Loading...
SIA (Recorded)SUBDIVISION IMPROVEMENT AGREEMENT THIS AGREEMENT, made and entered into this 5-d� day of �e , 20 CO, by and between CITY COUNCIL, CITY OF KALISPELL, MONTANA, Party of the First Part and hereinafter referred to as the CITY, and GWENN LEE TRUST, Parry of the Second Part and hereinafter referred to as DEVELOPER. WITNESSETH: THAT WHEREAS, the Developer is the owner and developer of a new subdivision known as Lee's Meridian Business Park, located in Kalispell, Montana in the NE 1/4, NE 1/4 of Section 13, Township 28N, Range 22W, Flathead County, Montana; and, WHEREAS, the City has conditioned it's approval of the final plat of Lee's Meridian Business Park, upon the conditions as set forth in the Preliminary Plat of the Subdivision being completed and all improvements, as cited in "Exhibit A", have not been completed at this time, and the Developer wishes to bond for the completion of those improvements set forth in "Exhibit A"; and, WHEREAS, the City's Subdivision Regulations require that a subdivider shall provide a financial security of 125% of the estimated total cost of construction of said improvements as evidenced by an estimate prepared by a licensed professional engineer included herewith as "Exhibit B"; and, WHEREAS, the estimated total cost of construction of said remaining improvements is the sum of $ 28,680.00 . NOW THEREFORE, in consideration of the approval of the final plat of said Subdivision by the City, the Developer hereby agrees as follows: 1. The Developer shall deposit as collateral with the City a Letter of Credit, or other acceptable collateral as determined by the City Council, in the amount of $ 35,850.00 . Said Letter of Credit or other collates al shall have an expiration date of at least sixty (60 j days following the date set for completion of the improvements, certifying the following: a. That the creditor guarantees funds in the sum of $ 35,850.00 , which represents 125% of the estimated cost of completing the required improvements in Lee's Meridian Business Park. b. That if the Developer fails to complete the specified improvements within the required period, the creditor will pay to the City immediately, and without further action, such funds as are necessary to finance the completion of those improvements up to the limit of credit stated in the Letter of Credit; 2. That said required improvements shall be fully completed by May 1, 2001 . Page 1 3. That upon completion of the required improvements, the Developer shall cause to be filed with the City a statement certifying that: a. All required improvements are complete; b. That the improvements are in compliance with the minimum standards specified by the City for their construction and that the Developer warrants said improvements against any and all defects for a period of one (1) year from the date of acceptance of the completion of those improvements by the City; C. That the Developer knows of no defects in those improvements-, d. That these improvements are free and clear of any encumbrances or liens, e. That a schedule of actual construction costs has been filed with the City; and, f. All applicable fees and surcharges have been paid. 4. The Developer shall cause to be filed with the City copies of final plans, profiles, grades and specifications of said improvements, with the certification, of the