Addendum 3 Police Search Building - RFI Responses with drawingPage 1 of 1 8/16/2021 5485 E. Olive Ave. ▪ Fresno, CA 93727 ▪ Phone (559) 243-4200 ▪ Fax (559) 222-2380 BID RFI NO. 1 To: David P From: Gurdeep Jhutti Company: Jackola Engineering & Architecture Company: BMY Construction Group, Inc. Email: dpugh@jackola.com Page(s): (1) Including Cover Page Date: 8/16/21 Reference: City of Kalispell Police Search Building BMY Construction Group, Inc. is requesting the following clarifications, specifications and/or request for information: 1. Can you please provide duration of this project? Thank you, BMY Construction Group, Inc. Gurdeep Jhutti Senior Estimator The preliminary schedule below is contingent on City Council acceptance of bids. Start date: no later than October 1, 2021 Substantial completion: March 31, 2022 Finish date (Liquidated damaged begin to apply) : May 1, 2022 Page 1 of 1 8/16/2021 BID RFI NO. 2 To: David Pugh From: Gurdeep Jhutti Company: Jackola Engineering & Architecture Company: BMY Construction Group, Inc. Email: dpugh@jackola.com Page(s): (1) Including Cover Page Date: 8/16/21 Reference: City of Kalispell Police Search Building BMY Construction Group, Inc. is requesting the following clarifications, specifications and/or request for information: 1. On sheet C1.10 note 2 states, 5” concrete slab refer to structural drawings; on Sheet S1.00 note 7 states 4” slab, coordinate location with civil. Can you specify slab section to be used at this concrete apron? Thank you, BMY Construction Group, Inc. Gurdeep Jhutti Senior Estimator 2829 Great Northern Loop, Suite B105 Missoula, MT 59808 MT. Reg No. 261547 406-550-2005 Concrete slab at entry and rear apron to be 5". Keynote on drawings will be revised. Page 1 of 1 8/16/2021 BID RFI NO. 3 To: David Pugh From: Gurdeep Jhutti Company: Jackola Engineering & Architecture Company: BMY Construction Group, Inc. Email: dpugh@jackola.com Page(s): (1) Including Cover Page Date: 8/16/21 Reference: City of Kalispell Police Search Building BMY Construction Group, Inc. is requesting the following clarifications, specifications and/or request for information: 1. On Sheet S1.00 at gridline C it refers to detail 2 on S4.00. This detail shows an apron like condition. Is there a concrete apron at this line? If so, please provide dimension and slab section. Thank you, BMY Construction Group, Inc. Gurdeep Jhutti Senior Estimator 2829 Great Northern Loop, Suite B105 Missoula, MT 59808 MT. Reg No. 261547 406-550-2005 There is no concrete apron at gridline C. There is one at Gridline A. Callout will to be