalispell Public Works Department as part of the development of the subdivision under the Standards for Design and Construction. Per city standards, mains shall be extended within the adjacent frontages to the far property line, with the main in West Springcreek extended with Phase 2. The main may need to be upsized in accordance with the water facility plan, and the city would participate in the upsize cost. There is adequate capacity within the city's water system to accommodate this subdivision. Proportionate water rights shall be dedicated to the City of Kalispell per Section 28.3.08 of the subdivision regulations. Sewer: Sewer to the subdivision will be provided by the City of Kalispell. The developer will tie into the existing Westside Interceptor that goes through Phase 1 and extend sewer mains throughout the development. The sewer system for the subdivision will be reviewed and approved by the Kalispell Public Works Department as part of the development of the subdivision under the Standards for Design and Construction. As with the water mains, city standards would require that the sewer mains be extended to the far property line within the adjacent frontage. There is an existing main along the full 9 frontage of Three Mile Drive. There will be a main installed within West Springcreek with Phase 2, but due to togopgraphy, an extension to the south property line will likely not be required. There is adequate capacity within the city's sewer system to accommodate this subdivision. Access and Roads: The overall development has frontage on three exterior roads: Two Mile Drive, Three Mile Drive, and West Springcreek There is one access onto each road. Additionally, there are several connections with Spring Creek Estates to the east of Phase 2 and north of Phase 1 of the development. Those future connections were established as part of the subdivision approval for that subdivision to allow a connection to this property when it develops. Each of those adjoining roads will need to be upgraded to a level as specified in the Transportation Plan and the Standards for Design and Construction. Two Mile would be to a major collector standard and both Three Mile and West Springcreek would be to a minor arterial standard. Improvements may include, but would not necessarily be limited to, widening travel lanes, pedestrian paths, landscape boulevard, streetlights, and curb/gutter. Dedication of additional right-of-way will be required for the improvements, as well as for the roundabout at the intersection of Three Mile Drive and West Springcreek. Improvements for Two Mile are required to be installed with Phase 1 and improvements for both Three Mile and West Springcreek should be installed with Phase 2. Internal streets would include streets built to local/collector design standards pursuant to the Standards for Design and Construction including, but not limited to, sidewalks, landscape boulevard, streetlights, and curb/gutter. The collector would begin at Three Mile and extend through the northern part of Phase 1 and connect with Two Mile. The applicant shows a roundabout in Phase 2 at the internal intersection near the apartments and commercial areas. It appears that a compact roundabout could be warranted from a safety perspective. A turning movement distribution should be provided if a compact roundabout is to be built. If justified, adequate right-of-way should be dedicated to provide a single lane, compact roundabout with a minimum 80-foot diameter. Provisions of the design should accommodate road maintenance services and pedestrian safety. As a note, at the west end of Triple Creek Drive, there needs to be a hammerhead turnaround or other approved measures to accommodate snow plowing and emergency access. Alleys will be private with public utility easements. Under Sec 28.3.15, the townhomes cannot have access onto the street due to their width and the access shall only be from the alley. Also, the subdivision regulations (Sec 28.3.25) require that the final plat include a note stating that "The owners hereby waive the right to protest the creation of an SID for the purpose of financing improvements to area roads which specifically benefit this subdivision." WGM Group prepared a traffic impact study ("TIS") in December 2021. Based on comments from Public Works, WGM also completed an updated traffic analysis submitted in February 2022. An additional update was completed in November 2022 to 10 address new information related to the Three Mile Drive/West Springcreek intersection. The traffic impact study analyzed the full buildout of the proposed development. The traffic study was prepared using standard techniques to forecast traffic volumes and operations at the approaches and nearby intersections. Under the city Standards for Design and Construction, the development shall maintain or improve the existing level of service for the affected roadways rather than simply maintaining an acceptable level of service. Based