Appendix L/Minutes from MeetingsKalispell City Airport Feasibility/Master Plan Study August 1999
APPENDIX L
MINUTES FROM MEETINGS
103
KALISPELL CITY AIRPORT
PUBLIC MEETING - CITY BUILDING
KALISPELL, MT
6/15/99
PRESENTATION
I'm Tim Orthmeyer, Morrison-Maierle Engineer. Here with me tonight are Tony Feilzer,
Terry Richmond from our Kalispell office, Dave Gabbert from the Airport District Office in
Helena, and Mike Ferguson, Montana Aeronautics. This is an informal meeting on the
plan we have developed from the Master Plan Study. We have completed Phase I which
was done earlier and we are now into Phase 11. We want to share some different
alternatives with you tonight. First I'll talk about how this project is broken down and give
you some project history and some educational material so that we can all talk about the
same thing when we get into more of the technical information.
Chapter 1. Phase I - the inventory section of the study was completed during the
Feasibility Study. That is where we looked at what is at your airport, i.e., how many
based aircraft, how many hangers, the runway alignment, etc. Just some basic
information to get started.
Chapter 2. We look at the forecasts and predict ow many aircraft will be using the
airport, how many hangers will be needed, how many tie downs will be needed, etc.
— future development items. We will get into more detail about all of these a little
later.
Chapter 3. This is the Feasibility Study that we did at the request of the FAA to
identify some key issues and see if there were some resolutions to those before we
went on. One of those issues is the "Through the Fence" operations. That is where
you have a public airport and have a private entity using that public airport without
some sort of compensation to the airport owner. That is considered "private use of
a public facility". If federal money is involved with the project, that isn't allowed by
the FAA. That is one of the things that will need to be cleared up should the FAA
participate in any part of the airport development.
• The AM Tower evaluation, many of you who are pilots know there are some
towers to the south of the airport that are considered obstructions. They are
bad enough obstructions that the FAA wants them taken care of in some way
before they will participate. They have asked the city to take care of in some
way before they will participate. They have asked the city to take care of
that as part of their obligation should the FAA participate in the funding. We
will talk about the resolution of that in a minute.
• We took a look at the air space analysis. We looked at what was available
and then with each of the alternatives we looked at some of the airspace
implications.
Land Acquisition Requirements: This is another item we looked at during
Phase I and identified what land would be needed for a B-II airport. The B-II
is basically the minimum size airport that the FAAwill participate in for safety
reasons. They expect the owner to protect that land from development in
and around the airport.
• Development Costs. We looked at what it would cost to build a B-11 airport
at the existing site and compared that to a generic site. That isn't a specific
site, but it is in the vicinity of Kalispell, 3-to-8 miles away from town. A
generic lay out at the generic location.
• Environmental Overview. We also take that a little bit father and looked at
an environmental overview of each alternative we looked at during Phase II.
Chapter 4. The Facility Requirements. That is based on the forecasts and the
existing facility. We looked at what facilities you will need in the planning period
which is about twenty years. From what we can determine whether the ideal site
will be at the existing location or a generic location. For example, how many
hangers, tie downs, runway length, etc.
Chapter 5. Site Analysis. That is where we looked at all the different alternatives
that we've identified.
Chapter 6. Financial Plan. That is the next phase of the project. Once we've
identified the costs, then we will sit down with the city staff and identify a method to
fund and finance the whole project.
Project History
In 1979, there was a Master Plan Study done. We reviewed the information in that Study
so we would be aware of what they predicted at that time. We also looked at the 1996
Neighborhood Plan. That was a good plan and it contained a lot of good information.
Some of that material has been incorporated into our study. That plan talked about the
town obstructions and the need to purchase the land for a B-11 airport.
Airport Reference Codes. (Referring to overhead). You will hear us talk bout B-1 and B-11
airports and I'll share with you a little bit of what that means. The airport approach
category is based on approach speed. That impacts the size airport you need. The
Design Group is numbers 1-4. Those are the physical characteristics of the aircraft — the
wider the wing span, the more clearance is needed. Runway Standards and dimensional
criteria are established by the approach speed and the wing span. Also the minimums —
the lower the minimums, the better airport you need and the more space requirements you
need.
A-1 = approach speed less than 91 knots. That is the slowest aircraft. The pretty
small ones with a wing span up to and not including 49 feet (i.e., Cessna 150, 172,
Bonanza, Beech Baron, Beaver)
B-1 = approach speed over 91 knots but less than 121 knots. They are faster than
an "A" but slower than a "C". The wing span is up to 49 feet (the same as A-1).