registered professional engineer responsible for their preparation, that all required improvements have been installed in conformance with said plans and specifications. IT IS ALSO AGREED BY AND BETWEEN THE PARTIES HERETO AS FOLLOWS, TO WIT: That the Developer shall provide for inspection of all required improvements by a registered professional engineer before the Developer shall be released from the Subdivision Improvement Agreement. That if the City determines that any improvements are not constructed in compliance with the plans and specifications, it shall furnish the Developer with a list of specific deficiencies and may with collateral suffi6e nt to insure such compliance. If the City determines that the Developer vaill not construct any or all of the improvements in accordance with the plans and specifications, or within the required time limit(s), it may withdraw the collateral and employ such funds as may be necessary to construct the improvements) in accordance with the plans and specifications. The unused portions of the collateral shall be returned to the Developer or the crediting institution, as is appropriate. That as improvements are completed, the Developer may apply to the City for a release of part of the collateral deposited with the City. The proportion of the collateral released may not exceed the proportion which the improvements completed represent of all originally required improvements; otherwise, said Letter of Credit may not be withdrawn until released by the City. That this agreement shall inure to the benefit of and be binding upon any successors in interest, heirs, or assignees. Page 2 IN WITNESS WHEREOF, the Parties to this agreement have hereunder set their hands and seals the day and year herein before written. LEE'S MERIDIAN BUSINESS PARK GWENN LEE TRUST B (Title) STATE OF MONTANA, COUNTY OF FLATHEAD On this G--� day of , 20 0(-\ , before me, a Notary Public for the State of Montana, personally appeared :J�% n 0,DVVJGIA known to me to be the person whose name is subscribed to the foregoing instrument and acknowledged to me that he executed the same. IN WITNESS WHEREOF, I have hereunto set my hand and affixed my Notary Seal this day and year first above written. 07 A Notary Public for the State of Montana } - Residing at {,2 t'( U B t'`r My Commission Expires (b /uq (o This agreement is hereby approved and accepted by the City of Kalispell this day of )200/ _. MAYOR, CITY OF KALISPELL ATTEST: F, By: Mayori Page 3 EXHIBIT "B" CERTIFICATION OF WORK TO BE COMPLETED LEE'S MERIDIAN BUSINESS PARK SUBDIVISION ROAD COMPLETED TO DATE 5-Dec-00 Item No. Description Unit Measure Estimated Quantity Unit Price Total Price QUANTITY COMPLETED TOTAL COST COMPLETED 101 Unclassified Excavation C.Y. 2,050 $ 1.80 $ 3,690.00 2,050 $3,690.00 102 Select Sub -Base, 3" (-) Pit Run Gravel LUMP SUM 1 $ 8,000.00 $ 81000.00 100% $8,000.00 103 Crushed Base, 3/4" Crushed Gravel S.F. 22,000 $ 0.14 $ 3,080.00 22,000 $3,080.00 104 Hot Plant Mix Asphalt (4" - Two Lifts) S.F. 18,880 $ 0.75 $ 14,160.00 18,880 $14,160.00 105 Curb and Gutter L.F. 1,022 $ 7.00 $ 7,154.00 1,022 $7,154.00 106 Valley Gutters w/ Aprons S.F. 320 $ 4.00 $ 1,280.00 0 $0.00 107 Sidewalk (5' Wide) w/ Prepared Base S.F. 6,900 $ 3.00 $ 20,700.00 0 $0.00 SUBTOTAL ITEMS 101-107 $ 58,064.00 $36,084.00 WATER SYSTEM Item No. Description Unit Measure