on the TIS and city review of the TIS, there are several areas which require mitigation. (a) Intersection of Three Mile Drive and West Springcreek There are projected to be some minor drops in service with a full build -out of the development that would at this time appear to justify the construction of a roundabout at the intersection. The intersection involves a state highway, and the Montana Department of Transportation ("MDT") would be involved with the design and timing of improvements to the intersection. Right-of-way at the northwest corner of Phase 3 has been allocated as part of the plat to accommodate the roundabout. (b) Intersection of the internal collector road and Three Mile Drive: When the collector road is constructed, it should include a northbound right turn lane. (c) Intersection of Camp Crook Avenue and Three Mile Drive: Northbound left-hand turns should be restricted. As this road connects with Phase 1, this improvement was required to be installed with the first phase unless otherwise determined by Public Works. Since Phase 2 also connects with that intersection, the improvement is also necessary prior to final plat of Phase 2. (d) Intersection of Heaven's Peak and Three Mile Drive: The traffic analysis indicates that there is a drop in level of service at this intersection. Mitigation would likely involve installing a traffic signal. However, as a state highway, MDT regulations dictate the timing and design of the improvements and require a warrant study after the development is constructed showing actual traffic volumes. The developer will need to provide a 14-hour intersection turning movement study and install a signalized intersection at Three Mile Drive and Heaven's Peak Drive when warrants are met per Manual on Uniform Traffic Control Devices and MDT. (e) Intersection of Stillwater Road and Three Mile Drive: This intersection is already failing and this project is going to negatively impact that intersection. As with the intersection of Heaven's Peak and Three Mile, a 14-hour intersection turning movement study should be conducted to determine if a signal is warranted. When warranted, staff recommends a regional SID to construct the signal. The traffic analysis took into account Two Mile Drive, including recent developments along the road. The analysis showed that there was not a decrease in service and no capacity improvements are required to accommodate this development. 11 Schools: The property is within the boundaries of School District 91 (West Valley) and Glacier High School. On average, it would be anticipated that there would be about 241 students (K-12) from Phases 2 and 3 of the neighborhood at full build -out. Section 76-3- 608(l) of the Montana Code Annotated states that the governing body may not deny approval of a proposed subdivision based solely on the subdivision's impacts on educational services. Police: Police services will be provided by the Kalispell Police Department. The department can adequately provide service to this subdivision. Fire Protection: Fire protection services will be provided by the Kalispell Fire Department. The department can adequately provide service to this development. Additionally, the road network to the subdivision provides adequate access for fire protection. As part of subdivision review and site review for the multi -family/ neighborhood commercial area, fire protection, including fire flow and hydrant location, will be reviewed. Fire station 62 is located approximately 2.2 miles away providing good response time. Parks and Recreation: Subdivision regulations require a minimum of 0.03 acres of parkland per dwelling unit for single-family lots, or 0.54 acres for the 18 single- family/townhome lots (or the equivalent value in land with improvements). The parks may include amenities that will be determined during the course of the detailed subdivision design review in conjunction with the Parks Department. With multi -family developments, the zoning ordinance requires recreational amenities equal to 500 square feet of land or the equivalent value in amenities that will need to be provided in conjunction with the development of any multi -family project. The proposal includes covenants and a management plan providing for maintenance of the shared facilities. It is imperative that these areas be well maintained for the visual aspects of the project and the functionality of the parks, open space, and storm drainage areas. Therefore, staff recommends that a note shall be placed on the final plat indicating a waiver of the right to protest creation of a park maintenance district. This district shall only be activated in the event that the property owners' association defaults on their park and open space amenity conditions. The taxes levied within the maintenance district shall be determined by the Parks and Recreation Department with approvals by the Kalispell City Council. Solid Waste: Solid waste collection can be provided throughout