The B-1 is used as a basic approach (i.e., the larger Beech Baron, Gates Lear Jet
28, Cessna 402).
B-II = approach speed is between 91 and 121 knots. We are going up a little bit
larger for the wing span - between 49 and 79 feet. (King Air, 200's, G1, and Cessna
2 & 3). Just because you build an airport to B-II standards doesn't mean that these
airplanes are going to use it. But keep in mind that the larger the airport, the larger
aircraft you get.
AM Towers. We hired a consultant from Denver that was a specialist in radio towers and
electronics associated with them. He came up with-
1) Reconfiguring the tower array to eight 100 foot towers. Lower the towers but
you need more towers;
2) The other option was to relocate the existing towers to another site, or
3) Use another station's towers to broadcasts.
These are the things we looked at and identified some of the costs associated with that.
From that study, the preferred alternative was to reconfigure the existing array with lower
towers. The cost of doing that is about $400,000. That has been reflected in all the cost
estimates. That is shown as a 100% local cost. At least there is a way to lower the towers
without having the big expensive cost of relocating the whole radio station.
The Forecast Section (referring to overhead) - we looked at some of the things related to
that. We first established baseline guidance, i.e., how many aircraft you have on the site
now, we talked to local airport operators to find out how many people based their aircraft
here, the aircraft mix - what kinds of aircraft are using the airport, the different kinds of
aircraft based here. Then we look at how many people use the airport, i.e., local people,
itinerary travels, people passing through, and the military.
We also conducted a User Survey during the Fly - in last summer to get more information
about how the airport is used. We surveyed 223 local pilots during that study. Some
surveys were mailed out also and we received 96 responses. That helps us get a better
fell for who is using the airport, how they are using it, and how many people are flying in
and out. The results indicated they all owned small aircraft; 29 indicated they based their
aircraft at the airport either in hangars or tie downs' they average one passenger 50% of
the time; 41 indicated they would be interested in leasing hangars - that helps us identify
the need and space requirements for hangars; and the average maximum rental rate they
would pay is $108.00 We also asked why they used the Kalispell City Airport. The
responses were: people flying in, fuel business, and flight instruction, etc. It was pretty
evenly spread out.
From that information we predicted future growth. We identify every five-year increment
over twenty years. We used a number of sources to do that. We first look at the historic
data, i.e., how the airport has grown, loss of people or travelers. We found that historically
it has grown, then declined, then been pretty flat. That is reflected by the condition of the
facility. If you have a better maintained, better quality runway and infrastructure, you will
have more people using your airport.
We looked at the FAA Terminal Area Forecasts. There are conducted and researched by
the FAA. The statistics are published annually nationwide. From that we can establish
some general trends - they are showing fairly flat growth, not real steep growth in general
aviation. But they are showing growth. We also looked at the Forecast Section of the
Master Plan done by Glacier Park International Airport nearly two years.
Then we looked at some of the industry trends, basically the General Aviation
manufacturers Association organization. From that we have identified a 1.9% growth. Not
real steep growth but it's proved to be some growth otherwise we wouldn't be providing the
facilities you need here should things grow faster than that. I would like to think we could
provide a good facility here.
(Showing overhead) - Regarding environmental concerns, in this study we are looking at
just identifying the potential of some impacts. Should development proceed on and we
build or expand the airport in this area, an environmental Assessment will identify more of
the environmental problems and concerns.
(Showing overhead) - From our analysis, we ranked alternative #2 with the highest score;
alternative #1 came in second, alternate #4, the generic site, ranked 3`d, the B-1 airport
ranked 4th, and the "No-go" ranked the lowest. That is the way we rated them and basically
that is our opinion. We are hoping to get some input from the different facets involved - the
State Aeronautics people. We want to get a general sample of this.
Tim showed more overheads with specific details of each of the alternatives and how they
arrived at their conclusions. (Those are attached as Exhibit A).
This ends our formal presentation. We wanted to share where we are at right now and I
can give you an overview of where we see this going. We are planning to start into the
next phase which is the financial analysis. Normally we would expect the city to pick a site
they like the best and we would base our financial information on that specific site.