Estimated Quantity Unit Price QUANTITY Total Price COMPLETED TOTAL COST COMPLETED 201 8" PVC Water Main (Outside Meridian Rd) L.F. 466 $ 24.00 S 11,184.00 466 $11,184.00 202 8" PVC Water Main (Within Meridian Rd) L.F. 24 S 35.00 S 840.00 24 $840.00 203 8" Gate Valves and Boxes EACH 1 $ 800.00 $ 800.00 1 $800.00 204 12"x12"x8" Tapping Sleeve & Valve LUMP SUM 1 $ 3,800.00 $ 3,800.00 100% $3,800.00 205 Fire Hydrant w/ Aux. Valves EACH 2 $ 2,200.00 $ 4,400.00 2 $4,400.00 Tees & Misc. Fittings EACH 6 5 250.00 $ 1,500.00 6 $1,500.001" Water Services EACH 7 $ 500.00 $ 3,500.00 7 $3,500.00 F07 Flushing Hydrant EACH 1 S 600.00 $ 600.00 1 $600.00 SUBTOTAL ITEMS 201 - 208 $ 26,624.00 $26,624.00 SEWER SYSTEM Item No. Description Unit Measure Estimated Quantity Unit Price Total Price QUANTITY COMPLETED TOTAL COST COMPLETED 301 8" PVC Sewer Main L.F. 503 $ 22.00 $ 11,066.00 503 $11,066.00 302 4" Services EACH 7 S 500.00 $ 3,500.00 7 $3,500.00 303 4' Diameter Manhole w/ Ring & Cover EACH 5 $ 900.00 $ 4,500.00 5 $4,500.00 304 Connect New Service to Exist. Service EACH 1 $ 500.00 $ 500.00 1 $500.00 SUBTOTAL ITEMS 301 - 304 1 $ 19,566.00 $19,566.00 STORMWATER DRAINAGE Item No. Description Unit Measure Estimated Quantity Unit Price Total Price QUANTITY COMPLETED TOTAL COST COMPLETED 401 8" PVC Storm Drain L.F. 92 $ 18.00 $ 1,656.00 92 $1,656.00 402 12" PVC Storm Drain L.F. 410 $ 22.00 $ 9,020.00 410 $9,020.00 403 Catch Basins w/ Frames & Grates EACH 4 S 600.00 S 2,400.00 4 $2,400.00 404 Connections to Existing SO Manholes EACH 2 $ 400.00 $ 800.00 2 $800.00 SUBTOTAL ITEMS 401 - 404 1 $ 13,876.00 $13,876.00 EXHIBIT "B" LEE'S MERIDIAN BUSINESS PARK LETTER OF CREDIT CERTIFICATION 12/05/00 1 OF 2 PAGES MISCELLANEOUS WORK COMPLETED TO DATE 5-Dec-00 Item No. Description Unit Measure Estimated Quantity Unit Price Total Price QUANTITY COMPLETED TOTAL COST COMPLETED 501 Topsoil (Boulevards) C.Y. 66 $ 20.00 $ 1,320.00 0 $0.00 502 Hydroseed S.F. 12,500 $ 0.20 $ 2,500.00 0 $0.00 503 Pavement Striping LUMP SUM 1 $ 850.00 $ 850.00 0% $0.00 504 Traffic Control LUMP SUM 1 $ 500.00 $ 500.00 100 o $500.00 505 Street Signs EACH 2 $ 300.00 $ 600.00 0 $0.00 506 Fencing Along South Prop. Line LU MP SUM 1 $ 5,400.00 $ 5,400.00 90% $4,860.00 SUBTOTAL ITEMS 501 - 506 $ 11,170.00 $5,360.00 UTILITIES Item No. Description Unit Measure Estimated Quantity Unit Price Total Price QUANTITY COMPLETED TOTAL COST COMPLETED 601 Utility Trench L.F. 675 $ 2.00 $ 1,350.00 675 $1,350.00 602 Furnish/Install 2" Conduit L.F. 2,020 $ 1.80 $ 3,636.00 2,020 $3,636.00 603 Furnish/Install 3" Conduit L.F. 1,350 $ 2.20 $ 2,970.00 1,350 $2,970.00 604 Three Phase Transformer Vault EACH 3 $ 300.00 $ 900.00 ' 4 $1,200.00 SUBTOTAL ITEMS 601-604 $ 8,856.00 $9,156.00 ENGINEERING, SURVEYING, UTILITY COMPANIES - PERMITS, FEES Item No. Description Unit Measure Estimated Quantity Unit Price Total Price QUANTITY COMPLETED TOTAL COST COMPLETED 701 Natural Gas (Montana Power Company) LUMP SUM 1 $ 6,500.00 $ 6,500.00 100% $6,500.00 702 Telephone (Centurytel) LUMP SUM 1 $ 7,321.00 $ 7,321.00 100% $7,321.00 703 Electrical (FEC) - Includes Street Lights LUMP SUM 1 $ 8,264.00 $ 8,264.00 100% $8,264.00 704 MDEQ Review Fee LUMP SUM 1 $ 700.00 $ 700.00 100% $700.00 705 FRDO Final Plat Fee LUMP SUM 1 $ 550.00 $ 550.00 100% $550.00 Design & Construction LUMP SUM 1 $ 11,900.00 S 11,900.00 90% $10,710.00 