Chapter 4Kalispell City Airport Feasibility/Master Plan Study August 1999
CHAPTER FOUR - FACILITY REQUIREMENTS
FACILITY REQUIREMENTS
The facility requirements chapter of this report defines the physical facilities needed to safely
and efficiently accommodate the current and future aviation demands at the Kalispell City Airport.
The aviation forecasts discussed in the previous sections are used as the basis for determining the
physical requirements such as pavement, buildings, and support facilities needed to meet the aviation
needs of the community through the next twenty-year period. Facilities discussed in this section
include the runway, taxiway, tiedowns, hangars, apron, navigational aids, and miscellaneous
facilities.
Although the required developments are defined in specific time frames, it is necessary to
continually review the activity levels achieved. For example, if the number of operations and based
aircraft forecast increase more rapidly than indicated, the time frame for development would also
be accelerated. Likewise, if the number of operations or based aircraft should decrease, the time
frame for development would be delayed.
Recent technical developments in Global Navigation Satellite Systems applications, may
make it possible for Kalispell City Airport to achieve a non- precision instrument approach within
the study period. Commissioning of a non -precision approach would generate several new
requirements that are not met by the existing site and increases several dimensions of an airport that
has a visual approach. For example, larger safety areas are required in width and longer beyond the
runway end, runway protection zones are larger, runway width is increased to 100 feet, and the
object free area is also increased. However, the ultimate plan will consider the non -precision
approach and make provisions to accommodate the growth required.
CRITICAL AIRCRAFT
Federal interest in funding airport development is influenced by the operation of the critical
aircraft using the facility. Critical aircraft are considered to be those aircraft using the airport facility
which because of their size and capacity, require the greatest facility considerations, (ie. runway
length, runway width, separation distances, etc). Generally, ten operations per week of the critical
aircraft (520 annual operations) determines the type of airport needed.
Once the critical aircraft is known, the Airport Reference Code (ARC) may be determined,
and the design criteria associated with that ARC applied to the design of airport facilities. The ARC
is a coding system used to relate airport design criteria to the operational and physical characteristics
of the airplanes intended to operate at the airport. FAA Advisory Circular 150/5300-13, entitled
"Airport Design" indicates that the ARC has two components relating to the critical aircraft. The
41
Kalispell City Airport Feasibility/Master Plan Study August 1999
first component is the aircraft approach category, which relates to aircraft approach speed. The
second component is the airplane design group, which relates to airplane wingspan.
The "Aircraft Approach Category" is a grouping of aircraft based on 1.3 times their stall
speed in their landing configuration at the maximum certificated landing weight. The categories are
as follows:
Category A: Speed less than 91 knots;
Category B: Speed 91 knots or more but less than 121 knots;
Category C: Speed 121 knots or more but less than 141 knots;
Category D: Speed 141 knots or more but less than 166 knots.
The "Airplane Design Group" is a grouping of aircraft based on wingspan. The groups are
as follows:
Airplane Design Group I: Wingspans up to but not including 49 feet;
Airplane Design Group II: Wingspans 49 feet up to but not including 79 feet;
Airplane Design Group III: Wingspans 79 feet up to but not including 118 feet.
The users survey indicates that the Kalispell City Airport is used almost exclusively by small
(12,500 lbs. or less maximum takeoff weight) Design Group I, Approach Category A and B aircraft.
The airport is also used by Design Group II aircraft. The most demanding aircraft based at Kalispell
City Airport currently is a Turbo Comander (maximum takeoff weight less then 12,500, ARC A -I).
Based on the results of the users survey, this study indicates a present need for facilities which will
accommodate B-I aircraft. The future ARC for the Kalispell City Airport should be a B-II aircraft.
The B-II aircraft have been increasing in use by business concerns, and the user survey indicates that
in the future there may be B-II aircraft operations. The air ambulance operators are also flying
aircraft that are in the B-II ARC.
The type of approach procedure utilized at the facility (le. visual, nonprecision instrument,
or precision instrument) must also be considered when determining the applicable design criteria.
Visual Runway is a runway solely intended for the operation of aircraft using visual
approach procedures, with no straight -in instrument approach procedure and no instrument
designation indicated on an FAA approved airport layout plan, or on other planning
documents.
Nonprecision Instrument Runway is one with an instrument approach procedure utilizing
air navigation facilities, with only horizontal guidance, or area type navigation equipment
42
Kalispell City Airport Feasibility/Master Plan Study August 1999
for which straight -in nonprecision instrument approach procedure has been approved or
planned and no precision approach facility or procedure is planned or indicated on an FAA
approved airport layout plan or other planning document.
Precision Instrument Runway is one with an instrument approach procedure utilizing a
conventional instrument landing system (ILS), global positioning system (GPS), microwave
landing system (MLS), or precision approach radar (PAR). A planned precision instrument
runway is one which a precision approach system or procedure is indicated on an FAA
approved airport layout plan or other approved planning document.