relocated in pending addendum. Page 1 of 1 8/18/2021 BID RFI NO. 4 To: David Pugh From: Gurdeep Jhutti Company: Jackola Engineering & Architecture Company: BMY Construction Group, Inc. Email: dpugh@jackola.com Page(s): (1) Including Cover Page Date: 8/18/21 Reference: City of Kalispell Police Search Building BMY Construction Group, Inc. is requesting the following clarifications, specifications and/or request for information: 1. Can you confirm if section 31 2113 Radon Mitigation is applicable to this project? 2. Can you confirm if sections 328423 underground sprinkler and 32 9219 seeding is applicable to this project? 3. On detail 1 on sheet S4.00 Foundation details, it shows 4” Perf pipe at perimeter foundation wall. Is this drain applicable to this project? 4. Can you provide a copy of the soils report for this project? Thank you, BMY Construction Group, Inc. Gurdeep Jhutti Senior Estimator 2829 Great Northern Loop, Suite B105 Missoula, MT 59808 MT. Reg No. 261547 406-550-2005 1. Omit spec section 2. Omit spec section 3. Foundation drain is not required. Drawing will be revised in pending addendum. 4. No site specific geotech was performed. Basis of design is listed in the drawings. Page 1 of 1 8/18/2021 BID RFI NO. 5 To: David Pugh From: Gurdeep Jhutti Company: Jackola Engineering & Architecture Company: BMY Construction Group, Inc. Email: dpugh@jackola.com Page(s): (1) Including Cover Page Date: 8/18/21 Reference: City of Kalispell Police Search Building BMY Construction Group, Inc. is requesting the following clarifications, specifications and/or request for information: 1. Could you please provide the location for temporary power and water hook ups? 2. Can you provide the lay down area for the contractor’s use? Thank you, BMY Construction Group, Inc. Gurdeep Jhutti Senior Estimator 2829 Great Northern Loop, Suite B105 Missoula, MT 59808 MT. Reg No. 261547 406-550-2005 1. The building adjacent to the south has power and ¾ water line. The concrete pad area has a 2 inch water line. City will provide access to the necessary temporary utilities. 2. Shop staff will work with identifying a lay down area, they also have an area for trailers/lifts etc. to the south by the sand shed. Page 1 of 1 8/23/2021 BID RFI NO. 6 To: David Pugh From: Gurdeep Jhutti Company: Jackola Engineering & Architecture Company: BMY Construction Group, Inc. Email: dpugh@jackola.com Page(s): (1) Including Cover Page Date: 8/23/21 Reference: City of Kalispell Police Search Building BMY Construction Group, Inc. is requesting the following clarifications, specifications and/or