the subdivision by the City of Kalispell. Specific designs of the garbage enclosures and collection areas for the multi-family/commercial area will be reviewed in conjunction with the building permit and site review process for the buildings. There is sufficient capacity within the landfill to accommodate this additional solid waste generated from this subdivision. Medical Services: Ambulance service is available from the fire department and ALERT helicopter service. Kalispell Regional Medical Center is approximately 2.0 miles from the site. 12 E. Effects on Agriculture and agricultural water user facilities: The site has been traditionally used for agricultural uses. According to the Kalispell Growth Policy Resources and Analysis Section, "Important Farmlands" map, the property includes some areas designated as prime farmland if irrigated. Current policies in the Kalispell Growth Policy Plan -It 2035, Chapter 5, Land Use: Natural Environment, state the following: Policy Encourage urban growth only on agriculture lands entirely within the city's annexation policy boundary. The subject property is entirely within the annexation policy boundary and was previously annexed as part of the prior proposed development. By allowing higher density development within the city's growth policy area, it can reasonably be expected that more farmland could be conserved because the availability of residential and commercial lots within the Kalispell Growth Policy boundary, limiting sprawl/leapfrog development. F. Relation to the Kalispell Growth Policy: The Kalispell Growth Policy Future Land Use Map designates the subject property as Neighborhood Commercial, High Density Residential, and Suburban Residential. The City of Kalispell Growth Policy Plan -It 2035, Chapter 4A on Housing, encourages a variety of residential development that provides housing for all sectors and income levels within the community. Chapter 4B on Business and Industry provides for neighborhood commercial areas designed to address the daily needs of the immediate neighborhood. City services including sewer, water and streets are in the vicinity and available to the subject property. The property also falls within the Kalispell West Neighborhood Plan, which was adopted in 2009. The plan anticipates this portion of the plan area to be developed to accommodate growth in the short -to -medium term from the plan's adoption (within 15- 20 years), and the area was also included within the annexation boundary established in the growth policy (the subject property was annexed in 2018). It was anticipated that development would utilize the existing and proposed road arterial system and allow for neighborhood shopping centers. G. Compliance with Zoning: The request is in compliance with the B-1, RA-1, and R-3 zoning regulations with the PUD overlay applicable to the development. 13 H. Compliance with the Kalispell Subdivision Regulations: This request complies with provisions of the Kalispell Subdivision Regulations and PUD overlay applicable to the development. One of the PUD subdivision deviations applicable to these phases relates to block length. Generally, block lengths should not exceed 600 feet. The PUD allowed the development to exceed the block length provided that it is in substantial compliance with the PUD plan as well as other PUD conditions. This plat meets those requirements and would be in compliance. RECOlV NMNDATION Staff recommends that the Kalispell City Planning Board and Zoning Commission adopt staff report #KPP-23-01 as findings of fact and recommend to the Kalispell City Council that the preliminary plat for Spring Creek Park Phases 2 and 3 be approved subject to the conditions listed below: CONDITIONS OF APPROVAL 1. The development of the site shall be in substantial compliance with the application submitted, the site plan, materials and other specifications as well as any additional conditions associated with the preliminary plat as approved by the city council. 2. The preliminary plat approval shall be valid for a period of three years from the date of approval. 3. The storm water ponds shall be designed in a way that they become a visual interest to the development. Chain link fencing surrounding the retention pond as the dominant fixture shall not be allowed without mitigation. The developer shall work closely with the Parks Department and Public Works to develop a design that is both visually appealing and meets the required safety guidelines. It is intended that when the project is developed the ponds will act as features, particularly along the roadways, rather than a private maintenance utility facility. 4. The developer shall submit to the Kalispell Public Works Department for review and approval a storm water report and an engineered drainage plan that meets the requirements of the current city standards for design and construction. Any open storm water facilities should have an elevated aesthetic design to be reviewed and approved by the city Architectural Review Committee. Prior to final plat, a certification shall be submitted to the public works department stating that the drainage plan for the subdivision has been installed as designed and approved. 