r07Engineering, Surveying, Legal & Construction LUMP SUM 1 $ 8,250.00 $ 8,260.00 100% $8,250.00 SUBTOTAL ITEMS 701 - 707 $ 43,485.00 1 $42,295.00 TOTAL PROJECT BUDGET TOTAL ESTIMATED COST OF CONSTRUCTION AMOUNT COMPLETED PRIOR TO BONDING AMOUNT OF REMAINING WORK AMOUNT OF BOND (125% OF REMAINING WORK) AMOUNT OF WORK COMPLETED TO DATE PERCENTAGE OF WORK COMPLETED TO DATE AMOUNT OF WORK REMAINING ORIGINAL BOND AMOUNT AMOUNT OF BOND TO BE RETAINED (125%, OF REMAINING WORK) BOND AMOUNT TO BE RELEASED AMOUNT PREVIOUSLY RELEASED AMOUNT TO BE RELEASED AT THIS TIME $ 181,641.00 1 1 $ 152,961.00 $ 181,641.00 S 152,961.00 $ 28,680.00 $ 35,850.00 $ 152,961.00 84% $ 28,680.00 $ 35,850.00 $ 35,850.00 5 - AS ENGINEER OF RECORD FOR LEE'S MERIDIAN BUSINESS PARK, I CERTIFY THAT THE WORK LISTED HEREIN IS CORRECT. IN ADDITION, I CERTIFY THAT THE ASSOCIATED COSTS ARE REASONABLY ACCURATE ESTIMATES OF THE RESPECTIVE COSTS OF THE WORK. THE VALUE OF CONSTRUCTION AND OTHER WORK COMPLETED TO DATE IS ESTIMATED TO BE ............... $ 162,961.00 THE TOTAL VALUE OF THE REMAINING WORK, SERVICES AND FEES IS ESTIMATED TO BE .................. $ 28,680.00 SECURITY HELD AT 125% OF THE REMAINING COSTS SHOULD BE IN THE AMOUNT OF ........................ $ 35,850.00 THEREFORE, IT IS IN ACCORDANCE WITH THE SUBDIVISION IMPROVEMENTS AGREEMENT TO REDUCE THE TOTAL AMOUNT OF THE j� Y ELD BY $ l �'A / 1\ N n *ALL IMPROVEMENTS SHALL BE COMPLETED BY MAY 1, 2001 EXHIBIT "B" LEE'S MERIDIAN BUSINESS PARK LETTER OF CREDIT CERTIFICATION 12/05/00 2 OF 2 PAGES ;;Z001009 140 (90 RESOLUTION NO. 4553 A RESOLUTION CONDITIONALLY APPROVING THE PRELIMINARY PLAT OF LEE'S MERIDIAN BUSINESS PARK, LOCATED ON THE WEST SIDE OF MERIDIAN ROAD, AND MORE PARTICULARLY DESCRIBED ON EXHIBIT "A". WHEREAS, Gwenn Lee, the owner o above, has petitioned Plat'of said property, f certain real property described for approval of the Subdivision and WHEREAS, the Kalispell City -County Planning Board and Zoning Commission held a public hearing on April 11, 2000, on the proposal and reviewed Subdivision Report #KPP-00-3 issued by the Flathead Regional Development Office, and WHEREAS, the Kalispell City -County Planning Board and Zoning Commission -has recommended approval of the Preliminary Plat of Lee's Meridian Business Park, subject to certain conditions and recommendations, and WHEREAS, the City Council. of the City of Kalispell at its regular Council Meeting of May 1, 2000, reviewed the FRDO Report #KPP-00-3, reviewed the recommendations of the Kalispell City -County Planning Board and Zoning Commission, and found from the Preliminary Plat, and evidence, that the subdivision.is in the public interest. NOW THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF KALISPELL, MONTANA AS FOLLOWS: SECTION I. That the Findings of Fact contained in Flathead Regional Development Office Report #KPP-00-3 are hereby adopted as the Findings of Fact of the City Council. SECTION II. That the application of Gwenn Lee -for approval of the Preliminary Plat of Lee's Meridian Business Park, Kalispell, Flathead County, Montana is hereby approved subject to the following conditions: 1. The subdivision shall be in compliance with the preliminary plat, which shall govern the general location of the lots, roadways and improvements. 