request for information: 1. Section 08 3613, Sectional Doors – Can you confirm Midland Garage door as acceptable manufacture? Please see attached Midland specifications. Thank you, BMY Construction Group, Inc. Gurdeep Jhutti Senior Estimator 2829 Great Northern Loop, Suite B105 Missoula, MT 59808 MT. Reg No. 261547 406-550-2005 Yes, Midland Garage is an acceptable manufacturer. FOUNDATION LEGEND FOOTING THICKENED SLAB SAWCUT CONTROL JOINT HOLD-DOWN FROM ABOVE, SEE SHEAR PLAN A A 1 1 C C 4 4 SLOPE PER CIVIL 1 2 TOF: (FF) -4'-0" 4 5 5 5 5 5 7 T.O. PIER: (FF) 0'-6" TYP 8 8 8 8 8 3 4" 4" 8' - 8 " 8' - 6 " 10 ' - 0 " 9' - 8 " 5' - 8" B B 2 2 3 3 1' - 6 " 1' - 0 " 9' - 6 " 9' - 0 " 21 ' - 6 " 40 ' - 0 " 12' - 4"27' - 8" 40' - 0" 3 T.O. FTG: (-) 4'-0" 9 1' - 4" 11' - 3" C1 C1 C1 C1 C1 1 S4.00 1' - 4 " TOW: (FF) 0'-0" TOW: (FF) -0'-5" 4 S4.00 2 S4.00 3 S4.00 TYP 8 S4.00 7' - 0" 9 4' - 0 " 6' - 6" 6 S4.00 1' - 4" 3" 5' - 0 " 10 8 S4.00 TYP 10 10 10 C2 C2 8" TYP 7 C 2 S4.00 TYP C DATE: JACKOLA ENGR. & ARCH., P.C. WITHOUT THE WRITTEN CONSENT OF MAY NOT BE USED OR REPRODUCED IS PROPRIETARY. THIS DOCUMENT THE INFORMATION CONTAINED HEREIN REVISIONS: FOR PERMIT KALISPELL 406-755-3208 # BOZEMAN 406-586-0707 VANCOUVER 360-852-8746 DRAW N:CHECKED: info@jackola.com jackola.com S1.00 4/1/2021 CI T Y O F K A L I S P E L L PO L I C E S E A R C H B U I L D I N G 1S T A V E W . KA L I S P E L L M T 5 9 9 0 1 FOUNDATION PLAN JTJHH PR O J E C T # : 2 0 0 2 0 4 FOUNDATION KEYNOTES 1 5" SLAB, #4 BAR @ 24" O.C. E.W. 2 POUR THRU @ OVERHEAD DOOR, TYP 3 POUR THRU @ MAN DOOR 4 8" CONCRETE WALL W/ 16"W X 8" THICK FTG, TYP 5 FLOOR DRAIN, SLOPE SLAB TO DRAIN, COORDINATE LOCATION WITH MECH 7 5" SLAB, COORDINATE LOCATION WITH CIVIL 8 12" SONOTUBE W/ 24" BIGFOOT, 4'-0" DEPTH, TYP 9 10" THICK, THICKENED SLAB 10 BOLLARD. SEE CIVIL FOR LOCATION COLUMN SCHEDULE TAG SIZE MATERIAL COLUMN BASE COLUMN CAP C1 6X6 TIMBER ABU66Z CC66, CAP @ END COLUMNS ECC66 C2 6X6 TIMBER 3/8" = 1'-0"1 FOUNDATION M O NTAN A PR O F E S S ION A L E N G INEE R LICE N S E D ERIC D. GARBERG No. 14108 PEC C ADDENDUM 8/27/2021 WD STUDS 8" (4)#5 HORIZ. EQ. SPACING 5/8" X 12"A.B. @ 32" O.C. MAX FLASHING PER ARCH #5 BAR 2" FROM TOP, TYPICAL 5" SLAB IJ SEE 4/S4.00 FTG BACKFILL PER GEOTECHNICAL RECOMMENDATION W SEE 4/S4.00 FOR TYP. SLAB PREP DAMPROOFING #4 LATERALS @ 16" O.C. REBAR CONTINUOUS IN FOOTING W<16" - (2) #4 16"≤W<24" - (3) #4 24"≤W<36" - (4) #4 PERIMETER INSULATION SEE ARCH. FOR LOCATION & SIZE. #4 @16" O.C. VERTS ALT. BEND DIRECTION INTO FOUNDATION 3" M I N SE E P L A N SE E P L A N C FND WALL & FOOTING PER PLAN/ DETAILS