However, this situation is a little bit different so in this case we will base our financial
information on more than one site and the study well reflect that. There will not be one
preferred alternative at the end of the study. I think that is what the FAA is looking for also
- it needs a little bit more study. We are planning to work on the financial section then have
another public meeting probably early in August - tentatively August 9th. We will meet with
the city council and have a public meeting to present and discuss the alternatives and talk
about some of the financial issues. Then from there we will have a formal public hearing
30 days later where we will present the results of these studies. That is what we have lined
up for the remainder of the study.
At this time, if you have any comments or questions, I would appreciate it if you would
come to the microphone so we can get a clear recording of you question.
Art Thompson: Airport Advisory Board. You didn't talk very much about the
summation number at the bottom of the matrix diagram. It looks like
there is a substantial numerical difference between Alt. #2 at $178
and Alt. #1 at $162, but I don't think I recognize what this really
represents in terms of how clear the separation is between those two
alternatives.
Tim Orthmeyer: Referring to Matrix (showing overhead). I think what you will find is
that can change a little bit based on column 3 where you have some
flexibility. If you will look a little closer and compare the columns here.
If you look at the totals of column 1 and column 2, they are only two
apart; and if you look at column 3, they are only one apart. The real
difference is the weighted score. So something up in the column is
making the difference. It is a little bit subjective.
Art Thompson: The issue in my mind is that before we got to studying the matrix with
you, we had a pretty intuitive feeling about what was really going to
work in this situation. It happens to agree with the one you come up
with, the one that had the highest score. Based on prior experience
in other locations and studies, is this numerical difference you show
here objective enough to verify our intuitive feeling that this is the
right choice?
Tim Orthmeyer: I think is it.
Unknown: When you did your cost breakdowns in the various plans, did you
consider the affect of moving the runway 5 degrees and the increased
values of the real estate adjoining the highway? When you realign the
runway, you are moving the runway away from the highway and
increasing the quantity of highway frontage land the city may own.
Did you look at how that increased in value? You have more land that
is a higher dollar price per square foot than the land you are
acquiring.
Tim Orthmeyer: Increased in value? You have more land available on that side. If you
look at the existing alignment, we've got quite a bit of city -owned land
to the south. By moving the alignment farther to the west, we start
moving away from the city land and start picking up more private land
that we have to purchase. I thought there would be more value in that
land gained at a higher price that would offset the cost of buying more
land to the west. We have more analysis we are going to do to on the
land toward the west. Our appraiser has not been able to get to that
and he hasn't looked at the cost of Alt.#2 yet. But I thought by moving
it, that we would gain so much highway property that we wouldn't
have to buy, that it would offset - we would loose the cost of the
higher price land and gain less valuable land to the west. I thought
there would be more of a significant difference, but we gain so much
property going to the west, that it is still more expensive.
Unknown: When you calculated the bottom line, i.e., the cost of the project, did
you ...when you are moving the runway to the west on the south end,
did you add a value in for the increased value of the land along the
highway?
Tim Orthmeyer: No we didn't. That is a good point. Maybe that is something we need
to factor in.
Unknown: Well, the price per square foot of the land on the highway is far
greater than the land that you are taking. I think you should look at
that. It might affect the overall...
Tim Orthmeyer: So you are saying that by having more property still available on the
highway side, it would be more valuable?
Unknown: Well, the highway frontage property is likely to sell per square foot as
opposed to the acreage you are going to buy per acre.
Tim Orthmeyer: Ok, now I understand. We are going to take a closer look at that.
Ryan Horner: Regarding Atl. #4, if you were to go to another site and actually build
another facility, what would happen to the current airport and to the
businesses that are there?
Tim Orthmeyer: That is something that hasn't been given a great deal of consideration
in the study so far. There would definitely be an impact. There would
be an impact to a lot of the airport users, people who own hangars,
businesses on the airport, etc. Some of the costs we are a showing
as project associated costs but not essential costs such as helping
the relocation or buying of a business, etc. We are showing that there
is some financial commitment to help offset the cost of moving - that
is a non -essential cost.
Art Thompson: Would it be fair to add the board's feeling about the generic site? Our
impression is that it's there because the FAA asked us to do a
comparison with a generic site. But we consider it a non -option
because an inconvenient airport to the City of Kalispell is an
irrelevancy. The reason that this airport is valuable to this city is it's
proximity to the city and all of its services. We would say that if the
generic site was seriously considered for any reason by anybody, it
should be dismissed because the better option is just to beef up
Glacier Park International.