5. The developer shall submit to the Kalispell Public Works Department prior to construction an erosion/sediment control plan for review and approval and a copy of all documents submitted to Montana Department of Environmental Quality for the General Permit for Storm Water Discharge Associated with Construction Activities. 14 6. The developer shall submit water and sanitary sewer plans, applicable specifications, and design reports to the Kalispell Public Works Department and the Montana Department of Environmental Quality for concurrent review, with approval of both required prior to construction. 7. New infrastructure required to serve the subdivision shall be designed and constructed in accordance with the City of Kalispell's Standards for Design and Construction. All design work shall be reviewed and approved in writing by the Kalispell Public Works Department prior to construction. This infrastructure shall include but not be limited to streets, street lighting, street signage, curb, gutter, boulevard and sidewalks. 8. Water and sewer main extensions shall be designed and constructed in accordance with the City of Kalispell's Standards for Design and Construction and in compliance with the city's facilities update and extensions of services plans. The water and sewer main extension plans shall be reviewed and approved by the Kalispell Public Works Department. Prior to final plat, a certification shall be submitted to the Public Works Department stating that the water and sewer mains have been built and tested as designed and approved. 9. Per city standards, the water mains shall be extended within the adjacent frontages to the far property line. The main in West Springcreek shall be extended with Phase 2. The main may need to be upsized, and the city would participate in the upsize cost. 10. Any water rights associated with the property shall be transferred to the City of Kalispell. The water rights shall be allocated proportionally for each phase of the development prior to final plat. II. The full length of the sewer main within West Springcreek shall be installed in conjunction with Phase 2. Due to topography, a full extension to the south property line will likely not be required, but will be subject to review and approval by the Public Works Department. 12. The developer shall submit the street designs to the Kalispell Public Works Department for review and approval prior to construction. Street designs shall meet the city standards for design and construction. 13. Three Mile and West Springcreek shall be upgraded for the length of the frontage to a minor arterial standard. Improvements may include, but would not necessarily be limited to, widening travel lanes, bike/pedestrian paths, landscape boulevard, streetlights, and curb/gutter. Dedication of additional right-of-way will be required for improvements for the adjoining roadways, as well as for the roundabout at the intersection of Three Mile Drive and West Springcreek Improvements for both Three Mile and West Springcreek shall be installed with Phase 2. 14. Internal streets would include streets built to local/collector design standards pursuant to 15 the Standards for Design and Construction including, but not limited to, sidewalks, landscape boulevard, streetlights, and curb/gutter. At the west end of Triple Creek Drive, there shall be a hammerhead turnaround or other approved alternated design to accommodate snow plowing and emergency access. 15. A turning movement distribution shall be provided if a compact roundabout internal to Phase 2 is to be built. If justified, adequate right-of-way shall be dedicated to provide a single lane, compact roundabout with a minimum 80-foot diameter. 16. Alleys included within the plat shall be maintained as private alleys with public utility easements. Any lot located on the collector with an alley shall access only from the alley. 17. Pursuant to Sec 28.3.25 of the subdivision regulations, the final plat shall include a note stating that "The owners hereby waive the right to protest the creation of an SID for the purpose of financing improvements to area roads which specifically benefit this subdivision." 18. Prior to final plat, all mitigation recommended as part of the approved traffic impact study relative to the given phase shall be completed. All improvements shall be reviewed and approved by the Public Works Department. Per the city Standards for Design and Construction, the development shall maintain or improve the existing level of service for the affected roadways rather than simply maintaining an acceptable level of service. Improvements necessary to maintain the existing level of service will be required. 