Although the Kalispell City Airport includes an NDB, no published non -precision instrument
approach exists at the airport. Upgrading the existing runway to a nonprecision approach would
require removal of several buildings in the apron area, to provide clear primary and transitional
surfaces.
Some of the key dimensions for Airport Reference Code B-II, for a visual/nonprecision
instrument approach, and also for ARC B-II with a precision instrument/visual approach are shown
on Table 11. All design dimensions for ARC B-II with a visual/nonprecision instrument approach
and non-precision/precision approach are listed in Appendix G.
TABLE 11
DIMENSIONAL STANDARDS FOR
NON - PRECISION APPROACH (FT)
ITEM
ARC B-II
Non -Precision Instrument
RUNWAY:
Width of Pavement
75
Width of Safety Area
150
Length of Safety Area Beyond
300
Runway Threshold
TAXIWAY:
Width of Pavement
35
Width of Safety Area
79
SEPARATIONS:
Runway Centerline to Parallel
Taxiway Centerline
240
Runway Centerline to Parked
240
Aircraft
300*
Taxiway Centerline to Parked
66
Aircraft or Movable Object
* Aircraft parking Line based on 7:1 clearing a 7' obstruction (aircraft)
43
Kalispell City Airport Feasibility/Master Plan Study August 1999
RUNWAY
Advisory Circular 150/5325-4A, entitled Runway Length Requirements forAirportDesign,
divides aircraft into two groups for the purpose of determining runway length. These basic groups
include: 1) airplanes up to and including 60,000 pounds; and 2) airplanes over 60,000 pounds. For
the Kalispell City Airport, the required runway length is determined based on the procedures
outlined for airplanes up to and including 60,000 pounds.
This group of airplanes is further broken down into the following subgroups: 1) airplanes
with approach speeds less than 30 knots; 2) airplanes with approach speeds of 30 knots or more but
less than 50 knots; 3) airplanes with approach speeds of 50 knots or more and Maximum Certificated
Takeoff Weight of 12,500 pounds or less; 4) all airplanes with Maximum Certificated Takeoff
Weight of more than 12,500 pounds and up to and including 60,000 pounds. The majority of the
aircraft using the Kalispell City Airport fall into subgroup 3.
Considering the existing airport elevation of 2932 feet above sea level and the mean daily
maximum temperature in the hottest month of 87°F, Table 12 illustrates the approximate lengths of
runway required under criteria of subgroup 3 listed above. A computer output of required runway
lengths is included in Appendix G.
TABLE 12
RUNWAY DIMENSIONS (FT)*
AIRPORT TYPE
RUNWAY LENGTH (FT)
WIDTH
ARC B-II
N.P.I.
Small Airplanes w/less than 10 passenger seats
75% of these small airplanes
3,600
75
95% of these small airplanes
4,300
75
100% of these small airplanes
4,700
75
Small Airplanes w/10 or more passenger seats
4,680_=
75
* Runway Elevation 2932' MSL, Mean Daily Maximum Temperature 87°.
Small airplanes are those airplanes with a Maximum Certificate Takeoff Weight of 12,500 pounds
or less. v
N.P.I. Non -Precision Instrument
Kalispell City Airport Feasibility/Master Plan Study August 1999
The recommended ultimate runway length for the Kalispell City Airport considering the
above criteria and future needs of the airport and increased usage of business jets and larger
turboprop aircraft, is 4700 feet. This length will account for virtually 100% of small aircraft.
However, should the City of Kalispell decide to phase the construction of the runway lengths, the
initial length could be built to match the current length of 3600 feet with a runway extension to 4500
feet when aircraft demands warrant that runway length. It is apparent that the immediate needs
justify the 3600 foot length, however, as shown on the ALP drawings, the ultimate runway length
of 4700 feet is used for planning purposes and airport protection and may be required at a later date.
WIND COVERAGE
As previously noted, the most desirable orientation based on wind is one which has the
largest wind coverage and minimum crosswind components. If 95 % wind coverage is not feasible
with one runway for a 10.5 knot crosswind component, then a crosswind runway should be
considered. FAA design criteria requires a cross wind runway to be 80% of the length of the primary
runway.
The wind coverage data at Kalispell City Airport is somewhat limited, however the
information available from the reports of local pilots, along with wind data from Glacier Park
International Airport suggests that the highest percentages in the north -south directions.
HANGARS
The required member of hangar spaces and the number of tiedowns are directly related to the
number of based aircraft. Currently there are two nested tee hangars and eight commercial hanaars
located on the airport. The two tee hangars are capable of holding 6 aircraft in each for total of 12
hangars. The commercial hangars are large enough to store more than one aircraft in each facility.