Tim Orthmeyer: We agree with that. Thanks for sharing that. We had failed to mention
that. When the FAA considers funding the project they may say "we
can build a new airport for $4 million but it may cost $6 million to keep
the airport at the existing site. So we are only going to spend $4
million on the existing site if you want to keep the airport there." I
can't speak for the FAA, but they may say that. Just as a side not, the
FAA has not committed to any of these alternatives yet. They have
committed to doing the study and they felt it was worth doing further
evaluation here. After the study is done and the results are in, then
the city and the FAA should probably get together and determine
where they want to go from there. I'm not saying what that will be
because there are a lot of factors to consider, but I thing there is a
good chance the City of Kalispell could realize the benefit of some
federal money if we can get things done right.
Jack Archibald: I think that in some ways you've overstated the generic site. 1)
Finding land that would be suitable - it almost sounds like you can go
out and pick it, and you can't. 2) I've said this in every meeting I've
ever been at, the whole key to this airport is location, location,
location. That is what has made the airport, it is what made it busy
and al alternate - this study kind of shows a generic site as a little too
good and it won't be. There will be problems with getting the land and
getting the location and as far as wind direction, even the Glacier
International Airport has cross winds all the time. You just can't go
pick it out.
Tim Orthmeyer: Thank you I appreciate those comments. If we hadn't considered a
generic location, sometime down the road somebody would ask us if
we had. We are making a lot of assumptions when looking at the
generic location and maybe they are a little bit better than reality, but
without a specific site in mind, it is just our best guess at this point.
Art Thompson: What is the realistic time schedule for completion of the study? To fit
with the FAA's time schedule, when could we see some blacktop?
Tony Feilzer: Completion of this study will have to be followed by an environmental
assessment and land acquisition.
Time Orthmeyer: Now this is assuming - we are making assumptions here - that it is
something other than the B-1 alternate and the $1 million city option
is going to happen. Now say we get the study done on schedule in
early September. We have our public hearing in early September and
it is done. I don't know how much time the city or the FAA requires for
review and processing, but say Alt. #2 gets selected. We could get
started with an environmental assessment in September/October and
that will take about one year to complete. Land acquisition - you are
going to have 40 parcels of land to acquire. Even if things went
smooth with land acquisition and we had all willing sellers, you could
probably do it in a year/12 months. If we had some parcels that take
more time during negations and we decide we have to condemn some
parcels, land acquisitions could take up to three years with that many
people. But if we selected the B-1 city option, you could be paving
next summer.
Art Thompson: I've heard that before but that was in reference to this summer. Well,
you've answered pretty well. I think what we are really doing here by
way of commentary is really meeting both this communities and the
FAA's concern that we are planning something that is going to be
good 20/30/40 years hence. Rather than doing a mickey-mouse job
or no job at all. We don't think that we can afford to do either one of
those.
I would make a plea for whatever part of the process can be
expedited. Part of that is selfish - we've been on duty for five years.
It was scheduled to be a one-year job and we're running out of the
ability to stay the course. But we're here. Aside form that, the city
deserves to move ahead for its own reasons. I don't think it needs to
be expedited to the detriment of doing the right thing, but it needs to
be expedited. We need to have a motion here. It is amazing what has
happened just by getting this fencing in place in terms of recognition
by the local people that something is really happening on this airport.
When we get to the stage where we are really doing something on
the ground, it is going to be reinforced. People are going to realize
that hit is really happening and a lot of people who are concerned
about what is happening around the airport will begin to understand
what their options are. They need that. Those are the people who are
in business along the highway, the real estate concerns, city
government, etc. We need not to drag this out forever and ever.
Dave Gabbert: You mentioned something about wetlands? Assume that we took Alt.
#2 and went forward with wanting to buy the additional land, what
would you expect the EIS to say. Could we select Alt. #2 and then all
of a sudden find out that something is going to come out in the EIS
that would preclude our ability to go forward or do you feel that the
environmental issues are pretty solid and reasonable?
Tim Orthmeyer: From our initial analysis, we don't see any show stoppers with any of
them. Obviously there are some neighborhood impacts on the
existing alignment, but we don't see anything that would really stop
the project. We don't have any significant wetlands that we can see.
Mike Ferguson: State Aeronautics Division. We have made our position clear that we
would like to see this airport developed. We think it has great
potential. We think like you all do, but you have to jump through these
stupid hoops to satisfy the FAA about this alternative airport. Nobody
believes in it and nobody wanted ti, and they have to spend lots of
money proving that you don't want it. We hate to see that but we
know it is part of the requirements when yo are doing any airport
project.