2. The developer shall obtain a Certificate of Subdivision Approval from the Montana Department of Environmental Quality and obtain a letter from the Kalispell Public Works Department, which states that the water and sewer i facilities have been reviewed and approved for compliance with the City of Kalispell's Design and Construction Standards. 3. The internal roadway shall be designed and constructed.in accordance with the City of Kalispell's Design and Construction Standards and that a letter shall be obtained from the Kalispell Public Works Department verifying their construction. 4. A five foot sidewalk shall be installed along the west side of Meridian Road that connects to the pedestrian path proposed to the north of the subdivision and crosses the railroad right-of-way in accordance with a plan approved by the Kalispell Parks and Recreation Department. 5. An engineered storm water management plan shall be designed in accordance with the Kalispell Design and Construction Standards and shall be reviewed and approved by the Kalispell Public Works Department prior to -final plat approval. G. A traffic analysis shall be submitted to the Kalispell Public Works Department concurrently with the utility submitted which uses a model based on the most intensive uses of the property which might be allowed under the commercial zoning and that alternatives for mitigation of the potential traffic impacts be identified. 7. A letter shall be obtained from the Kalispell Fire Department approving the fire access and suppression system for compliance with the Uniform Fire Code. 8. The- alignment of the new internal roadway with Center Street shall be reviewed and approved by the Kalispell Public Works Department. 9. All new utilities for the subdivision shall be placed underground. 10. An additional ten (10) feet of right-of-way along Meridian Road shall be indicated on the final plat. 11. A sixty (60) foot right-of-way easement between Lots 5 and 6 shall be indicated on the final plat for future roadway extension. i 12. A "No access to railroad" strip shall be indicated on the final plat along Lots 1 through 5. 13: A buffer shall be provided along the southern boundary of the subdivision which complies with the Kalispell Zoning Ordinance, i.e., a six-foot site obscuring fence or coniferous hedge. SECTION III. This Preliminary Plat approval shall be valid for a period of three '(3) years from the date of approval. SECTION IV. Upon proper review and filing of the Final Plat of said subdivision in the office of the Flathead County Clerk and Recorder, said premises shall be a subdivision of the City of Kalispell. PASSED -AND APPROVED BY THE CITY COUNCIL AND SIGNED BY THE MAYOR OF THE CITY OF KALISPELL, THIS 15TH DAY OF MAY, 2000. Wm. E. Boharski Mayor ATTEST: T eresa White City Clerk EXHIBIT A LEGAL DESCIRPTION Gwenn Lee / Lee's Meridian Business Park - Annexation and Initial -Zoning DESCRIPTION: A TRACT OF LAND, SITUATED, LYING, AND BEING -IN NORTHEAST QUARTER OF THE NORTHEAST QUARTER OF SECTION 13, TOWNSHIP 28 NORTH, RANGE 22 WEST, P.X.,M., FLATHEAD COUNTY, MONTANA, AND MORE PARTICULARLY DESCRIBED AS FOLLOWS TO WIT: Commencing at the northeast corner of the Northeast Quarter of Section 13, Township 28 North, Range 22 West, P.M., M., Flathead .County, Montana; Thence along the east boundary of said -NE1/4 S01*09146`T'W 158.72 feet; Thence N88050114"W 50.00 feet to the westerly R/W .of Meridian