Therefore, an average of three aircraft per hangar will be assumed for this analysis. From this, we
estimate a total of 36 hangar sites are available on the airport.
Hangar sites typically include support items such as pavement for the taxilanes and hangar
floors, electricity, and automobile access/parking areas.
Assuming that 80 percent of all based aircraft are to be hangared at the Kalispell City
Airport, the current number of hangars does not meet the current demand and will obviously, not
meet the future demand. Currently there are 62 aircraft based at the airport, and 141 are forecast for
the year 2018 (see Table 4, Chapter 2). Based on 80 percent occupancy, at least 50 hangar spaces
are presently required at the airport. Table 13 indicates the number of hangar spaces that would be
needed to provide 80 percent housing for based aircraft throughout the planning period.
M.
Kalispell City Airport Feasibility/Master Plan Study August 1999
TABLE 13
HANGARS
YEAR
BASED
AIRCRAFT
HANGAR SPACE
AVAILABLE
HANGAR SPACE
NEEDED (80%)
1998
62
36
50
2003
78
36
62
2008
88
36
70
2013
102
36
82
2 118
119
36
95
TIEDOWNS AND APRON
Tiedowns must be available for those based aircraft not in hangars and for itinerant aircraft.
The number of tiedowns for transient aircraft are determined from peak day operations (see Table
3.2).
Using forecasting methodology presented in FAA AC 5300-13 (page 117), the average
number of itinerant operations per day is increased by 20% to determine an average peak for a busy
day. This is not the highest number of operations occurring on a given day, but it is the average of
the busy days. Because one operation is either a landing or take -off, only half of the peak day
operations represent an aircraft on the apron and in need of a tiedown. Some aircraft will not be on
the apron long enough to require a tiedown, such as aircraft on the apron for a fiiel stop or a
passenger pick-up.
TABLE 14
TRANSIENT AIRCRAFT TIEDOWNS
YEAR
MAXIMUM
ITINERANT
OPERATIONS*
AVG. DAY
OPERATIONS
PEAK DAY
FACTOR
PEAK DAY
OPERATIONS
TRANSIENT
AIRCRAFT
TIEDOWNS
2003
15,630
110
1.2
132
66
2008
17,964
127
1.2
152
76
2013
20,646
146
1.2
175
87
2018
23,728
167
1.2
200
100
Based on "Forecast Air Operations" Table 2.3 (439 -485 OpsBA), the assumption that July is the busiest
month with 21.9 % of the total annual operations (based on fuel sales), itinerant operations equal 41 % of the
annual operations, peak day factor of 20%, and parked aircraft equal 50% of peak day operations.
.n
Kalispell City Airport Feasibility/Master Plan Study August 1999
On a particularly busy day, contingency tiedowns will accommodate aircraft when no paved
tiedowns are available. Contingency tiedowns are not on pavement, but turf. When tiedown fees are
charged, it has been found that some owners of based aircraft prefer the less expensive turf tiedowns.
TABLE 15
TIEDOWNS
YEAR
BASED
AIRCRAFT
BASED
AIRCRAFT
TIEDOWNS
TRANSIENT
AIRCRAFT
TIEDOWNS
CONTINGENCY
TOTAL
TIEDOWNS
2003
1 78
26
66
10
102
2008
88
26
76
12
114
2013
102
26
88
13
127
2018
119
26
100
15
141{
Normally accepted planning criteria allows 300 square yards of tiedown apron per based
aircraft and 360 square yards per transient aircraft. These areas include taxiway and maneuvering
area. Besides the tiedown area several other items including fueling areas, access to hangar areas,
and ftiture expansion must be considered in order to determine the actual apron area required.
TABLE 16
PAVED TIEDOWN AREA
(SQUARE YARDS)
YEAR
BASED
AIRCRAFT
TIEDOWNS
AREA FOR
BASED
AIRCRAFT
TRANSIENT
AIRCRAFT
TIEDOWNS
AREA FOR
TRANSIENT
AIRCRAFT
AREA
NEEDED
2003
26
7800
66
23,760
31,560
2008
26
7800
76
27,360
35,160
2013
26
7800
88
31,680
39,480
2018
26
7800
100
36,000
43,800
Note: Area for based aircraft calculated at 300 square yards per aircraft and for transient aircraft it is calculated at
360 square yards per aircraft.
47
Kalispell City Airport Feasibility/Master Plan Study August 1999
NAVIGATIONAL AIDS
Navigation aids are divided into two categories: 1) visual aids, such as runway lighting,
airport beacon, obstruction lighting and PAPIs, and 2) instrument navigational aids such as Non -
Directional Beacon (NDB), Very High Frequency Omni Range (VOR), Instrument Landing System
(ILS) or Global Navigation Satellite System (GNSS).
Recent technical developments in Global Navigation Satellite Systems may make it possible
for Kalispell City Airport to obtain non -precision instrument approaches within the study period.
