Resolution 4257 - Change Order - South Woodland Phase It-2 7
3
IRESOLUTION NO. 4257
I
I
A RESOLUTION TO ALTER AND AMEND THE PLANS AND SPECIFICATIONS OF
CONTRACT WITH A-1 PAVING ON THE WOODLAND COURT PROJECT.
WHEREAS,, the City did, on November 15, 1995 enter into a
contract with A-1 Paving of 3131 Highway 2 East, Kalispell, Montana
for Installation of utilities in accordance with the Woodland Court
Project; and
WHEREAS, upon the advice and recommendation of Thomas, Dean &
Hoskins, Inc., who is the City's consultant and engineer on said
project, certain changes and alterations of design and
specifications have been found necessary and advisable and in the
best interests of the City; and said changes and alterations could
not have been necessarily foreseeable when the original design and
specifications were prepared on this phase of the installation of
utilities on the Woodland Court Project, and said changes are
contained in Exhibit "A", attached hereto and are by this reference
made a part hereof; and
WHEREAS, it appears in the best interests of the City to
approve said changes and alterations,
NOW THEREFORE, pursuant to the provisions of Section 7-5-
4308(l) MCA be it hereby resolved:
1. The alterations and modifications of the specifications
and plans of the contract between the City of Kalispell and A-1
Paving, dated February 5, 1996, as set out in Exhibit "All, attached
hereto, are hereby approved, and
2. As soon as the price to be paid for said alterations and
modifications are agreed to _1n writing, signed by the contractor,
as hereby approved by the Council, this approval thereof shall be
in effect.
PASSED AND APPROVED BY CITY COUNCIL AND MAYOR OF THE CITY OF
KALISPELL THIS DAY OF 1996.
ATTEST:
a�4�Affld, mc--
Debbie G 0, CMC
Clerk of'gorncil
Rauthe, mayor
A
1-:272
V
EXHIBIT "A"
CFLANGE ORDER
ORDER NO. 1
DATE 2
------- 15-1-96
AGREEMENT DATE: 11115195 -
NAME OF PROJ
"WOODLAND COURT PROJECT' MT HOME M94-SG300117/MT-CDBG-94HR-06
OWN
CONTRACTOR A-1 PAVING
The following changes are hereby made to the CONTRACT DOCUMENTS:
Add utility trench construction (electrical, telephone, television) to Schedule III Contract, based on
unit prices as shown on Exhibit A.
Change to CONTRACT PRICE:
Original CONTRACT PRICE: $80,056.00
Current CONTRACT PRICE adjusted by previous CHANGE ORDER:$ 80,056.00
The CONTRACT PRICE due to this CHANGE ORDER "I increase: $ 22,809.50
The new CONTRACT PRICE including this CHANGE ORDER will be $ 101865.500
CHANGE of CONTRACT TIME:
The CONTRACT TIME wfll increase by 12 dW
The date for completion of all work will be 42 days after the I st day g� Schedule III contract time.
Requested By:
Recommended By:
Accepted By:
e Mohl, A-1 Paving
ew---
Phillips, P.E., Thomas, Dean & Hoskins, Inc.
Al Thelen, Interim City Manager, City of Kalispell
I
I
7,
1273
a
Woodland Court Project
K94-46-4
31 —Jan-96
Schedule III
Contractor: A-1 Paving
Change Order No. I
EXHIBIT A
Utility trench construction, conduit, pull ropes, bases
UNIT
ITEM EST OTY UNIT PRICE AMOUNT
1. Electric Utility Trench 1850 LF $3,50 $6,475.00
2. Conduft 2 2000 LF $2.45 $4,900.00
a 1950 LF $3.45 $6,727.50
3. Pull Rope included in ftem 3.
4. Set transformer Bases 3 EA $650.00 $1,950.00
5. Sweeps
3" long radius 30 EA $78.00 $2,340.00
2" long radius 3 EA $139.00 $417.00
TOTAL $22,809.50
col exha.wkl