Road, which is THE TRUE: POINT OF BEGINNING OF THE TRACT OF LAND HERRIN DESCRIBED: Thence along said R/W S01*09146"W 329.09 feet; Thence leaving said R/W N89a35141"W 720.67 feet the southerly R/W of Burlington Northern Railroad, which point is on a 713.94 foot radius curve, concave southeasterly, (radial bearing S50*2410511E); Thence northeasterly along said R/W and along said curve through a central angle of 36&33116" an arc length of 455.49 feet; Thence N76*09111"E 358.51 feet to the point of beginning and containing 3.548 ACRES; Subject to and together with all appurtenant easements of record. STATE OF MONTANA, ss County of Flathead Recorddeedd+ at the request of L/e l this ( day of 20,01 at o'clock/9M and recorded in the records of Flat ea d County, Stat of Montana. Fee $ ✓ Pd. %„ t (Flathead County Clerk and Reco r) RECEPTION NO. /t}�' _ RETURN TO S®t µ //�� (Deputy) EXHIBIT "B" CERTIFICATION OF WORK TO BE COMPLETED LEE'S MERIDIAN BUSINESS PARK SUBDIVISION ROAD COMPLETED TO DATE 5-Dec-00 Item No. Description Unit Measure Estimated Quantity Unit Price Total Price QUANTITY COMPLETED TOTAL COST COMPLETED 101 Unclassified Excavation C.Y. 2,050 $ 1.80 $ 3,690.00 2,050 $3,690.00 102 Select Sub -Base, 3" (-) Pit Run Gravel LUMP SUM 1 $ 8,000.00 $ 8,000.00 100% $8,000.00 103 Crushed Base, 3/4" Crushed Gravel S.F. 22,000 $ 0.14 $ 3,080.00 22,000 $3,080.00 104 Hot Plant Mix As halt (4" - Two Lifts) S.F. 18,880 $ 0.75 $ 14,160.00 18,880 $14,160.00 105 Curb and Gutter L.F. 1,022 $ 7.00 $ 7,154.00 1,022 $7,154.00 106 Valley Gutters w/ Aprons S.F. 320 $ 4.00 $ 1,280.00 0 $0.00 107 Sidewalk (5' Wide) w/ Prepared Base S.F. 6,900 $ 3.00 $ 20,700.00 0 1 $0.00 SUBTOTAL ITEMS 101-107 $ 58,064.001 $36,084.00 WATER SYSTEM Item No. Description Unit Measure Estimated Quantity Unit Price Total Price QUANTITY COMPLETED TOTAL COST COMPLETED 201 8" PVC Water Main (Outside Meridian Rd) L.F. 466 $ 24.00 $ 11,184.00 466 $11,184.00 202 8" PVC Water Main (Within Meridian Rd) L.F. 24 $ 35.00 $ 840.00 24 $840.00 203 8" Gate Valves and Boxes EACH 1 $ 800.00 $ 800.00 1 $800.00 204 12"x12"x8" Tapping Sleeve & Valve LUMP SUM 1 $ 3,800.00 $ 3,800.00 100% $3,800.00 205 Fire H drant w/ Aux. Valves EACH 2 $ 2,200.00 $ 4,400.00 2 $4,400.00 206 Tees & Misc. Fittings EACH 6 $ 250.00 $ 1,500.00 6 $1,500.00 207 1" Water Services EACH 7 $ 500.00 $ 3,500.00 7 $3,500.00 208 Flushing Hydrant EACH 1 $ 600.00 $ 600.00 1 $600.00 SUBTOTAL ITEMS 201 - 208 $ 26,624.00 $26,624.00 SEWER SYSTEM Item No. Description Unit Measure Estimated Quantity Unit Price Total Price QUANTITY COMPLETED TOTAL COST COMPLETED 301 8" PVC Sewer Main L.F. 503 $ 22.00 $ 11,066.00 503 $11,066.00 302 4" Services EACH 7 $ 500.00 $ 3,500.00 7 $3,500.00 303 4' Diameter Manhole w/ Ring & Cover EACH 5 $ 900.00 $ 4,500.00 5 $4,500.00 304 Connect New Service to Exist. Service EACH 1 $ 500.00 $ 500.00 1 $500.00 SUBTOTAL ITEMS 301 - 304 $ 19,566.00 $19,566.00 STORMWATER DRAINAGE Item No. Description Unit Measure Estimated Quantity Unit Price Total Price QUANTITY COMPLETED TOTAL COST COMPLETED 401 8" PVC Storm Drain L.F. 92 $ 18.00 $ 1,656.00 92 $1,656.00 402 12" PVC Storm Drain L.F. 410 $ 22.00 $ 9,020.00 410 $9,020.00 403 Catch Basins w/ Frames & Grates EACH 4 $ 600.00 $ 2,400.00 4 $2,400.00 404 Connections to Existing SO Manholes EACH 2 $ 400.00 $ 800.00 2 $800.00 SUBTOTAL ITEMS 401 - 404 1 1 1 $ 