The possibility of the Kalispell City Airport obtaining a non -precision instrument will exist from a
technological standpoint and the possibility from an aeronautical stand point is likely. Ultimate
approaches for the new development alternatives identify a non -precision approach.
LAND
The Kalispell City Airport should acquire sufficient property to accommodate both initial
development and future development, as well as obtaining runway protection zone acreage. Figure
4 shows land requirements for a B-II runway. The runway and runway protection zones are a
constant acreage for each site, however, the access road land acquisition varies depending on the
location of the nearest public road.
LANDING AREA
APPROACH APPROACH
AREA PJ.%WA. AREA
BUILDING AREA
48
Kalispell City Airport Feasibility/Master Plan Study August 1999
FIGURE 4
MINIMUM LAND REQUIREMENTS
RUNWAY TYPE
RUNWAY
LENGTH
LANDING AREA
APPROACH
AREA
BUILDING AREA
TOTAL AREA
ACRES
B-II
NON -PRECISION
4,700 feet
93.66 acres
36.73 acres
35.41 acres
165.80 acres
Preferably, all land should be purchased fee simple. This would assure the complete control
over the use of that land as well as the revenues generated. If, for some reason, the runway
protection zone acreage cannot be acquired fee simple, then they should be controlled with an
easement. However, if future demands warrant use ofthe land for airport purposes, acquisition could
prove expensive, if not impossible. In addition to the airside purchase, access road acreage may be
required which varies considerably from site to site.
The FAA would require that the Owner of the Airport certify that they will have "good" title
to the property before a grant would be issued or initiate payment for the property. This will require
substantial money, time and effort up front by the sponsor for appraisal and review appraisal fees,
potential legal fees and purchase of those parcels that can be acquired, non contested or without
going through condemnation. If the City has to condemn, costs can potentially escalate. Before the
FAA would issue a grant, the FAA would also require that all of the parcels necessary to
accommodate the B-II facility and at least 95% of the runway length be acquired or guaranteed for
sufficient title prior to any payment or issuance of a grant.
Boundary fencing is also a very important item which must be constructed as land is
acquired. This item has been included in the initial cost estimates.
UTILITIES
Water - The City Water Department currently supplies water to those facilities on the airport
requiring water. Should greater industrial needs arise, (ie. agricultural spraying, manufacturing, etc.)
then additional water may need to be secured. A new site would require drilling of a new water well.
This item is not eligible for AIP funding.
Sewer - The airport is currently connected to city sewer. These connections are adequate for
a small pilots building and projected domestic needs of the airport subject to any local and state
requirements. Any manufacturing or commercial facilities constructed on airport property, may have
sensitive wastewater facility needs, such as for chemicals, oil or grease. These would have to be ad-
dressed individually and are not anticipated at this time. Precipitation which runs off any airport
Kalispell City Airport Feasibility/Master Plan Study August 1999
pavement and which is collected in a storm drainage system will need to comply with appropriate
storm water runoff requirements established by the State and EPA. Appropriate permits will be
required. The domestic and industrial sewage needs are not an item that is eligible for AIP funding,
however, stormwater management generated by the airport property is considered eligible for AIP
funding.
Electricity / Telephone - All new electrical / communication lines within the airport should
be placed underground in conduits. Electrical service to a new airport site for airport lighting is
considered eligible for AIP funding.
Airplane Fuel - There are presently five fuel storage tanks in use at the airport. They are
two 12,500 gallon underground tanks at Red Eagle Aviation, two above -ground storage tanks at
Eagle Aviation, an one two -compartment with a 17,000 gallon capacity at Diamond Aire. EPA
regulations require fueling facilities to provide overflow containment and leak detection. New fuel
storage facilities at a new site may be a future requirement. Fuel storage development is not
considered eligible for AIP funding.
AIRPORT ACCESS AND PARKING
Access to the existing airport is via Airport Road to the west and U.S. Highway 93 to the
east. Designated parking is located south of Red Eagle Aviation and on the north side of Diamond
Aire, and on the north side of Eagle Aviation. Signing and fencing should be provided to prohibit
access of unauthorized vehicles beyond a certain point. Access to a new airport site is a critical cost
for a new facility and will be considered in the preliminary cost estimates.
SUMMARY
The ultimate development for an airport serving the Kalispell community should utilize
ARC B-II aircraft as the design aircraft, have a runway length of 4700 feet in length, with non -
precision approaches at each end to meet the needs of the community for the 20 year planning
period. The facility should also have visual guidance equipment such as precision approach path
indicators (PAPI) at each runway end.
All separations and design criteria should be based on the above recommendation. Any
developments completed without this ultimate plan would be short sighted considering the recent
trends in navigation technology.
Land acquisition should be based on this plan as ultimate development. The runway
protection zones should be acquired in fee, if possible.
50