DOOR OPENING PER PLAN WALL BEYOND SLOPE SLAB @ DOOR FOR DRAINAGE SLOPE PER SITE SEE SOILS & GEOTECHNICAL NOTES FOR EXTERIOR FLATWORK PREP. 5/8" POLYISO, LOCATE UNDER DOOR THRESHOLD PER ARCH (2) #4 @ EDGE ASPHALT, SIDEWALK OR GRADE PER SITE SEE SOILS & GEOTECHNICAL NOTES FOR FILL REQUIREMENTS - 18 " 6" #4 DOWEL @ 32" O.C. #3 @ 18" O.C. EW 2' 2' SEALANT NPI OR EQUAL SEE PIJ A. FOR DOWEL DETAIL BACKER ROD EJ MATERIAL EJ @ SIDEWALK SLOPE AWAY FROM BUILDING APRON @ BUILDING POUR THRU C 4', 1/2" SMOOTH DOWELS @ 18" OC @ COLD JT LOCATIONS. GREASE END IN SECOND POUR T/ 4 PLASTIC OR PREFORMED HARDBOARD STRIP; IF SAWCUT ONLY, FILL WITH SEALER FREE END OF SMOOTH DOWELS TO BE COATED WITH NON-BONDING AGENT CONSTRUCTION COLD JOINT, FILL WITH SEALER CONTROL JOINT CONSTRUCTION JOINT REBAR PER PLAN TYPICAL SLAB 10 MIL VB TYP. SLAB SEE PLAN FOR THICKNESS & REBAR LOCATE REBAR IN CENTER OF SLAB SEE 'TYPICAL SLAB' FOR SUBGRADE 3/8" EXPANSION JOINT MATERIAL WR MEADOW FIBRE EXPANSION JOINT OR APPROVED EQUAL 3/8" WIDE X1/2" DEEP GROOVE W/SEALANT WR MEADOWS SAFE SEAL 3405 OR APPROVED EQUAL VB SEAL TO WALL SL A B SEE 'TYPICAL SLAB' FOR SUBGRADE SEE 'TYPICAL SLAB' FOR SUBGRADE 6" OPEN GRADED ROCK COMPACTED STRUCTURAL FILL TO UNDISTURBED NATIVE SEE 'TYPICAL SLAB' FOR SUBGRADE 3/8" EXPANSION JOINT MATERIAL WR MEADOW FIBRE EXPANSION JOINT OR APPROVED EQUAL 3/8" WIDE X1/2" DEEP GROOVE W/SEALANT WR MEADOWS SAFE SEAL 3405 OR APPROVED EQUAL VB SEAL TO WALL PERIMETER ISOLATION JOINT PIJ A. PERIMETER ISOLATION JOINT PIJ B. 2" LEVELING COURSE JOINT SPACING LIMITED TO MAXIMUM OF +/- 15 FEET 4', 1/2" SMOOTH DOWELS @ 18" OC ALTERNATE USE DIAMOND PLATE DOWEL BY PNA OR APPROVED EQUAL FRAMING FLUSH W/ INSIDE OF CONCRETE FRAMING FLUSH W/ OUTSIDE OF CONCRETE GREASE END 9/16" Ø HOLE 2" M I N 4" (3), #3 VERTICAL 12" SONO-TUBE #3 STIRRUPS @12" 6X6 TIMBER COLUMN SIMPSON ABU66 POST BASE SLAB IJ PER PLAN 4' - 0 " (3) #3 STIRRUPS @2" 1' - 0 1 / 4 " BF 24 t+ 1 1 / 2 " PR O J E C T I O N TREATED PLATE ANCHOR BOLT PER SCHEDULE. POSITION @ C/L OF PLATE. t= T H I C K N E S S PLATE WASHERS REQUIRED AT SHEAR WALLS, SEE SIZE TABLE SPLICE OR CORNER, WHERE OCCURS 12" MAX 6" MIN - 12" MAX 6" MIN - SPACING AS SCHEDULED 8" M I N . 