We are able to help with some of the local community sponsor's
share of the funding through both low interest loans and grants. The
program we have now is somewhat new and it is going very well and
is helping a lot of airports in the state with their local 10% share. A lot
of times it is not a lot of money, but it is essential to get projects
kicked off. We use this airport all the time. We use it annually for our
mountain search pilot clinic. Over the years we have been very much
involved in brining different tour groups into Kalispell because quite
frankly it is the only airport in the state that can accommodate those
kind of things satisfactorily. There are others who can do it, but
through a great deal of logistics and added expense. So we are really
committed to seeing this airport thrive.
I do have one correction I would like to make. With all due respect
"through the fence operations" are permitted by the FAA. They frown
upon it, but there is nothing prohibiting it so long as there is
reasonable compensation. That is in the FAA Advisory Circular. So
that may ease some of the concern. In state airports, we believe in
"through the fence operations." It helps the airport and we do get
compensation for it. We have 15 state-owned airports. We like to
encourage that but I know the FAA does not. However, it is
permissible.
Gil Johnson: What is "through thefence operations'? I'm notfamiliarwith that term.
Tim Orthmeyer: Explaining "through the fence operations" - that is when you have
private property adjacent to a public airport with access to the airport.
In other words, if you have private property with a hangar on your
property and you have access to the airport where you can taxi out
and use the airport, basically you have exclusive use to publicly -
owned property. It is not prohibited, but it is discouraged. What
makes it acceptable is if you pay some fee for access. It has to do
with fairness. The FAA is really strong on being fair to all the users of
the airport and that would give you an unfair advantage.
Gil Johnson: How would that affect our airport?
Unknown: Both FBO's are on private property and they both have access to the
airport facility. Under the "through the fence" rules, the FAA really
doesn't like to see that .Basically it allows uncontrolled access to the
airport facility and that is undesirable.
Tim Orthmeyer: At most airports that are FAA developed, i.e., the hangars and FBO,
they lease the property form the airport owners. At Glacier Park
International the FBO's lease the ground in order to have a hangar
and operate. That is how it is deemed fair.
Gil Johnson: So what it sounds like to me is you want to lengthen the runway, get
rid of the two FBO's, and spend a lot of money and fence everything
in?
Tim Orthmeyer: No, we are not saying get rid of the FBO's. We are encouraging the
FBO's to be a part of the airport, but what might happen is that the
city may ask them to pay a fee to use the airport if they have private
property. See that makes if fair then. They don't have exclusive use
of public property. It's a fairness thing. If you have property that you
own a house on and put a hangar on, then maybe the airport or city
would aks you to pay a fee to rent - an access fee.
Tony Feilzer: The bottom line is that before the FAA would approve any grant on
Kalispell City Airport, there would have to an approved "through the
fence" agreement between the city and the "through the fence"
operators. I don't have any idea what would be a part of that
agreement, but it would have to be approved before any federal
money could be spent on this airport.
Gil Johnson: What is the fee? Does anybody know?
Unknown: A nominal lease rate fee. It is kind of a discrimination issue. So if you
are out there and you are not paying a similar fee structure, then you
have an advantage. So somehow equalization of that fee structure
has to happen.
Art Thompson: I want to point out that we have a little bit of a unique situation here.
Both of the fixed based operators are on owned property even though
they are right on the airport - they own their property fee and clear. I
is fee simple property, it is not city property. They are not going to be
on a lease with the city. Historically they have had a relationship with
the city right along and we expect that will be formalized in some way
that will be satisfactory to the FAA
Dave Hoerner: Red Eagle Aviation(?) Right now there is a fee and in fact there
always has been. We are not using it free, we pay a fee. It is nominal
but we still pay.
Art Thompson: Our FBO's have acted as agents for the city in several respects over
the years. So the relationship has been good and 1 expect it will
continue to be good.
Dave Downey: President of Local Hangar of the Montana Pilots Association. It is
hard to be unbiased when you are a pilot. It is awfully nice to be able
to fly out of the Kalispell City Airport but I don't think that is
justification for having Kalispell City Airport. But I don't think it has
been mentioned here tonight about the economic impact this has for
the city of Kalispell. Is that going to be part of your study?
Tim Orthmeyer: We are not specifically looking at the economic impact. We
understand and realize there is significant economic impact to the
community by having the airport. There are a lot of studies that have
been done in other communities around the country that show a
significant benefit to having the airport. We aren't providing that as
part of this study. I understand the Board has talked to somebody
about getting one done.
