11-21-89 S&W Comm MinutesNovember Zl, IVbV SL'WLK AND WATLK UUMMIYEL'L MINU1Lb 4:UU 1). Ill.
v
Attendance: Chairman Nystul.
Others Present: S/W Supt. Van Dyke, Asst. S/W Supt. Allen, Dennis Carver of Carver
Engineering.
WWTP - Design - Report The design flows for the treatment plant have been upgraded
to 11.0 MGD during peak times due to storm drain and roof drain infiltration into
the sanitary system. This increased flow capacity will reflect additional costs.
The bid date is scheduled for April 1, 1990 and the Notice to Proceed is scheduled
for around June 1, 1990. Rate increases are estimated between 12% and 181.
Discussion took place regarding Southwest Kalispell. Mr. Carver recommended the
city close out the project and withhold a $5,000.00 CD to assure that street surface
work which cannot be completed due to winter onset will be completed in the spring.
Adjourned: Approximately 5:00 p.m.