2 3/4" 6" COMPACTED STRUCTURAL FILL TO NATIVE 9/16"Ø HOLE 4" DEEP 3/8" EXPANSION JOINT MATERIAL PER 3/ S1.1 1/2" SMOOTH DOWEL 24" LONG, MATCH BOTTOM BAR LAYOUT, GREASE END IN WALL THICKENED SLAB BOTTOM BARS THICKENED SLAB @ FOUNDATION WALLS PROVIDE #4 DROP BAR LATERALS @ 32" O.C. & TIE OFF TO #4 SLAB STEEL AS SHOWN. #4 BAR HORIZONTAL, (1) BAR FOR EACH 12" OF WIDTH SLAB THICKNESS PER PLAN RUN SLAB BARS THRU #5 BAR 5/8" SIMPSON TITEN HD BOLTS @ 32" O.C. 4" MIN. EMBED, MAX 8" FROM END AT PLATES 2X4 OR 2X6 FRAMED WALL PER PLAN PER PLAN PE R P L A N P.T. PLATE 1 1 SEE NOTES FOR SUBSLAB RECOMMENDATIONS COUNTERSUNK 1/2"X3" TITEN HD L-3X3X1/4"-6" ANGLE PE R P L A N PER PLAN STAIR STRINGER BAR SIZE HOOKED REINFORCEMENT TENSION DEVELOPMENT LENGTH SCHEDULE TENSION DEVELOPMENT LENGTH, (ldh), INCHES f'c = 3 KSI #3 #4 #5 #6 9" #7 #8 #9 #10 #11 4db 2 1/2" MIN. ldh db 12 d b SEE NOTES BELOW FOR BAR YIELD STRENGTH FACTOR f'c = 4 KSI 11" 14" 17" 20" 22" 25" 28" 31" 8" 10" 12" 15" 17" 19" 22" 24" 27" BENDING RADIUS 3db FOR #3 THROUGH #8 AND 4db FOR #9 THROUGH #11 MEASURED TO THE INTERIOR OF THE BARFACE OF SUPPORT, HORIZONTAL OR VERTICAL JOINT OR POTENTIAL CRACK LINE db BENDING DIAMETER 6db FOR #3 THROUGH #8 AND 8db FOR #9 THROUGH #11 MEASURED TO THE INTERIOR OF THE BAR ldh NOTES: 1. TABULATED DEVELOPMENT LENGTHS ARE BASED ON REINFORCING YIELD STRENGTH FY = 60 KSI AND NORMAL WEIGHT CONCRETE. 2. ALL TABULATED VALUES ARE MINIMUM LENGTHS. IN CASE OF CONFLICT WITH THE PLANS, SECTIONS OR DETAILS, USE THE LONGER LENGTH. 3. ADJUST TABULATED LENGTHS BY THE FOLLOWING FACTOR WHERE APPLICABLE. A. REINFORCING BAR YIELD STRENGTH OTHER THAN 60 KSI: ( fy/ 60,000) STRAIGHT SPLICE LENGTH SCHEDULE SEE NOTES BELOW FOR COVER AND SPACING FACTORS DEV.LENGTH LAP LENGTH <6" AND ld/5 DEV.LENGTH REINFORCING DOWELS OR BARS CONTINUOUS THROUGH JOINT FACE OF SUPPORT, HORIZONTAL OR VERTICAL JOINT OR POTENTIAL CRACK LINE DEVELOPMENT REFER TO "HOOKED REINFORCEMENT TENSION DEVELOPMENT LENGTH SCHEDULE" WHEN THE STRAIGHT DEV. LENGTH IN TENSION CANNOT BE ACCOMMODATED IN THE CONCRETE SECTION. LAP SPLICE LAP SPLICES IN ADJACENT BARS SHALL BE STAGGERED A MINIMUM OF 24 INCHES. NOTES: 1. ALWAYS USE TENSION DEVELOPMENT LENGTH AND TENSION LAP SPLICE LENGTH VALUES, EXCEPT WHEN THE PLANS OR DETAILS NOTE SPECIFICALLY COMPRESSION LENGTHS. 2. TABULATED DEVELOPMENT AND LAP SPLICE LENGTHS ARE BASED ON REINFORCING YIELD STRENGTH FY = 60 KSI, NORMAL WEIGHT CONCRETE AND CLASS B LAPS. 3. TOP BARS ARE DEFINED AS HORIZONTAL BARS WITH MORE THAN 12 INCHES OF FRESH CONCRETE CAST IN THE MEMBER BELOW THE DEVELOPMENT LENGTH OR SPLICE. 4. WHEN DIFFERENT BAR DIAMETERS ARE SPLICED, USE LARGER BAR LAP SPLICE LENGTH. 5. ALL TABULATED VALUES AREA MINIMUM LENGTHS. IN CASE OF CONFLICT WITH THE PLANS, SECTIONS OR DETAILS, USE THE LONGER LENGTH. 6. TABULATED VALUES FOR DEVELOPMENT AND LAP LENGTHS IN TENSION SHALL BE FACTORED BY 1.5 WHEN THE CLEAR COVER IS LESS THAN db AND THE CLEAR SPACING IS LESS THAN db (AND THERE ARE STIRRUPS OR TIES ALONG ld) OR IS LESS THAN 2db (AND THERE ARE NO STIRRUPS OR TIES ALONG ld). 