Art Thompson: We recognize the value of that. The problem with doing a formal
study is expenses and it can not under current conditions be included
in the FAA contract for the Master Plan Study and we understand
that. Nevertheless, we have had some conversations with Greg
Davis, Professor at Flathead Valley Community College and also with
the Bureau of Economic Research at the university of Montana. Again
it is an expensive thing to do a full study. The only semblance of a
study is now 20 years. It showed a $1.5 million economic benefit
estimate at that time and on an inflation basis over twenty years, it
would be twice that. So we are currently probably experiencing a $3
million economic benefit to this valley and it is anticipated that could
be verified by a formal study. It might in fact, by some estimates
including people from Glacier Park, be as much as $5 million
currently and that is without improvements to the airport.
Gil Johnson: It seems to me that these studies are going to go on and they are
necessary but is there anybody we can talk to to get a couple of
things done on the runway, i.e., the numbers painted, a sweeper to
come in and take the rocks off the runway, etc? At least improve it in
some way? Some of the feeders like Fed Ex. And the small airlines
come in and use our airport, I see them all the time. They can't get
into Glacier because it is foggy, etc. Those are expensive machines
and so are the light aircraft and it is really hard on the propellers. I
don't know if you can do anything about it or if anybody here can, but
I would at least like to see the numbers painted and maybe a sweeper
go down the runway. I don't want to put a lot of money into this thing
if we are going to change it, but a small improvement would be nice.
Lorraine White: I've been to a lot of these meetings and I always hear "down the road"
for things to be done. My problem is that there is $1 million in the city
coffers for the airport. I'm wondering if that money can be tapped
before/after/during/while we are waiting for the FAA to do something,
can we use that money to sweep the runway? Can we use it to paint
numbers? If the decision is the 5 degree angle, can we put the paving
out to 3,600 feet first and then move it out to 4,300 and on to 4,700?
Why are we waiting with this $1 million? I know the interest must be
great at 10% but I say "take this money, we've already set it aside for
the airport. It was our money in the beginning." They are out there
building those softball courts and that money was set aside at the
same time as the airport money. They are making great headway on
their fields. I would like to see somebody think in terms of the $1
million - what can we do with it constructively moving toward FAA
commitment or eventually B-1 or B-2? Use it now and get something
done.
Dale Harr: City Councilman. I would like to just clarify a couple of things
regarding the maintenance. We do have a budget, we have the
fencing budget, we are looking at hiring a part-time manager and I'm
sure that we can find a way to do some maintenance that you alluded
to - at least get the gravel off and paint the numbers. But another
issue is the $1 million. We have committed the $1 million but that
money is in the property where the Daily Fields were. As of late last
week when we were to open the bids for the sale of the three acres
north of the Rosauer site which is under construction, we didn't
receive one bid. So the money isn't in the bank. The commitment is
there and we have the 10+ acres that will net that amount in some
way at some point. We have not had a meeting yet on the bid
opening and the fact that there weren't any bids. So we are kind of
back to the drawing board. It is not that we want to procrastinate or
take any more time. We are as anxious as all of you are to move this
thing forward and get a good decision made. The city is committed.
We've assured you that there is $1 million. It will be there, but it isn't
there to spend now. We do have a budget and we are trying to
increase that. I think we've adopted a new fee schedule and there is
going to be a part-time manager. That money will flow in. But the
committee can take that up and get some maintenance done.
Mike Ferguson: We cant's remember which state just developed a matrix for a low-
cost economic impact study for an airport. We'll find out what we can
about that and get a copy.
Art Thompson: I believe it is New York State and I believe it is state-wide rather than
just one airport. I made some inquiry about that. The State University
System and New York State was involved in that and it's an on -going
thing. They will do one or a few at a time, but they are going to do it
as a state-wide program. I think it was funded by the legislature there.
Mike Ferguson: I don't think that is the one we are talking about. I believe it was a
southern state like Louisiana or Georgia. It had numerical data -
number of based aircraft, number of tie downs, etc., and was all tied
into the economic impact of the airport.
Art Thompson: The methodology is there. Oregon has done a pretty good job through
their Aeronautics Division for a number of different airports in Oregon.
CLOSING
Tim Orthmeyer: If there are no other comments, we really appreciate everyone coming
out tonight. We appreciate all your comments. Just to remind you if
you would like to provide some written comments or information
please send it to the City Manager by July 15th and we'll get it
incorporated into the project and the study. Thanks for coming.
Meeting Adjourned at 8:45 p.m.