13,876.001 $13,876.00 EXHIBIT "B" LEE'S MERIDIAN BUSINESS PARK LETTER OF CREDIT CERTIFICATION 12/05/00 1 OF 2 PAGES MISCELLANEOUS WORK COMPLETED TO DATE 5-Dec-00 Item No. Description Unit Measure Estimated Quantity Unit Price Total Price QUANTITY COMPLETED TOTAL COST COMPLETED 501 Topsoil (Boulevards) C.Y. 66 $ 20.00 S 1,320.00 0 $0.00 502 H droseed S.F. 12,500 S 0.20 S 2,500.00 0 $0.00 503 Pavement Striping LUMP SUM 1 S 850.00 S 850.00 0% $0.00 504 Traffic Control LUMP SUM 1 S 500.00 S 500.00 100% $500.00 505 Street Signs EACH 2 S 300.00 $ 600.00 0 $0.00 506 Fencing Along South Prop. Line LUMP SUM 1 5 5,400.00 $ 5,400.00 90% $4,860,00 SUBTOTAL ITEMS 501 - 506 $ 11,170.00 $5,360.00 UTILITIES Item No. Description Unit Measure Estimated Quantity Unit Price QUANTITY Total Price COMPLETED TOTAL COST COMPLETED 601 Utility Trench L.F. 675 $ 2.00 $ 1,350.00 675 $1,350.00 602 Furnish/Install 2" Conduit L.F. 2,020 $ 1.80 $ 3,636.00 2,020 $3,636.00 603 Furnish/Install 3" Conduit L.F. 1,350 $ 2.20 $ 2,970.00 1,350 $2,970.00 604 Three Phase Transformer Vault EACH 3 $ 300.00 $ 900.00 4 $1,200.00 SUBTOTAL ITEMS 601-604 $ 8,856.00 $9,156.00 ENGINEERING, SURVEYING, UTILITY COMPANIES - PERMITS, FEES Item No. Description Unit Measure Estimated Quantity Unit Price QUANTITY Total Price COMPLETED TOTAL COST COMPLETED 701 Natural Gas (Montana Power Company) LUMP SUM 1 $ 6,500.00 $ 6,500.00 100% $6,500.00 702 Telephone (Centur el) LUMP SUM 1 $ 7,321.00 S 7,321.00 100% $7,321.00 703 Electrical (FEC) - Includes Street Lights LUMP SUM 1 $ 8,264.00 S 8,264.00 100% $8,264.00 704 MDEQ Review Fee LUMP SUM 1 $ 700.00 5 700.00 100% $700.00 705 FRDO Final Plat Fee LUMP SUM 1 $ 550.00 S 550.00 100% $550.00 706 lEngineering, Design & Construction LUMP SUM 1 S 11,900.00 $ 11,900.00 90% $10,710.00 707 ISurveying, Legal & Construction LUMP SUM 1 $ 8,250.00 $ 8,250.00 100% 1 $8,250.00 SUBTOTAL ITEMS 701 - 707 $ 43,485.00 $42,295.00 TOTAL PROJECT BUDGET TOTAL ESTIMATED COST OF CONSTRUCTION AMOUNT COMPLETED PRIOR TO BONDING AMOUNT OF REMAINING WORK AMOUNT OF BOND (125% OF REMAINING WORK) AMOUNT OF WORK COMPLETED TO DATE PERCENTAGE OF WORK COMPLETED TO DATE AMOUNT OF WORK REMAINING ORIGINAL BOND AMOUNT AMOUNT OF BOND TO BE RETAINED (125 % OF REMAINING WORK) BOND AMOUNT TO BE RELEASED AMOUNT PREVIOUSLY RELEASED AMOUNT TO BE RELEASED AT THIS TIME $ 181,641.00 $ 152,961.00 S 181,641.00 $ 152,961.00 $ 28,680.00 $ 35,850.00 $ 152,961.00 84% S 28,680.00 S 35,850.00 $ 35,850.00 S - AS ENGINEER OF RECORD FOR LEE'S MERIDIAN BUSINESS PARK, 1 CERTIFY THAT THE WORK LISTED HEREIN IS CORRECT. IN ADDITION, I CERTIFY THAT THE ASSOCIATED COSTS ARE REASONABLY ACCURATE ESTIMATES OF THE RESPECTIVE COSTS OF THE WORK. THE VALUE OF CONSTRUCTION AND OTHER WORK COMPLETED TO DATE IS ESTIMATED TO BE ............... $ 152,961.00 THE TOTAL VALUE OF THE REMAINING WORK, SERVICES AND FEES IS ESTIMATED TO BE .................. $ 28,680.00 SECURITY HELD AT 125 % OF THE REMAINING COSTS SHOULD BE IN THE AMOUNT OF ........................ $ 35,850.00 THEREFORE, IT IS IN ACCORDANCE WITH THE SUBDIVISION IMPROVEMENTS AGREEMENT TO REDUCE THE TOTAL AMOUNT OF THE Y ELD BY $ p IOTA THOMAS M. COWAN P.E *ALL IMPROVEMENTS SHALL BE COMPLETED BY MAY 1, 2001 THO AS M. � COWAN C') EXHIBIT "B" 32' 141 10 LEE'S MERIDIAN BUSINESS PARK LETTER OF CREDIT CERTIFICATION N/ 12/05/00 2 OF 2 PAGES � OF S 5\off