7. ALL STRAIGHT BAR DEVELOPMENTS AND SPLICES SHALL BE IN ACCORDANCE WITH THE LATEST EDITION OF ACI 318. 8. db = BAR DIAMETER LAP SPLICE LENGTH, INCHES FOOTINGS TOP BOTTOM #3 BAR SIZE #4 #5 #6 FDN WALLS VERTS HORIZ. SLABS SINGLE MAT DOUBLE MAT 28" 37" 46" 56" 21" 28" 36" 43" 28" 37" 46" 56" 21" 28" 36" 43" MINIMUM 60 KSI STEEL MINIMUM 3000 PSI CONCRETE 28" 37" 46" 56" STD ACI HOOK PER TYP. DTL 1. CORNER BARS MAY BE OMITTED IF BOTH WALL STEEL BARS HAVE 90 ˚HOOKS WITH MINIMUM LAPS AS SCHEDULED. 2. MATCH SIZE, SPACING, NUMBER, AND LOCATION OF HORIZONTAL WALL, FOOTING, OR GRADE BEAM BARS. 3. USE AT ALL CONCRETE CORNERS INCLUDING THICKENED SLAB ON GRADE, WALLS, CURBS, BEAMS, GRADE BEAMS, AND SLABS UNLESS INDICATED OTHERWISE. SINGLE REINFORCING MAT 1. ALL 90˚ HOOKS SHALL EXTEND TO FAR SIDE REINFORCING OF WALL OR FOOTING. DOUBLE REINFORCING MAT STD ACI HOOK FOR TYP. DTL VERTICAL BARS REQ'D @ CORNER AND LAP -3" WALL JOINT VFY JOINT LOCATIONS W/ STRUCTURAL ENGINEER IN ADVANCE WATERSTOP RQ'D WHEN EXTERIOR GRADE IS ABOVE F.F. 2x4 KEYWAY LAP PER SCHED LA P P E R S C H E D LA P P E R S C H E D LA P P E R S C H E D LAP PER SCHED LA P P E R S C H E D S C H E D LA P P E R LA P P E R S C H E D LAP PER SCHED LAP PER SCHED VERTICAL BARS REQ'D @ CORNER AND LAP -3" MIN CLEARANCES SEE TABLE FOR SCHED LAP PER 1/2" PREMOLDED EXP. JT. WHERE CONC. OCCURS SONO TUBE FDN EXTEND TO GRADE WHEN NOT IN PAVEMENT GRANULAR FILL 4"Ø CONC. FILLED STEEL PIPE -PAINT PER ARCH ROUNDED CONC. TOP 1/2" CROWN 3' - 0 " COORDINATE W/ MANUFACTURER 4' - 0" TYP. MIN 1' - 6" DATE: JACKOLA ENGR. & ARCH., P.C. WITHOUT THE WRITTEN CONSENT OF MAY NOT BE USED OR REPRODUCED IS PROPRIETARY. THIS DOCUMENT THE INFORMATION CONTAINED HEREIN REVISIONS: FOR PERMIT KALISPELL 406-755-3208 # BOZEMAN 406-586-0707 VANCOUVER 360-852-8746 DRAW N:CHECKED: info@jackola.com jackola.com S4.00 4/1/2021 CI T Y O F K A L I S P E L L PO L I C E S E A R C H B U I L D I N G 1S T A V E W . KA L I S P E L L M T 5 9 9 0 1 FOUNDATION DETAILS JTJHMH PR O J E C T # : 2 0 0 2 0 4 1" = 1'-0"1 TYP. 8" FOUNDATION WALL DTL 1" = 1'-0"2 TYP. POUR THRU & APRON 1" = 1'-0"4 SLAB AND CONTROL JOINTS 1" = 1'-0"3 SONOTUBE FOUNDATION 1" = 1'-0"5 ANCHOR LOC'NS 1" = 1'-0"6 TYP. THICKENED SLAB 1" = 1'-0"8 STAIR STRINGER CONN. TO FLOOR 1" = 1'-0"9 STANDARD REINFORCEMENT SCHEDULES 3/4" = 1'-0"7 TYP. CORNER REINFORCING DET. 3/4" = 1'-0"10 TYP. PIPE BOLLARD M O NTAN A PR O F E S S ION A L E N G INEE R LICE N S E D ERIC D. GARBERG No. 14108 PE C ADDENDUM 8/27/2021