19. Based on the Traffic Impact Study ("TIS") and city review of the TIS, there are several areas which require mitigation. (a) Intersection of Three Mile Drive and West Springcreek: A roundabout shall be installed with Phase 2 at the intersection. The roundabout will require dedication of additional right-of-way. The specific design of the roundabout is subject to MDT review and approval, as well as review and approval by the Kalispell Public Works Department. (b) Intersection of the internal collector road and Three Mile Drive: The intersection shall include a northbound right turn lane. (c) Intersection of Camp Crook Avenue and Three Mile Drive: Northbound left-hand turns shall be restricted. This improvement, which is also a condition of Phase 1, shall be installed prior to the final plat of Phase 2 (d) Intersection of Heaven's Peak and Three Mile Drive: The developer shall provide a 14-hour intersection turning movement study and install a signalized intersection at Three Mile Drive and Heaven's Peak Drive when warrants are met per Manual on Uniform Traffic Control Devices and MDT. (e) Intersection of Stillwater Road and Three Mile Drive: The developer shall provide a 14-hour intersection turning movement study to determine if a signal is warranted. When warranted, staff recommends a regional SID to construct the signal. 16 20. The recommendations in the Geotech report shall be followed. 21. Basements are not allowed within the development unless appropriately designed with waterproofing and other design elements required by the Kalispell Building Department. All building sites within the development shall be subject to additional review if required by the Kalispell Building Department including, but not necessarily limited to, site specific geotechnical investigation. 22. Under Section 28.3.06 of the subdivision regulations, the development shall maintain a minimum 100-foot setback from wetlands to any proposed lot boundaries. Under Section 28.3.07, the development shall limit uses within the 50-foot setback from the stream. 23. Prior to final plat, a letter from the Kalispell Public Works Department shall be submitted stating that all new infrastructure has been accepted by the City of Kalispell, any private infrastructure has been constructed per city standards, and a proper bond has been accepted for unfinished work. 24. All existing and proposed easements shall be indicated on the face of the final plat. Utility easements for city water and sewer shall be provided to allow for the logical extension of utilities from this subdivision to adjoining properties. A letter from the Kalispell Public Works Department shall be obtained stating that the required easements are being shown on the final plat. 25. The following statement shall appear on the final plat: "The undersigned hereby grants unto each and every person, firm or corporation, whether public or private, providing or offering to provide telephone, telegraph, electric power, gas, cable television, water or sewer service to the public, the right to the joint use of an easement for the construction, maintenance, repair, and removal of their lines and other facilities, in, over, under, and across each area designated on this plat as "Utility Easement" to have and to hold forever." Developer's Signature 26. Prior to filing the final plat, a letter from the US Postal Service shall be included stating the Service has reviewed and approved of the design and location of the mail delivery site. The mail delivery site shall be installed or bonded for prior to final plat. In addition, the mail delivery site and improvements shall also be included in the preliminary and final engineering plans to be reviewed by the Public Works Department. The mail delivery site shall not impact a sidewalk or proposed boulevard area. 27. A homeowner's association (HOA) shall be formed and established to provide for the maintenance of the common areas, including, but not necessarily limited to, roads, parks and open space. Maintenance of any private roads and alleys shall include both short term and long-term maintenance including, but not necessarily limited to, snow plowing, landscaping, sidewalks, street repairs, overlays, and rebuilds of the street. 17 28. A letter from the Kalispell Fire Department approving the access, placement of the fire hydrants and fire flows within the subdivision shall be submitted prior to final plat. 29. A letter shall be obtained from the Parks and Recreation Director approving a landscape plan for the placement of trees and landscaping materials within the landscape boulevards of the streets serving the subdivision, common area, and adjoining rights -of -way. The approved landscape plan shall be implemented or a cash -in -lieu payment for installation of the street trees and groundcover be provided to the Kalispell Parks and Recreation Department. 30. A park plan shall be created and approved by the Parks and Recreation Director prior to final plat of Phase 2. 31. A note shall be placed on the final plat indicating a waiver of the right to protest creation of a park maintenance district. This district shall only be activated in the event that the property owners' association defaults on their park and open space amenity conditions. The assessments levied within the maintenance district shall be determined by the Parks and Recreation Department with approvals by the Kalispell City Council. 32. A note shall be placed on the final plat indicating a waiver of the right to protest creation of a stormwater maintenance district. This district shall only be activated in the event that the property owner(s) default on the maintenance of the approved stormwater facilities. The assessments levied within the maintenance district shall be determined by the Public Works Department with approvals by the Kalispell City Council. 33. A minimum of two-thirds of the necessary infrastructure for the subdivision shall be completed prior to final plat submittal. 34. All utilities shall be installed underground and in locations that are approved by the Kalispell Public Works Department in accordance with the Kalispell Standards for Design and Construction. 35. All areas disturbed during development shall be re -vegetated with a weed -free mix immediately after development. 18 CITY OF Kalispell Zoning KALISPELL Spring Creek Park Phase 2 R-3/PUD Residential With Pud iv �B-1/PUD����.;....Neighborhood Busiiiess:WithPud ® Subject Parcel B-1 Neighborhood Business w/ PUD R-2 Residential w/ PUD R-3 Residential R-3 Residential w/PUD RA-1 Residential Apartment w/PUD Data Sources: Montana Cadastral, Flathead County GIs. City of Kalispell GIs, Austin Bachurski - 01/17/2023 bj R-2/PUD Residential With Pud R-3/PUD Residential With Pud R-3 Residential 1- R-3 Residential 0 137.5275 550 825 Feet Basemap: Esri Community Maps, ArcGIS.com CITY OF Kalispell Growth Policy KALISPELL Spring Creek Park Phase 2 ® Subject Parcel Neighborhhod Commercial High Density Residential Suburban Residential Suburban Residential Object Data Sources: ce Montana Cadastral, N 0 137.5275 550 825 Flathead County GIs. Feet City of Kalispell GIs, Basemap: Austin Bachurski - 01/17/2023 Esri Community Maps, ArcGIS.Com From: iudyshoe(&a.com To: Kirstin Robinson Subject: EXTERNAL Spring Ck Phase 2 Date: Tuesday, February 14, 2023 2:36:52 PM Dear Planning Board Members, I have continued concerns for the development of the land on the South side of Three Mile Drive East of Spring Ck Road. Since the last proposed development on this land, the state, county nor city have done anything to improve the infrastructure of the roads, especially to Three Mile, to handle the additional traffic a subdivision of this size would put on a two lane road. We have heard talk for years about the development of an intersection to be built on Three Mile and Spring Creek Rd to assist in a better flow of traffic. That has not been started nor surveyed as best I can see. The additional traffic for construction will all be on Three Mile. Then after construction vehicles clear out, we will have additional residential vehicles. The way the letter states, the subdivision will have 18 single family homes, equally a minimum of 36 cars. The multi -family lots will contain 464 units each for a minimum of 1392 cars IF only one car is for each unit. The lifestyle and rents for the area would most likely mean a minimum of 2 cars per unit. This brings to a total of 4200 cars per day. That doesn't include the additional traffic from the two developments North of Mountain Vista Estates on Farm to Market Road or along West Valley Road. Let's widen Three Mile to assist with traffic and bicycle/pedestrian users, fix the corner at Farm to Market and Three Mile Dr, and pave Four Mile drive for residents in these new subdivisions to have a choice than just driving Three Mile to access anything East of this area. Respectfully, Judy Schumacher 154 Jackson Peak Dr. From: Wendy Wilson To: Kirstin Robinson; Kalispell Meetings Public Comment Subject: EXTERNAL Development on Three Mile Date: Tuesday, February 14, 2023 11:45:45 AM Planning board, I want to express my great concern about approving any more housing developments that will significantly add traffic to Three Mile Drive. It is not designed for the amount of traffic that is using it already. I live on Blue Crest Drive and have to tum left onto Three Mile to get to work. It is scary! I have to hope for a break in the constant string of cars heading to Kalispell. Now that there is increased construction there is mo traffic heading out of town as well. So finding a way out becomes very difficult!! When I finally get an opening I have to gun it and hope that I don't slide off the road and down a steep embankment on the other side. So before approving more development something needs to be done to address the impact on Three Mile for the safety of all the residents that have to use it. Can you address what that plan will be? Thanks, Wendy Wilson Sent from my iPhone